Sample report · Thailand

Starch mills: cassava, maize and cereals · Industrial wastewater

A sample Extended Report for a modelled project. Your report has the same structure (the Standard Report has fewer sections) and uses your own data.

Business situation

Historical Thai cassava-starch wastewater reference. Published flow, COD, removal and methane fraction are separated from modelling assumptions. Installed costs and auxiliary loads are not disclosed: the economics use the model's reactor-cost estimate (engineering judgement, LOW), so the result can never be rated strong and is not an investment case.

Operating assumptions

  • Operating days: 330 d/a
  • Active months: 12 1–12
  • Starting month: 1 1–12
  • Scenario uncertainty: 50 %
  • Methane capture: 95 % CH₄
  • Removed COD to biomass: 8 % COD
  • Sludge dry solids: 5 % TS
  • VS / TS: 80 % VS/TS
  • Heat recovery: 0 %
  • Avoided treatment charge: 0 THB/m³
  • Q: 6,560 m³/d
  • COD: 12,200 mg COD/L
  • COD removal: 92 % COD
  • CH₄: 55 % vol
  • HRT: 25.3 d
  • OLR: 0.48 kg/(m³·d)
  • Inlet temperature: 28 °C
  • Electricity: — · Electricity price on your bill (if known): —
  • All year: hot water, steam, process
  • Land available for spreading digestate: — · Distance to the gas grid (for biomethane): —
  • Grid connection? Yes

What to verify

The source states HRT 15 days, yet 165,970 m³ divided by 6,560 m³/day is 25.3 days. Confirm working volume and operating flow; do not calibrate to incompatible values. Obtain gas normalisation conditions and current costs.

Reference data: Lerdlattaporn et al. — cassava starch circular economy, 2021

TH · 2021 · Source checked: 2026-10-29

ParameterValueType
Q6,560 m³/dReported
COD12,200 mg/LReported
COD removal92 %Reported
CH₄55 % volReported
V165,970 m³Reported
Biogas41,000 m³/dReported
HRT15 dReported
Source

Possible with conditions

It can pay off, but only if the key conditions hold — confirm them in a feasibility study.

  • Base NPV positive (US$2.5M), payback ≈ 7.8 yrs.
  • Conservative-case NPV is negative (-US$9.9M) — sensitive to key assumptions.
  • Data confidence is low — the verdict is preliminary.

Largest benefit — “surplus electricity sold”: ≈ 100 % of all revenue and savings.

What would change the verdict
  • → Verify the inlet analysis and operating history, seasonal availability, and a supplier guarantee for the proposed treatment train.
  • → Confirm complete installed-cost quotations, residuals disposal, final effluent treatment and the energy offtake contract. Check the downside case before investment.
  • → Obtain site-specific permits and grid gas-quality requirements; extend this pre-tax screening to tax, working capital and lender cash-flow modelling.

Subsidies and tariffs excluded from the verdict. Preliminary screening, not an engineering design.

How firm is this answer?

Grey zone: the answer flips between the conservative and the optimistic case. Before paying for a feasibility study, check these first:

NPV: conservative -US$9.9M · base US$2.5M · optimistic US$7M

  1. Energy prices −20 % (-US$3.8M)
  2. Feedstock potential −20 % (-US$3.3M)
  3. CH₄ −20 % (-US$3.3M)

These are screening assumptions, not independently validated accuracy limits. Confirm BMP, supplier scope, grid connection and offtake terms before an investment decision.

To reach a bankable estimate (±15 %)
  1. Laboratory methane-potential (BMP) test of 2–3 feedstock samples — ≈ US$336–US$895 each
  2. 2–3 supplier quotes for the plant
  3. Grid or gas-network connection conditions from the operator
  4. Letters of intent for feedstock supply and for heat, power or biomethane offtake
  5. Then a feasibility study with permits and financing (±15 %)
From screening to construction

Key figures

Ranges: conservative — base — optimistic. We don't show fake precision.

