A mill runs for much of the year, which helps the plant, and may be far from a grid connection. The result depends on the price of power or fuel replaced and on the rules for connection and sale. In our model the Thai POME case is possible with conditions.
What drives payback
Methane that would be lost from the open pond becomes energy. The model counts losses and the climate effect separately.
Gas replacing diesel or purchased electricity at the mill has a higher value than export.
Selling power depends on access and on the tariff of the country. A long connection line changes the result.
Harvest peaks change the volume of POME. The reactor is sized for the average.
What it takes to work
- A mill working most of the year at a steady throughput
- Use of the gas on site or a realistic grid connection
- A pond or reactor design that keeps methane from escaping
Frequently asked questions
Do I need to treat the effluent anyway?
Yes, to meet discharge or land application rules. The reactor is a first stage that removes much of the COD.
Is the empty fruit bunch a feedstock?
It can be added, but it is fibrous and needs pretreatment. The calculator keeps it separate.
Are carbon credits included?
No. Carbon revenue is a separate case and does not change the base verdict.