Biogas for starch processing plants

A starch plant produces large volumes of wastewater with a high organic load. This is not a feedstock you buy but a stream you must treat anyway. The owner decides whether anaerobic treatment is cheaper than the existing aerobic one, and what to burn the gas in.

The model treats this stream as a wastewater case, measured by COD and flow, not as invented solid feedstock. The gas can replace fuel in the dryer or boiler. The result depends on how steady the flow is and on the campaign of the raw material.

What drives payback

COD load and flow

The tonnes of COD removed set the gas. A dilute or irregular stream gives little.

Treatment cost saved

Anaerobic treatment needs less energy than aeration. This saving is counted next to the gas.

Gas use

Biogas burned in a boiler or dryer gives the highest value; power only helps if you cannot use the heat.

Campaign season

Raw-material harvest may last a few months. A reactor with idle months has a longer payback.

What it takes to work

  • Measured COD and flow, not an estimate
  • A fuel consumer for the gas on site
  • A raw-material season long enough to keep the reactor running

Frequently asked questions

What data do you need?

Flow in m³ a day and COD in mg per litre (or kg a day). Without a measurement the verdict stays preliminary.

Does it replace my existing treatment?

It is a first stage; the water still needs finishing before discharge according to local limits.

Where does the sludge go?

Excess sludge from the reactor is a small stream. It is counted in the mass balance.