Economics

Preliminary investment
US$9.8M – US$12M
≈ THB 350M (base)
Payback
5.6 yr – > 25 yr
base: 7.8 yr · no subsidies
NPV (base)
US$2.5M
range: -US$9.9M … US$7M
Chosen route
CHP (power + heat)
Confidence: Low

1 EUR = 1.1193 USD · ECB · 2026-11-09

Feedstock and energy

Industrial wastewater
6,560 m³/d
COD: 12,200 mg COD/L
Biogas
6.1M – 14M Nm³/yr
≈ 1,683 Nm³/h (base)
Net energy
12,000 – 32,000 MWh/yr
useful heat: 0 MWh
Candidate capacity
4,400 kWe
large (1–5 MW)

How far you can rely on these numbers

Low · 44/100
  • Backed by your data and our sources44
  • You can still add+46
  • Needs a feasibility study (lab, quotes, contracts)10

44/100: how much of what a screening can know about this project rests on your data and current sources. A missing input costs points in proportion to how far it could still move your result.

What you can add

  • Biggest gainHeat needed per year (if known) (kWh)Large effectFuel bills for one year: gas m³ or kWh of heat+14
  • Annual electricity consumption — savings from self-consumption cannot be counted without it (kWh)Large effectAdd up the kWh on your last 12 electricity bills+12
  • Route-specific CAPEX lacks independent local validation — obtain comparable supplier quotations+8
  • At least one price affecting this route relies on an unconfirmed market proxy or uncontracted offtake — confirm the applicable tariff or buyer contract+6
  • Electricity price on your bill (if known) (THB/kWh)Large effectTotal of one bill divided by the kWh on it+6

With all of it: up to 90/100

High requires verified laboratory and project documents, so a screening stops at 90/100.

Cost fields left blank are estimated from the reactor volume (UASB/EGSB or covered lagoon) at a unit cost set by engineering judgement, because no dated public cost curve exists for these reactors, plus a maintenance share, own power use and the surplus-digestate price for the sludge. Pretreatment, aerobic polishing and discharge are not included. Without your reactor budget the result cannot reach the top verdict. Each figure you enter replaces its estimate.

  • CAPEX
  • OPEX
  • Residuals disposal cost
  • Upstream electricity use
  • Additional process heat
Model warnings
  • Upstream budgets must include pretreatment, logistics, storage and final treatment; they are not independently verified installed quotations.
  • BMP/COD and retention time alone do not verify salinity, ammonia inhibition, toxic contaminants or treatment stability; confirm with representative analysis and continuous pilot/vendor data.
  • Cassava (tapioca) starch: wastewater and pulp can hold up to ≈ 200 mg/L cyanide, which inhibits methane-forming bacteria; reactors adapted over months have degraded it, but recovery was seen only below ≈ 10 mg/L in the reactor. The model does not check cyanide: measure total cyanide in the raw wastewater and plan a slow start-up with the reactor supplier. Not relevant for potato, wheat or maize starch.
  • CHP performance uses a 50 Hz biogas full-load catalogue reference (03/2025), interpolated between ratings; part-load and ambient derating require supplier confirmation.
  • CHP rating is outside the 20–2,300 kW reference curve; endpoint efficiency is only a proxy. Obtain a multi-engine or equipment-specific design.
  • Market data require review (econ.electricity_spot_eur_kwh). Observation dates and validity are shown in the evidence; these are not verified current customer quotations.
Country conditions
  • POME covered lagoons at palm-oil mills are the standard industrial application.

Action plan: what would make it stronger

Changes tested on this project with the same model. Break-even values show how far each must go; the scenario assumptions are LOW-confidence judgements to replace with offers.

What separates this project from “Strong candidate”
  • Payback in the base case is 7.8 yr; it needs to be 6.5 yr or less.
  • The conservative case must stay profitable too (its NPV is -US$9.9M).
  • Data confidence is low (44/100): see “What you can add”.
ChangeVerdictNPV (base)Δ NPVBreak-even
Sell the spare heat
A year-round heat buyer (drying, process heat, greenhouse or district heating) for ≈ 23,000 MWh a year, valued at ≈ THB 1.5 per kWh.
Possible with conditionsUS$13M+US$10Mpays even with free heat
Order of action
  1. 1Find a heat buyer for ≈ 23,000 MWh a year (pays even with free heat).
  2. 2Ask 3–5 suppliers for quotes: the project breaks even up to an investment of US$12M. →

Break-even prices

Each value on its own brings the base-case NPV to zero; everything else stays as calculated.

Electricity value at NPV = 0
US$0.058/kWh
now US$0.0665/kWh
Highest installed cost at NPV = 0
US$12M
now US$10M

What could break the economics

Each stress test applied to the base case on its own.

Change in NPV vs base, USD (base: 2.5M)

  1. Energy prices −20 %-3.8M
  2. Feedstock potential −20 %-3.3M
  3. CH₄ −20 %-3.3M
  4. CAPEX +20 %-2.5M
  5. OPEX +30 %-1.7M
  6. Maintenance +30 %-1M
  7. CHP downtime +10 pp-710K
  8. Useful heat (economic) −50 %0
NPV = 0 if CAPEX falls by
already positive
grant, leasing, cheaper equipment
NPV = 0 if energy prices rise by
already positive
relative to the base case

Flip the NPV sign: Energy prices −20 %; Feedstock potential −20 %; CH₄ −20 %; CAPEX +20 %.

Scenarios

Route: CHP (power + heat). Scenarios bundle consistent assumptions (lower yield comes with higher CAPEX).

Revenue + savings / yrUS$1.9M
  • Electricity sales1.9M
OPEX / yrUS$610K
  • CHP service and overhaul reserve270K
  • Residuals disposal cost120K
  • OPEX87K
  • Insurance52K
Operating margin (EBITDA)US$1.3M
ScenariosConservativeBaseOptimistic
Biogas, 1 000 Nm³/yr6,058.313,462.814,487.1
CAPEXUS$12MUS$10MUS$9.8M
OPEX / yrUS$460KUS$610KUS$610K
Revenue + savings / yrUS$660KUS$1.9MUS$2.3M
Operating margin (EBITDA)US$200KUS$1.3MUS$1.7M
Simple payback> 25 yr7.8 yr5.6 yr
Discounted paybackno payback11.2 yr7.5 yr
NPV-US$9.9MUS$2.5MUS$7M
IRR-13.2 %10.5 %16.4 %
DSCR (min)0.21.52

Pre-tax, nominal USD, 15-year horizon, discount rate of the country or your own; a screening estimate, not a bankable feasibility study. DSCR = EBITDA ÷ debt service at 50 % debt (no taxes).

Cumulative cash flow, USD
-13M-4.8M3.8M12M21M03691215yearsConservativeBaseOptimistic

Biogas use routes compared

Base case. The model picks the route with the best NPV among technically sensible ones.

RouteCAPEXEBITDA / yrPaybackNPV (base)NPV low…high
CHP (power + heat) chosenUS$10MUS$1.3M7.8 yrUS$2.5M-US$9.9M … US$7M
Boiler (heat only) US$6.7M-US$570Kno payback-US$13M-US$13M … -US$12M
Biomethane US$11MUS$1.4M7.8 yrUS$1.9M-US$17M … US$19M
  • CHP pays when you use the power yourself and the heat is really used.
  • Biomethane: raw biogas ≈ 1,658 Nm³/h. The smallest upgrading units take ≈ 50–100 Nm³/h, and the cost per Nm³ falls steeply with size, so a small plant pays much more for each unit of gas.

National support schemes — separate cases

Not in the verdict: tariffs get cut, auctions fail, grant calls close. Status and source shown for each.

Bottom line

No support scheme is open for your project right now

The verdict rests on market prices only, so it does not change. Closed or unconfirmed schemes, if any, are listed below for reference.

Country overviewchecked 30 Oct 2026

The biogas feed-in tariff (2.07 THB/kWh) awarded no biogas projects in the 2022 round and no new round is open; industrial biogas runs on self-use.

Closed schemes (1)

Intake has ended. Shown for reference only.

VSPP/SPP biogas FiT 2022–2030

Closed
Electricity tariff
For reference
NPV change
-US$3.4M
NPV with support
-US$970K
Payback
8.7 yr
IRR
5.7 %

Reference figures: intake is closed.

Conditions
  • met: CHP of a practical size, from 25 kW (project ≈ 4,370 kW)
  • no data: Gas-source category accepted by the scheme
What the case uses
  • Route: CHP (power + heat)
  • Tariff: US$0.0616/kWh
Scheme terms

2.0724 THB/kWh (+0.50 in southern border provinces); shown for reference — no open round.

Next step: Do not plan on it. Watch the operator's announcements for a successor scheme.

Source: ERC 2022 RE FiT procurement regulation · checked 30 Oct 2026 · Data confidence: Medium

Support never changes the verdict. Each case is pre-tax, uses the scheme's published terms and assumes the support is awarded; it does not confirm eligibility or promise funding.

Where the energy goes

Heat produced ≠ useful heat. Heat without a user isn't income.

40/100

Of every 100 kWh of energy in the methane, 40 become a product that earns money or replaces a purchase.

100 % = 74,000 MWh of methane energy a year (LHV), base case. Every figure in this block is calculated by the model from your inputs.

Stream by stream

Calculated

Earns money

  • Electricity sold to the grid29,000 MWh 40 %

Runs the plant

  • Plant’s own electricity2,300 MWh 3 %

Produced, not used

  • Heat with no buyer29,000 MWh 39 %

Losses

  • Conversion losses (engine, boiler)12,000 MWh 16 %
  • Methane leaks1,100 MWh 2 %

What this means for the project

  • Heat brings no income in this result: a heat need is named, but its amount is not entered. Enter the annual heat or gas use to count it.
  • 29,000 MWh of heat a year has no buyer. A heat user nearby (drying, a greenhouse, process heat, a heating network) would turn it into income.
  • Methane leaks are 2 % of production in the base case: lost income and a greenhouse gas. Gas-tight digestate storage and regular leak checks keep them low.

What the figures rest on

Engine efficiency: electricity / heat
43 % / 43 %Assumption
Heat need
named, amount not enteredNot entered
Site electricity use
—Not entered
Methane leaks, base case
2 %Assumption
Main product, conservative – optimistic
12,000 – 32,000 MWhCalculated

How it works: from feedstock to products

Heat produced (gross)
29,034 MWh
Digester heat demand
0 MWh
Useful heat (economic)
0 MWh of 29,034
Power: own use / sold
0 / 29,232 MWh

Scores by dimension

No single magic number. The overall score comes with its explanation.

Feedstock fit
100/100
  • Energy equivalent ≈ 4370 kWe (scale score 100/100)
  • Process-specific inlet basis; no generic feedstock energy-density score.
  • Feedstock available 12 of 12 months
Energy fit
30/100
  • Own consumption absorbs 0 % of the electricity produced
  • Useful heat 0 MWh of 29034 MWh available after digester needs
  • Electricity consumption not given
  • Heat consumption not given
Location & logistics
100/100
  • Land for digestate unknown
Technical feasibility
100/100
  • Standard layout for this scale, no critical obstacles
Economics
67/100
  • Base-case simple payback ≈ 7.8 years
Regulatory complexity
27/100 risk
  • Number and weight of permitting / regulatory steps: 11 points (more = harder)
Environmental risk
24/100 risk
  • Expected methane loss 2.5 % (good practice ≤ 2 %)
  • Unknown where the digestate will go
Overall project viability
76/100
  • Weighted: economics 30 %, feedstock 20 %, energy 15 %, technical 10 %, location 10 %, regulatory 7.5 %, environment 7.5 %.
  • Strongest: Feedstock fit (100); weakest: Energy fit (30).

Calculation details

Industrial wastewater

Leave unknown costs and auxiliary loads blank. Economics require these inputs.

COD in
26,410,600 kg COD/a
COD out
2,112,840 kg COD/a
COD → X
1,943,820 kg COD/a
COD → CH₄
22,353,900 kg COD/a
m sludge (wet)
34,222.1 t/a
m in
2,164,800 t/a
m gas
18,196 t/a
m out
2,112,380 t/a
V
165,970 m³
HRT
25.3003 d
OLR
0.482208 kg COD/m³/d
COD out
1,000.22 mg COD/L
CH₄ → CHP / Upgrading / Boiler
7,404,530 Nm³ CH₄/a
CH₄ loss
389,712 Nm³ CH₄/a
CH₄ total
7,794,250 Nm³ CH₄/a
m residual
34,222.1 t/a

Enter the project budget for the upstream process, including pretreatment, logistics, storage and final treatment. Gas conversion equipment and energy are calculated separately. Enter zero only for a confirmed zero cost. Exclude from this budget; calculated separately: residuals disposal cost, biogas purchase price.

Technology & digester

COD / Covered lagoon

Working volume
≈ 170,000 m³
Retention time
25.3 days

    Climate: Northeast (Khon Kaen), mean 27.8 °C, ≈ 0 heating degree-days. Closest climate analogues: Dresden (DE, east) (Δ 18.5 °C), Prague (CZ) (Δ 18.8 °C), Copenhagen (DK) (Δ 19 °C).

    Monthly energy balance

    Base case, chosen route. Gas energy is usable methane energy (LHV) after losses.

    MonthFeedstock, tGas energy, MWhDigester heat, MWhUseful heat, MWhNet electricity, MWh
    Jan183,7346,172002,481
    Feb167,4355,624002,261
    Mar183,7346,172002,481
    Apr177,8075,973002,401
    May183,7346,172002,481
    Jun177,8075,973002,401
    Jul183,7346,172002,481
    Aug183,7346,172002,481
    Sept177,8075,973002,401
    Oct183,7346,172002,481
    Nov177,8075,973002,401
    Dec183,7346,172002,481
    Σ2,164,80072,7160029,232
    CAPEX, OPEX, revenue (base case)
    CAPEX (USD)
    Industrial wastewater4.3M
    Gas handling and cleaning200K
    CHP (power + heat)3.6M
    Heat network400K
    Electrical systems and controls250K
    Pipework170K
    Civil works250K
    Grid connection250K
    Engineering and permits410K
    Contingency550K
    Total10M
    OPEX / yr (USD)
    Staff25K
    CHP service and overhaul reserve270K
    Maintenance49K
    Insurance52K
    Testing and monitoring5.6K
    OPEX87K
    Residuals disposal cost120K
    Total610K
    Revenue + savings / yr (USD)
    Electricity sales1.9M
    Total1.9M

    Unit costs are estimates. Replace them with supplier quotations.

    Digestate and residues

    Excess sludge ≈ 34,222 t/yr (wet); effluent ≈ 1,000 mg COD/L goes on to final treatment. Confirm the discharge limit and the sludge route.

    Methane losses & climate

    Expected losses: 2.5 % of methane produced (range 1.5 % – 4 %) ≈ 3,562 t CO₂e/yr; fossil emissions displaced ≈ 15,961 t CO₂/yr. Losses vs benefit: 22 %.

    Methane not captured by the project: ≈ 389,712 Nm³ CH₄/yr. It is outside the plant loss figure above.

    • Expected loss 2.5 % is above good practice (2 %): budget for monitoring.
    • Gas-tight covers on the digester and digestate storage (incl. lagoon covers) — the single most important measure.
    • Leak detection and repair (LDAR): optical gas imaging or tracer method at least yearly, plus an acceptance test after construction.
    • Continuous gas-holder pressure monitoring; a standby flare instead of venting.
    • CHP with an oxidation catalyst and tuning regime to cut methane slip.

    Avoided emissions from open manure storage are not credited (conservative).

    Permits & regulation (indicative)

    Complexity: lower. “To verify” means a local lawyer or engineer must confirm the item during the feasibility study.

    • Construction permit and national environmental approval / EIA screening
      New installation · effort: medium · to verify
    • Gas-safety approval and hazardous-area classification (IECEx or national code)
      Methane in the gas phase · effort: medium · to verify
    • Effluent / digestate discharge or land-application permit
      Digestate or treated effluent leaves the site · effort: medium · to verify
    • Power-purchase / net-metering agreement and grid connection
      Electricity export · effort: medium · to verify
    • Confirm discharge limits, final polishing and sludge disposal authorisations
      Process-specific site conditions; no automatic legal eligibility · effort: high · to verify
    Safety (risk register)
    • Methane: explosion and fire (flammable range ≈ 5–15 % in air) high
      • Hazardous-area (ATEX/IECEx or national) zoning and suitably rated equipment
      • Fixed gas detectors in the CHP room and near tanks
      • Flame arresters, over/under-pressure relief, safety flare
      • Ignition-source control and hot-work permits
    • Hydrogen sulphide (H₂S): acute toxicity, corrosion high
      • Biological / chemical desulphurisation of the biogas
      • Personal H₂S monitors, no lone working
      • H₂S monitoring upstream of the CHP (engine protection)
    • Confined spaces (digester, storage, pits): asphyxiation, toxic gases high
      • Entry only under permit, ventilation, standby person
      • Self-contained breathing apparatus for rescue
    • Over/under-pressure: membrane roof rupture, tank deformation medium
      • Liquid seals / relief valves venting to a safe location
      • Gas-holder level and pressure sensors
    • CHP: carbon monoxide, fire, high temperatures medium
      • CHP room ventilation, CO detectors
      • Emergency stop, fire suppression
    • Soil and water pollution: slurry/digestate spills, lagoon overflow high
      • Bund sized for the largest tank
      • Level sensors and a spill-response plan
      • Digestate storage covering the closed spreading season

    Software does NOT replace a qualified process engineer and a process-safety engineer. Every final engineering design, hazardous-area classification and safe-operation programme must pass human professional review.

    Assumptions used (128)

    Every number has a source, date, country and confidence, and is tagged FACT / ASSUMPTION / CALCULATION / ESTIMATE. Full register: →

    • Support: The biogas feed-in tariff (2.07 THB/kWh) awarded no biogas projects in the 2022 round and no new round is open; industrial biogas runs on self-use.
    • POME covered lagoons at palm-oil mills are the standard industrial application.
    • The verdict excludes subsidies; national support is shown as separate cases.
    • This is a preliminary (screening) assessment — not a detailed engineering design and not a commercial offer.
    • Financial results are pre-tax project cash flows. Depreciation, income taxes, working capital, financing fees and detailed debt covenants are not modelled; DSCR is an EBITDA-based screening ratio, not lender CFADS.
    • Parameter bounds are tested individually using the applicable market/CAPEX evidence. These engineering or tariff ranges are not statistical confidence intervals and do not replace supplier quotations or customer bills.

    Published technical observations; unreported inputs are engineering assumptions. No current installed budget or upstream operating accounts disclosed.

    • Operating days: 330 d/a · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · TH
    • Active months: 12 1–12 · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · TH
    • Starting month: 1 1–12 · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · TH
    • Scenario uncertainty: 50 % · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · TH
    • Q: 6,560 m³/d · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · TH
    • COD: 12,200 mg COD/L · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · TH
    • COD removal: 92 % COD · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · TH
    • CH₄: 55 % vol · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · TH
    • Methane capture: 95 % CH₄ · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · TH
    • Removed COD to biomass: 8 % COD · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · TH
    • Sludge dry solids: 5 % TS · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · TH
    • VS / TS: 80 % VS/TS · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · TH
    • HRT: 25.3 d · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · TH
    • OLR: 0.4822 kg/(m³·d) · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · TH
    • Inlet temperature: 28 °C · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · TH
    • Heat recovery: 0 % · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · TH
    • Avoided treatment charge: 0 THB/m³ · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · TH
    • Methane COD equivalent: 4 kg COD/kg CH₄ · ENGINEERING_ASSUMPTION · HIGH · 2019-01-01 · GLOBAL · https://www.ipcc-nggip.iges.or.jp/public/2019rf/pdf/5_Volume5/19R_V5_6_Ch06_Wastewater.pdf
    • Biomass COD/VSS: 1.42 kg COD/kg VSS · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · GLOBAL
    • processCapexLocal: model estimate (field left blank): 4,347,000 USD · ENGINEERING_ASSUMPTION · LOW · undated · TH
    • processOpexLocalYear: model estimate (field left blank): 86,940 USD/a · ENGINEERING_ASSUMPTION · LOW · undated · TH
    • residualCostLocalT: model estimate (field left blank): 3.391 USD/t · ENGINEERING_ASSUMPTION · LOW · undated · TH
    • auxiliaryKwhYear: model estimate (field left blank): 0 kWh/a · ENGINEERING_ASSUMPTION · LOW · undated · TH
    • auxiliaryHeatKwhYear: model estimate (field left blank): 0 kWh_th/a · ENGINEERING_ASSUMPTION · LOW · undated · TH

    What could break the economics

    Each stress test applied to the base case on its own.

    chp: local CAPEX factor
    0.546 … 1.014 —
    NPV low…high: US$400K … US$4.5M
    Discount rate (nominal, pre-tax, EUR-equivalent, incl. country risk)
    0.062 … 0.092 —
    NPV low…high: US$890K … US$3.4M
    Business electricity reference, excl. VAT (default if the customer gives none)
    0.09256 … 0.1397 USD/kWh
    NPV low…high: US$2.5M … US$2.5M
    COD
    6,100 … 18,300
    NPV low…high: -US$2.5M … US$5.1M
    COD removal
    46 … 99
    NPV low…high: -US$2.5M … US$3.3M
    Every number has a source, date, country and confidence, and is tagged FACT / ASSUMPTION / CALCULATION / ESTIMATE. Full register:
    Biomethane price without support, base: 0.4477 USD/Nm³ · CALCULATED_VALUE · LOW
    National estimate (project team, 2026-10) — no official series found for this item; your own price overrides it; local market for biomethane / RNG without credits
    WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
    Local CAPEX relative to the German baseline: 0.78 — · CALCULATED_VALUE · LOW
    0.72 traded equipment + 0.28 × local/German labour cost (2.4/31.5 €/h); split after DBFZ/Fraunhofer 2024; supplier quotes needed
    ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
    chp: local CAPEX factor: 0.78 — · CALCULATED_VALUE · LOW
    0.72 traded equipment + 0.28 × local/German labour cost (2.4/31.5 €/h); split after DBFZ/Fraunhofer 2024; supplier quotes needed
    ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
    Debt interest rate (EUR-equivalent): 0.057 — · CALCULATED_VALUE · MEDIUM
    Discount rate − 1.5 pp (senior debt is cheaper than blended project capital); consistent with ECB MIR corporate loan rates + project margin; a bank term sheet replaces this
    WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
    Debt share for DSCR test: 0.5 — · ENGINEERING_ASSUMPTION · MEDIUM
    Typical agri / project lending (KfW, EBRD, IFC practice)
    ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
    Debt tenor: 7 a · ENGINEERING_ASSUMPTION · MEDIUM
    Typical
    ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
    Digestate that has no adequate land: 3.391 USD/t · CALCULATED_VALUE · MEDIUM
    Third-party export of digestate ≈ 2.5 €/t + 0.22 h/t × labour; ≈ 12 €/t in Germany, in line with manure-exchange prices in surplus regions (LWK Niedersachsen Nährstoffbericht: 10–20 €/t)
    WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
    Discount rate (nominal, pre-tax, EUR-equivalent, incl. country risk): 0.072 — · CALCULATED_VALUE · MEDIUM
    Nominal, pre-tax, EUR-equivalent: 6.0 % mature-market WACC + 0.6 × country risk premium 1.98 % (Baa1; Damodaran, 2026-07); not a bank offer
    2026-07-01 · checked 2026-10-27 · Rating-based CRP; baseline WACC and lambda are engineering/financial assumptions
    WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
    Business electricity reference, excl. VAT (default if the customer gives none): 0.1108 USD/kWh · CALCULATED_VALUE · MEDIUM
    PEA medium/large general service TOU, 22-33 kV, excluding VAT. Reference 500 kW/200 MWh per month, continuous load; public holidays and transformer losses are excluded. Published PEA TOU energy rates + current Ft; add demand and service charges for the stated reference. Self-generation only avoids the energy/Ft portion; no peak-demand reduction is assumed. Converted at 37.485 THB/EUR (2026-11-09).
    2026-09/2026-12 · checked 2026-10-30 · PEA medium/large general service TOU, 22-33 kV, excluding VAT. Reference 500 kW/200 MWh per month, continuous load; public holidays and transformer losses are excluded.
    WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
    FX (2026-11-09): 37.49 THB/EUR (MARKET_DATA); TOU rate 1: 4.184 THB/kWh (MARKET_DATA); Reference load weight 1: 65 h/week (ENGINEERING_ASSUMPTION); TOU rate 2: 2.604 THB/kWh (MARKET_DATA); Reference load weight 2: 103 h/week (ENGINEERING_ASSUMPTION); Fuel adjustment: 0.1623 THB/kWh (MARKET_DATA); Demand charge: 132.9 THB/kW/month (MARKET_DATA); Service charge: 312.2 THB/month (MARKET_DATA); Reference billing demand: 500 kW (ENGINEERING_ASSUMPTION); Reference monthly electricity: 200,000 kWh/month (ENGINEERING_ASSUMPTION)
    Wholesale electricity price (market average): 0.07823 USD/kWh · CALCULATED_VALUE · LOW
    ERC Ft filings 2026: fuel + power-purchase cost per kWh, single-buyer system ≈ 2.62 THB/kWh (no spot market; incl. ≈ 8–9 % capacity payments); converted at 37.485 THB/EUR (2026-11-09)
    2026-07-31 · checked undated · Historical national/regional reference; latest publication and customer applicability require verification
    REVIEW_REQUIRED: Observation is 101 days old; exceeds the 60-day review policy
    Documented nominal reference (may include estimated adders): 2.62 THB (ENGINEERING_ASSUMPTION); FX (2026-11-09): 37.49 THB/EUR (MARKET_DATA)
    Annual escalation of energy prices (nominal EUR): 0.02 — · ENGINEERING_ASSUMPTION · MEDIUM
    At the ECB/Fed inflation target — no real energy-price growth assumed (conservative)
    ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
    Share of the wholesale price realised for surplus power: 0.85 — · ENGINEERING_ASSUMPTION · MEDIUM
    15 % profile & balancing discount for a small seller (assumption, same for all markets)
    ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
    Exchange rate: 33.49 THB/USD · MARKET_DATA · HIGH
    Official EUR reference rate, 2026-11-09
    2026-11-09 · checked 2026-11-10 · THB per EUR; dated reference, not a guaranteed transaction rate
    WITHIN_REVIEW_WINDOW: Within the 7-day review policy; applicability and latest publication must still be checked
    Value of useful heat (displaced gas / boiler efficiency): 0.04473 USD/kWh th · CALCULATED_VALUE · LOW
    Business gas 35.968678671468595 €/MWh LHV ÷ 0.9
    2026-07-31 · checked undated · Historical national/regional reference; latest publication and customer applicability require verification
    WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
    Documented nominal reference (may include estimated adders): 1,215 THB (ENGINEERING_ASSUMPTION); FX (2026-11-09): 37.49 THB/EUR (MARKET_DATA)
    Evaluation horizon: 15 a · ENGINEERING_ASSUMPTION · MEDIUM
    Shorter than the 20-year technical life — conservative
    ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
    Official hourly labour cost, economy-wide (wages + employer costs): 2.711 USD/h · CALCULATED_VALUE · MEDIUM
    BOT/NSO average monthly employee wage, not a specialist biogas operator quotation. Monthly wage x12 x1.05 employer allowance /2200 hours /THB per EUR. Employer allowance and working hours are engineering assumptions. Converted at 37.485 THB/EUR (2026-11-09).
    2026-Q2 · checked 2026-10-30 · BOT/NSO average monthly employee wage, not a specialist biogas operator quotation.
    WITHIN_REVIEW_WINDOW: Within the 730-day review policy; applicability and latest publication must still be checked
    FX (2026-11-09): 37.49 THB/EUR (MARKET_DATA); Monthly employee wage: 15,850 THB/month (MARKET_DATA); Employer multiplier: 1.05 — (ENGINEERING_ASSUMPTION); Annual working hours: 2,200 h/year (ENGINEERING_ASSUMPTION)
    Plant operator wage relative to the economy-wide average: 1 — · ENGINEERING_ASSUMPTION · MEDIUM
    Plant operator ≈ economy-wide average (middle-income economy; no premium)
    ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
    Annual escalation of operating costs (nominal EUR): 0.025 — · ENGINEERING_ASSUMPTION · MEDIUM
    Inflation target + 0.5 pp wage drift
    ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
    Share of the bill actually avoided by self-generation: 0.91 — · ENGINEERING_ASSUMPTION · MEDIUM
    TOU reference: energy/Ft portion only, demand/service charges retained. Else 85% engineering allowance. User invoice uses the generic allowance until its energy/demand split is known.
    ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity