Sample report · Thailand

Thai palm-oil mill, POME

A sample Extended Report for a modelled project. Your report has the same structure (the Standard Report has fewer sections) and uses your own data.

Business situation

A southern Thai palm-oil mill assesses methane recovery from 250,000 t/year of POME. This is also a test of the model's limits for lagoon technology.

Operating assumptions

  • Palm-oil mill effluent (POME): 250,000 t/yr · DM: 5 % · 12 months
  • Electricity: 4,000,000 kWh/yr · Electricity price on your bill (if known): 3.95 THB/kWh
  • No heat needed
  • Land available for spreading digestate: 3,000 ha · Distance to the gas grid (for biomethane): —
  • Existing lagoon / store that could be covered: 100,000 m³
  • Grid connection? Yes

What to verify

Measure COD, discharge temperature and seasonal flow. Obtain lagoon-specific CAPEX, liner and cover design, H₂S treatment and current utility terms before using the result for investment.

Possible with conditions

It can pay off, but only if the key conditions hold — confirm them in a feasibility study.

  • Base NPV positive (US$2.7M), payback ≈ 6.3 yrs.
  • Conservative-case NPV is negative (-US$1.8M) — sensitive to key assumptions.
  • Data confidence is low — the verdict is preliminary.

Largest benefit — “surplus electricity sold”: ≈ 65 % of all revenue and savings.

What would change the verdict
  • → Secure long-term heat and power offtake; benchmark CAPEX with 3–5 suppliers.
  • → Fill in missing data and run a laboratory feedstock analysis.

Subsidies and tariffs excluded from the verdict. Preliminary screening, not an engineering design.

How firm is this answer?

Grey zone: the answer flips between the conservative and the optimistic case. Before paying for a feasibility study, check these first:

NPV: conservative -US$1.8M · base US$2.7M · optimistic US$4.9M

The conservative case stacks every adverse assumption at once: a stress test, not the likely outcome. In 160 likely combinations the NPV was positive in 99 % of cases.

  1. Get an offer for exported power (PPA or tariff) · Energy prices −20 % (-US$2M)
  2. Feedstock potential −20 % (-US$1.5M)
  3. Lab test of the methane yield (BMP) · CH₄ −20 % (-US$1.5M)

These are screening assumptions, not independently validated accuracy limits. Confirm BMP, supplier scope, grid connection and offtake terms before an investment decision.

To reach a bankable estimate (±15 %)
  1. Laboratory methane-potential (BMP) test of 2–3 feedstock samples — ≈ US$336–US$895 each
  2. 2–3 supplier quotes for the plant
  3. Grid or gas-network connection conditions from the operator
  4. Letters of intent for feedstock supply and for heat, power or biomethane offtake
  5. Then a feasibility study with permits and financing (±15 %)
From screening to construction

Key figures

Ranges: conservative — base — optimistic. We don't show fake precision.

Economics

Preliminary investment
US$4.4M – US$5.8M
≈ THB 160M (base)
Payback
4.6 yr – 13.8 yr
base: 6.3 yr · no subsidies
NPV (base)
US$2.7M
range: -US$1.8M … US$4.9M
Chosen route
CHP (power + heat)
Confidence: Low

1 EUR = 1.1193 USD · ECB · 2026-11-09

Feedstock and energy

Feedstock potential
250,000 t/yr
energy ≈ 140 kWh CH₄/t
Biogas
4.4M – 6.1M Nm³/yr
≈ 706 Nm³/h (base)
Net energy
11,000 – 14,000 MWh/yr
useful heat: 0 MWh · ≈ 85 % of your electricity use
Candidate capacity
1,900 kWe
large (1–5 MW)

How far you can rely on these numbers

Low · 49/100
  • Backed by your data and our sources49
  • You can still add+41
  • Needs a feasibility study (lab, quotes, contracts)10

49/100: how much of what a screening can know about this project rests on your data and current sources. A missing input costs points in proportion to how far it could still move your result.

What you can add

  • Biggest gainLaboratory DM, VS and BMP results for every feedstock streamLarge effectSend a sample to a laboratory: dry matter and VS take a few days, BMP several weeksValues equal to the typical ones shown in the form do not count as a laboratory result.+27
  • Route-specific CAPEX lacks independent local validation — obtain comparable supplier quotations+8
  • At least one price affecting this route relies on an unconfirmed market proxy or uncontracted offtake — confirm the applicable tariff or buyer contract+6

With all of it: up to 90/100

High requires verified laboratory and project documents, so a screening stops at 90/100.

Model warnings
  • "palm oil mill effluent (POME)" is very dilute: consider a high-rate reactor (UASB / covered lagoon) instead of a CSTR — the model's CSTR costing is conservative here.
  • CHP performance uses a 50 Hz biogas full-load catalogue reference (03/2025), interpolated between ratings; part-load and ambient derating require supplier confirmation.
  • Market data require review (econ.electricity_spot_eur_kwh). Observation dates and validity are shown in the evidence; these are not verified current customer quotations.
  • Both digester types were assessed for this liquid feed and climate. Chosen: Covered anaerobic lagoon (unheated, ambient temperature) (NPV US$2.7M); alternative: Wet mesophilic digestion (CSTR) (NPV US$760K, CAPEX US$6.4M). A covered lagoon is cheaper but gives ≈ 100 % of a heated tank's gas (EPA AgSTAR) and needs land.
Compared with the market
Our estimate: ≈ 2,600 USD/kW at ≈ 1,880 kW
  • 3,358–5,037 USD/kW — Biogas plants, Ukraine · below rangeSupplier estimate (Zorg Biogas, ≈ €3,500/kW at 1 MW — primary source not found); Ecodevelop 333 kW ≈ €1.5 m (older project) · ≈2013–2020 · Supplier estimate

Market figures are mostly trade press and supplier estimates, not audited budgets. Real prices come from 3–5 supplier quotes.

Country conditions
  • POME covered lagoons at palm-oil mills are the standard industrial application.

Action plan: what would make it stronger

Changes tested on this project with the same model. Break-even values show how far each must go; the scenario assumptions are LOW-confidence judgements to replace with offers.

What separates this project from “Strong candidate”
  • The conservative case must stay profitable too (its NPV is -US$1.8M).
  • Data confidence is low (49/100): see “What you can add”.
ChangeVerdictNPV (base)Δ NPVBreak-even
Sell the spare heat
A year-round heat buyer (drying, process heat, greenhouse or district heating) for ≈ 11,000 MWh a year, valued at ≈ THB 1.5 per kWh.
Possible with conditionsUS$7.1M+US$4.5Mheat ≥ THB 0.101 per kWh
Order of action
  1. 1Find a heat buyer for ≈ 11,000 MWh a year (heat ≥ THB 0.101 per kWh).
  2. 2Ask 3–5 suppliers for quotes: the project breaks even up to an investment of US$7.1M. →

What to verify first

Inputs ranked by what exact knowledge is worth before you decide (expected value of perfect information). Each range is tested on its own; inputs you already supplied are not listed.

CheckNPV across the plausible rangeWorth knowing
Get supplier quotes for the plantUS$940K … US$4.4M—
Verify the market priceUS$1.7M … US$3.2M—
Check how your bill splits energy and capacity chargesUS$2.1M … US$3.2M—
Check the fertiliser value of the digestateUS$2.6M … US$2.7M—
How to check: Get supplier quotes for the plant
  1. Send the same request to at least three suppliers.
  2. Compare like for like: scope, exclusions, guaranteed gas output, own power use, availability and the O&M price.
Request to send
Request for quotation: turnkey biogas plant
Site: Thailand.
Feedstock (screening values, to be confirmed):
- palm oil mill effluent (POME): 250,000 t/year, DM ≈ 5.0 %
Design basis from the screening: raw biogas ≈ 710 Nm³/h at ≈ 62 % CH₄; digester working volume ≈ 27,000 m³; combined heat and power ≈ 1,900 kWe; new digestate storage ≈ 0 m³.
Please quote turnkey: feeding, digester(s), gas system with flare and desulphurisation, the gas-use equipment above, electrical and I&C, civil works, engineering and commissioning. List exclusions (grid connection, permits, land, digestate storage if separate). State the guaranteed gas output, own power and heat use, availability and the price of a full O&M contract.

Then enter it in: Step 3, “Optional: contracts and financing”: supplier quote and its technology

How to check: Verify the market price
  1. Check the official source shown for this price in the market-data table and compare it with your own contract.

Then enter it in: Energy step: your own price, if you have a contract

How to check: Check how your bill splits energy and capacity charges
  1. Take the last 12 electricity invoices.
  2. Split each into the energy part (per kWh) and capacity, network and fixed charges; own generation saves mainly the energy part.

Then enter it in: Energy step: electricity price per kWh (energy part, excl. VAT)

How to check: Check the fertiliser value of the digestate
  1. Ask neighbouring farms what they would pay per tonne of digestate, delivered and spread.
  2. Check the land available for spreading against the nitrogen limit.

Then enter it in: Site step: land available for digestate

Break-even prices

Each value on its own brings the base-case NPV to zero; everything else stays as calculated.

Electricity value at NPV = 0
US$0.0552/kWh
now US$0.0749/kWh
Highest installed cost at NPV = 0
US$7.1M
now US$4.9M
Feedstock price headroom
US$1.02/t
can pay up to US$1.02 per tonne more for every input

Probability range (Monte Carlo)

160 draws of the scenario quantities (yield, dry matter, CAPEX, prices, heat use, operating hours…). Energy and biomethane prices move together, the rest independently. Not a forecast: it shows how often the project stays positive when the uncertainties do not all go wrong at once.

NPV P10 (1 in 10 worse)
US$840K
Median NPV
US$1.9M
NPV P90 (1 in 10 better)
US$2.7M
Chance that NPV > 0
99 %
Median payback
7 yr

No real-plant check for this type of project yet: we have no open data on operating plants like this one to compare with the model. The range above shows only the model's own uncertainty; confirm the gas yield with a lab test (BMP) or a pilot first.

What could break the economics

Each stress test applied to the base case on its own.

Change in NPV vs base, USD (base: 2.7M)

  1. Energy prices −20 %-2M
  2. Feedstock potential −20 %-1.5M
  3. CH₄ −20 %-1.5M
  4. CAPEX +20 %-1.1M
  5. CHP downtime +10 pp-890K
  6. Maintenance +30 %-710K
  7. Useful heat (economic) −50 %0
  8. Feedstock transport +50 %0
NPV = 0 if CAPEX falls by
already positive
grant, leasing, cheaper equipment
NPV = 0 if energy prices rise by
already positive
relative to the base case

Scenarios

Route: CHP (power + heat). Scenarios bundle consistent assumptions (lower yield comes with higher CAPEX).

Revenue + savings / yrUS$1M
  • Electricity sales680K
  • Electricity self-consumption savings340K
  • Incremental digestate value26K
OPEX / yrUS$270K
  • CHP service and overhaul reserve170K
  • Maintenance59K
  • Insurance24K
  • Staff14K
Operating margin (EBITDA)US$770K
ScenariosConservativeBaseOptimistic
Biogas, 1 000 Nm³/yr4,440.55,645.26,096.8
CAPEXUS$5.8MUS$4.9MUS$4.4M
OPEX / yrUS$290KUS$270KUS$260K
Revenue + savings / yrUS$710KUS$1MUS$1.2M
Operating margin (EBITDA)US$420KUS$770KUS$950K
Simple payback13.8 yr6.3 yr4.6 yr
Discounted paybackno payback8.5 yr5.9 yr
NPV-US$1.8MUS$2.7MUS$4.9M
IRR2.2 %14.4 %20.8 %
DSCR (min)0.81.82.5

Pre-tax, nominal USD, 15-year horizon, discount rate of the country or your own; a screening estimate, not a bankable feasibility study. DSCR = EBITDA ÷ debt service at 50 % debt (no taxes).

Cumulative cash flow, USD
-6.9M-2M2.9M7.8M13M03691215yearsConservativeBaseOptimistic

Biogas use routes compared

Base case. The model picks the route with the best NPV among technically sensible ones.

RouteCAPEXEBITDA / yrPaybackNPV (base)NPV low…high
CHP (power + heat) chosenUS$4.9MUS$770K6.3 yrUS$2.7M-US$1.8M … US$4.9M
Boiler (heat only) US$2.6M-US$190Kno payback-US$4.5M-US$5.6M … -US$4M
Biomethane US$6MUS$730K8.2 yrUS$770K-US$7.4M … US$9.4M
  • CHP pays when you use the power yourself and the heat is really used.
  • Biomethane: raw biogas ≈ 695 Nm³/h. The smallest upgrading units take ≈ 50–100 Nm³/h, and the cost per Nm³ falls steeply with size, so a small plant pays much more for each unit of gas.

Plant size

The same feedstock mix at other sizes, each option re-sized by the model. Extra feedstock is assumed on your terms (price, transport, disposal saving); CAPEX is the model's estimate, not your quote.

Sizet/yrBest optionkWeCAPEXNPV (base)
× 0.5 130,000CHP (power + heat)920US$2.7MUS$1.2M
× 0.75 190,000CHP (power + heat)1,380US$3.8MUS$1.8M
× 1 your input250,000CHP (power + heat)1,880US$4.9MUS$2.7M
× 1.5 380,000CHP (power + heat)2,800US$6.8MUS$4.2M
× 2 500,000CHP (power + heat)3,730US$8.7MUS$6M
× 3 750,000CHP (power + heat)5,600US$12MUS$9.8M

National support schemes — separate cases

Not in the verdict: tariffs get cut, auctions fail, grant calls close. Status and source shown for each.

Bottom line

No support scheme is open for your project right now

The verdict rests on market prices only, so it does not change. Closed or unconfirmed schemes, if any, are listed below for reference.

Country overviewchecked 30 Oct 2026

The biogas feed-in tariff (2.07 THB/kWh) awarded no biogas projects in the 2022 round and no new round is open; industrial biogas runs on self-use.

Closed schemes (1)

Intake has ended. Shown for reference only.

VSPP/SPP biogas FiT 2022–2030

Closed
Electricity tariff
For reference
NPV change
-US$1.2M
NPV with support
US$1.5M
Payback
6.7 yr
IRR
11.5 %

Reference figures: intake is closed.

Conditions
  • met: CHP of a practical size, from 25 kW (project ≈ 1,880 kW)
What the case uses
  • Route: CHP (power + heat)
  • Tariff: US$0.0616/kWh
Scheme terms

2.0724 THB/kWh (+0.50 in southern border provinces); shown for reference — no open round.

Next step: Do not plan on it. Watch the operator's announcements for a successor scheme.

Source: ERC 2022 RE FiT procurement regulation · checked 30 Oct 2026 · Data confidence: Medium

Support never changes the verdict. Each case is pre-tax, uses the scheme's published terms and assumes the support is awarded; it does not confirm eligibility or promise funding.

Where the energy goes

Heat produced ≠ useful heat. Heat without a user isn't income.

39/100

Of every 100 kWh of energy in the methane, 39 become a product that earns money or replaces a purchase.

100 % = 35,000 MWh of methane energy a year (LHV), base case. Every figure in this block is calculated by the model from your inputs.

Stream by stream

Calculated

Earns money

  • Electricity sold to the grid10,000 MWh 29 %
  • Electricity used on site3,400 MWh 10 %

Runs the plant

  • Plant’s own electricity1,100 MWh 3 %

Produced, not used

  • Heat with no buyer14,000 MWh 39 %

Losses

  • Conversion losses (engine, boiler)5,500 MWh 16 %
  • Gas sent to the flare680 MWh 2 %
  • Methane leaks520 MWh 1 %

What this means for the project

  • 14,000 MWh of heat a year has no buyer. A heat user nearby (drying, a greenhouse, process heat, a heating network) would turn it into income.
  • Methane leaks are 2 % of production in the base case: lost income and a greenhouse gas. Gas-tight digestate storage and regular leak checks keep them low.

What the figures rest on

Engine efficiency: electricity / heat
44 % / 44 %Assumption
Heat need
no heat userYour data
Site electricity use
4,000 MWhYour data
Methane leaks, base case
2 %Assumption
Main product, conservative – optimistic
11,000 – 14,000 MWhCalculated

How it works: from feedstock to products

  1. Feedstock250,000 t/yr
  2. Biogas5.6M Nm³/yr
  3. Electricity14,000 MWh
  4. Useful heat0 MWh
  5. Heat without demand14,000 MWh
  6. Digestate240,000 t/yr
Heat produced (gross)
13,509 MWh
Digester heat demand
0 MWh
Useful heat (economic)
0 MWh of 13,509
Power: own use / sold
3,400 / 10,184 MWh

Climate case (EU RED method)

EU Renewable Energy Directive default values for your feedstock mix, digestate storage and route. Separate from the verdict; outside the EU an indicative benchmark. Credits are valued only in the support cases where an official mechanism exists.

Emissions of the product
30 g CO₂e/MJ
gas-tight digestate storage
Fossil comparator
183 g CO₂e/MJ
Greenhouse-gas saving
84 %
RED minimum: 80 %
Avoided emissions
7,490 t CO₂e
  • Meets the RED minimum.
  • RED sustainability criteria apply (rated input ≥ 2 MW).
  • Residues other than manure, maize and food waste use the RED biowaste values.

Scores by dimension

No single magic number. The overall score comes with its explanation.

Feedstock fit
86/100
  • Energy equivalent ≈ 1880 kWe (scale score 100/100)
  • Feedstock energy ≈ 140 kWh of methane per tonne (score 30/100)
  • Feedstock available 12 of 12 months
Energy fit
35/100
  • Own consumption absorbs 25 % of the electricity produced
  • Useful heat 0 MWh of 13509 MWh available after digester needs
Location & logistics
100/100
  • No critical site constraints found from your answers
Technical feasibility
100/100
  • Standard layout for this scale, no critical obstacles
Economics
78/100
  • Base-case simple payback ≈ 6.3 years
Regulatory complexity
14/100 risk
  • Number and weight of permitting / regulatory steps: 8 points (more = harder)
Environmental risk
24/100 risk
  • Expected methane loss 2.5 % (good practice ≤ 2 %)
Overall project viability
78/100
  • Weighted: economics 30 %, feedstock 20 %, energy 15 %, technical 10 %, location 10 %, regulatory 7.5 %, environment 7.5 %.
  • Strongest: Location & logistics (100); weakest: Energy fit (35).

Calculation details

Feedstock & logistics
Streamt/yrDM, %Nm³ CH₄/tLogistics / energyMax. distance
Palm-oil mill effluent (POME)250,000514on site≈ 18 km

Max. distance = where haulage eats half of a tonne's energy value. Low-energy feedstock (slurry) belongs next to the plant.

Technology & digester

Covered anaerobic lagoon (unheated, ambient temperature)

Lined lagoon with HDPE gas-tight cover, sludge removal and gas collection

Working volume
≈ 27,000 m³
Retention time
40 days
Loading rate
1 kg VS/(m³·d)
Digestate storage
≈ 20,000 m³
  • Warm climate (annual mean ≈ 28 °C) and a liquid feed (5.0 % DM): an unheated covered lagoon is the lowest-cost proven option.
  • Continuous feed — continuous operation gives steady gas and the simplest control.
  • Single stage plus a gas-tight digestate store as post-digester: sufficient at this scale.
Alternatives
  • Heated CSTR or UASB for higher, steadier gas yield per m³

Climate: Southern Thailand (Surat Thani), mean 27.9 °C, ≈ 0 heating degree-days. Closest climate analogues: Dresden (DE, east) (Δ 18.9 °C), Prague (CZ) (Δ 19.2 °C), Copenhagen (DK) (Δ 19.2 °C).

Monthly energy balance

Base case, chosen route. Gas energy is usable methane energy (LHV) after losses.

MonthFeedstock, tGas energy, MWhDigester heat, MWhUseful heat, MWhNet electricity, MWh
Jan21,2182,917001,153
Feb19,3362,658001,051
Mar21,2182,917001,153
Apr20,5342,823001,116
May21,2182,917001,153
Jun20,5342,823001,116
Jul21,2182,917001,153
Aug21,2182,917001,153
Sept20,5342,823001,116
Oct21,2182,917001,153
Nov20,5342,823001,116
Dec21,2182,917001,153
Σ250,00034,3720013,584
CAPEX, OPEX, revenue (base case)
CAPEX (USD)
Digester820K
Covering existing storage530K
Feedstock reception and preparation74K
Gas handling and cleaning100K
CHP (power + heat)1.9M
Electrical systems and controls210K
Pipework140K
Civil works210K
Grid connection120K
Engineering and permits330K
Contingency440K
Total4.9M
OPEX / yr (USD)
Staff14K
CHP service and overhaul reserve170K
Maintenance59K
Insurance24K
Testing and monitoring5.6K
Total270K
Revenue + savings / yr (USD)
Electricity self-consumption savings340K
Electricity sales680K
Incremental digestate value26K
Total1M

Unit costs are estimates. Replace them with supplier quotations.

Digestate: asset or liability

Status: asset · 243,250 t/yr · nitrogen ≈ 166,250 kg/yr · land needed ≈ 978 ha (available 3,000 ha).

Incremental fertiliser value US$26K/yr, handling US$0/yr, net US$26K/yr.

  • Digestate storage for 3 months for the closed spreading season; keep ≈ 150 days (incl. the digester) gas-tight, otherwise methane and N are lost.
  • Spread by injection or trailing hose (not splash plate): less odour and ammonia loss.
Methane losses & climate

Expected losses: 2.5 % of methane produced (range 1.6 % – 4 %) ≈ 1,697 t CO₂e/yr; fossil emissions displaced ≈ 7,417 t CO₂/yr. Losses vs benefit: 23 %.

  • Expected loss 2.5 % is above good practice (2 %): budget for monitoring.
  • Gas-tight covers on the digester and digestate storage (incl. lagoon covers) — the single most important measure.
  • Leak detection and repair (LDAR): optical gas imaging or tracer method at least yearly, plus an acceptance test after construction.
  • Continuous gas-holder pressure monitoring; a standby flare instead of venting.
  • CHP with an oxidation catalyst and tuning regime to cut methane slip.

Avoided emissions from open manure storage are not credited (conservative).

Permits & regulation (indicative)

Complexity: lower. “To verify” means a local lawyer or engineer must confirm the item during the feasibility study.

  • Construction permit and national environmental approval / EIA screening
    New installation · effort: medium · to verify
  • Gas-safety approval and hazardous-area classification (IECEx or national code)
    Methane in the gas phase · effort: medium · to verify
  • Effluent / digestate discharge or land-application permit
    Digestate or treated effluent leaves the site · effort: medium · to verify
  • Power-purchase / net-metering agreement and grid connection
    Electricity export · effort: medium · to verify
Safety (risk register)
  • Methane: explosion and fire (flammable range ≈ 5–15 % in air) high
    • Hazardous-area (ATEX/IECEx or national) zoning and suitably rated equipment
    • Fixed gas detectors in the CHP room and near tanks
    • Flame arresters, over/under-pressure relief, safety flare
    • Ignition-source control and hot-work permits
  • Hydrogen sulphide (H₂S): acute toxicity, corrosion high
    • Biological / chemical desulphurisation of the biogas
    • Personal H₂S monitors, no lone working
    • H₂S monitoring upstream of the CHP (engine protection)
  • Confined spaces (digester, storage, pits): asphyxiation, toxic gases high
    • Entry only under permit, ventilation, standby person
    • Self-contained breathing apparatus for rescue
  • Over/under-pressure: membrane roof rupture, tank deformation medium
    • Liquid seals / relief valves venting to a safe location
    • Gas-holder level and pressure sensors
  • CHP: carbon monoxide, fire, high temperatures medium
    • CHP room ventilation, CO detectors
    • Emergency stop, fire suppression
  • Soil and water pollution: slurry/digestate spills, lagoon overflow high
    • Bund sized for the largest tank
    • Level sensors and a spill-response plan
    • Digestate storage covering the closed spreading season

Software does NOT replace a qualified process engineer and a process-safety engineer. Every final engineering design, hazardous-area classification and safe-operation programme must pass human professional review.

Assumptions used (165)

Every number has a source, date, country and confidence, and is tagged FACT / ASSUMPTION / CALCULATION / ESTIMATE. Full register: →

  • Support: The biogas feed-in tariff (2.07 THB/kWh) awarded no biogas projects in the 2022 round and no new round is open; industrial biogas runs on self-use.
  • POME covered lagoons at palm-oil mills are the standard industrial application.
  • The verdict excludes subsidies; national support is shown as separate cases.
  • This is a preliminary (screening) assessment — not a detailed engineering design and not a commercial offer.
  • Financial results are pre-tax project cash flows. Depreciation, income taxes, working capital, financing fees and detailed debt covenants are not modelled; DSCR is an EBITDA-based screening ratio, not lender CFADS.
  • Parameter bounds are tested individually using the applicable market/CAPEX evidence. These engineering or tariff ranges are not statistical confidence intervals and do not replace supplier quotations or customer bills.

What could break the economics

Each stress test applied to the base case on its own.

chp: local CAPEX factor
0.546 … 1.014 —
NPV low…high: US$940K … US$4.4M
Discount rate (nominal, pre-tax, EUR-equivalent, incl. country risk)
0.062 … 0.092 —
NPV low…high: US$1.7M … US$3.2M
Mineral potassium price
0.7981 … 0.9065 USD/kg K₂O
NPV low…high: US$2.7M … US$2.7M
Mineral nitrogen price
1.17 … 2.035 USD/kg N
NPV low…high: US$2.6M … US$2.7M
Mineral phosphorus price
1.588 … 2.068 USD/kg P₂O₅
NPV low…high: US$2.7M … US$2.7M
Avoidable share of an unsplit customer electricity bill
0.7 … 1 —
NPV low…high: US$2.1M … US$3.2M
Every number has a source, date, country and confidence, and is tagged FACT / ASSUMPTION / CALCULATION / ESTIMATE. Full register:
Biomethane price without support, base: 0.4477 USD/Nm³ · CALCULATED_VALUE · LOW
National estimate (project team, 2026-10) — no official series found for this item; your own price overrides it; local market for biomethane / RNG without credits
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
chp: local CAPEX factor: 0.78 — · CALCULATED_VALUE · LOW
0.72 traded equipment + 0.28 × local/German labour cost (2.4/31.5 €/h); split after DBFZ/Fraunhofer 2024; supplier quotes needed
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Debt interest rate (EUR-equivalent): 0.057 — · CALCULATED_VALUE · MEDIUM
Discount rate − 1.5 pp (senior debt is cheaper than blended project capital); consistent with ECB MIR corporate loan rates + project margin; a bank term sheet replaces this
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Debt share for DSCR test: 0.5 — · ENGINEERING_ASSUMPTION · MEDIUM
Typical agri / project lending (KfW, EBRD, IFC practice)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Debt tenor: 7 a · ENGINEERING_ASSUMPTION · MEDIUM
Typical
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Digestate that has no adequate land: 3.391 USD/t · CALCULATED_VALUE · MEDIUM
Third-party export of digestate ≈ 2.5 €/t + 0.22 h/t × labour; ≈ 12 €/t in Germany, in line with manure-exchange prices in surplus regions (LWK Niedersachsen Nährstoffbericht: 10–20 €/t)
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Incremental digestate handling on adequate land: 1.556 USD/t · CALCULATED_VALUE · MEDIUM
Pumping & trailing-hose spreading ≈ 1.2 €/t machinery + 0.08 h/t × labour; ≈ 4.8 €/t in Germany, in line with KTBL contractor rates (3–6 €/m³)
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Discount rate (nominal, pre-tax, EUR-equivalent, incl. country risk): 0.072 — · CALCULATED_VALUE · MEDIUM
Nominal, pre-tax, EUR-equivalent: 6.0 % mature-market WACC + 0.6 × country risk premium 1.98 % (Baa1; Damodaran, 2026-07); not a bank offer
2026-07-01 · checked 2026-10-27 · Rating-based CRP; baseline WACC and lambda are engineering/financial assumptions
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Wholesale electricity price (market average): 0.07823 USD/kWh · CALCULATED_VALUE · LOW
ERC Ft filings 2026: fuel + power-purchase cost per kWh, single-buyer system ≈ 2.62 THB/kWh (no spot market; incl. ≈ 8–9 % capacity payments); converted at 37.485 THB/EUR (2026-11-09)
2026-07-31 · checked undated · Historical national/regional reference; latest publication and customer applicability require verification
REVIEW_REQUIRED: Observation is 101 days old; exceeds the 60-day review policy
Documented nominal reference (may include estimated adders): 2.62 THB (ENGINEERING_ASSUMPTION); FX (2026-11-09): 37.49 THB/EUR (MARKET_DATA)
Annual escalation of energy prices (nominal EUR): 0.02 — · ENGINEERING_ASSUMPTION · MEDIUM
At the ECB/Fed inflation target — no real energy-price growth assumed (conservative)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Share of the wholesale price realised for surplus power: 0.85 — · ENGINEERING_ASSUMPTION · MEDIUM
15 % profile & balancing discount for a small seller (assumption, same for all markets)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Mineral potassium price: 0.8519 USD/kg K₂O · CALCULATED_VALUE · MEDIUM
World Bank Pink Sheet, 12-month mean 2025M10–2026M09; ÷ nutrient share × 1.35 farm-gate markup
2025M10 / 2026M09 · checked 2026-10-27 · World commodity reference; actual digestate nutrient substitution and local fertiliser price require confirmation
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Trailing-year commodity reference: 378.6 USD/t product (MARKET_DATA); Latest-month reference (2026-09): 367.5 USD/t product (MARKET_DATA); FX (2026-11-09): 1.119 USD/EUR (MARKET_DATA); Farm-gate markup: 1.35 — (ENGINEERING_ASSUMPTION)
Mineral nitrogen price: 1.489 USD/kg N · CALCULATED_VALUE · MEDIUM
World Bank Pink Sheet, 12-month mean 2025M10–2026M09; ÷ nutrient share × 1.35 farm-gate markup
2025M10 / 2026M09 · checked 2026-10-27 · World commodity reference; actual digestate nutrient substitution and local fertiliser price require confirmation
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Trailing-year commodity reference: 507.3 USD/t product (MARKET_DATA); Latest-month reference (2026-09): 407.5 USD/t product (MARKET_DATA); FX (2026-11-09): 1.119 USD/EUR (MARKET_DATA); Farm-gate markup: 1.35 — (ENGINEERING_ASSUMPTION)
Mineral phosphorus price: 1.878 USD/kg P₂O₅ · CALCULATED_VALUE · MEDIUM
World Bank Pink Sheet, 12-month mean 2025M10–2026M09; ÷ nutrient share × 1.35 farm-gate markup
2025M10 / 2026M09 · checked 2026-10-27 · World commodity reference; actual digestate nutrient substitution and local fertiliser price require confirmation
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Trailing-year commodity reference: 639.8 USD/t product (MARKET_DATA); Latest-month reference (2026-09): 690 USD/t product (MARKET_DATA); FX (2026-11-09): 1.119 USD/EUR (MARKET_DATA); Farm-gate markup: 1.35 — (ENGINEERING_ASSUMPTION)
Exchange rate: 33.49 THB/USD · MARKET_DATA · HIGH
Official EUR reference rate, 2026-11-09
2026-11-09 · checked 2026-11-10 · THB per EUR; dated reference, not a guaranteed transaction rate
WITHIN_REVIEW_WINDOW: Within the 7-day review policy; applicability and latest publication must still be checked
Value of useful heat (displaced gas / boiler efficiency): 0.04473 USD/kWh th · CALCULATED_VALUE · LOW
Business gas 35.968678671468595 €/MWh LHV ÷ 0.9
2026-07-31 · checked undated · Historical national/regional reference; latest publication and customer applicability require verification
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Documented nominal reference (may include estimated adders): 1,215 THB (ENGINEERING_ASSUMPTION); FX (2026-11-09): 37.49 THB/EUR (MARKET_DATA)
Evaluation horizon: 15 a · ENGINEERING_ASSUMPTION · MEDIUM
Shorter than the 20-year technical life — conservative
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Official hourly labour cost, economy-wide (wages + employer costs): 2.711 USD/h · CALCULATED_VALUE · MEDIUM
BOT/NSO average monthly employee wage, not a specialist biogas operator quotation. Monthly wage x12 x1.05 employer allowance /2200 hours /THB per EUR. Employer allowance and working hours are engineering assumptions. Converted at 37.485 THB/EUR (2026-11-09).
2026-Q2 · checked 2026-10-30 · BOT/NSO average monthly employee wage, not a specialist biogas operator quotation.
WITHIN_REVIEW_WINDOW: Within the 730-day review policy; applicability and latest publication must still be checked
FX (2026-11-09): 37.49 THB/EUR (MARKET_DATA); Monthly employee wage: 15,850 THB/month (MARKET_DATA); Employer multiplier: 1.05 — (ENGINEERING_ASSUMPTION); Annual working hours: 2,200 h/year (ENGINEERING_ASSUMPTION)
Plant operator wage relative to the economy-wide average: 1 — · ENGINEERING_ASSUMPTION · MEDIUM
Plant operator ≈ economy-wide average (middle-income economy; no premium)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Annual escalation of operating costs (nominal EUR): 0.025 — · ENGINEERING_ASSUMPTION · MEDIUM
Inflation target + 0.5 pp wage drift
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Road transport of organic feedstock: 0.07499 USD/(t·km) · CALCULATED_VALUE · MEDIUM
0.06 €/t·km vehicle & fuel + 0.003 × driver labour cost (€/h); matches KTBL slurry haulage ≈ 0.12–0.16 €/t·km in Germany
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Loading/unloading per tonne: 0.7275 USD/t · CALCULATED_VALUE · MEDIUM
0.6 €/t pump & loader + 0.02 h/t × labour cost (KTBL Betriebsplanung machine-cost norms, scaled by national labour cost)
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Avoidable share of an unsplit customer electricity bill: 0.85 — · ENGINEERING_ASSUMPTION · LOW
Engineering judgement, no published value: energy share of an unsplit bill; customer tariff sheet takes precedence
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Customer electricity price (invoice split not verified): 0.1179 USD/kWh · USER_INPUT · MEDIUM
USER_INPUT 3.95 THB/kWh / FX 37.485; Official EUR reference rate, 2026-11-09. Invoice date not supplied; energy/demand split assumed separately.
REVIEW_REQUIRED: Customer input; invoice date, contract and validity not independently verified
pome: dry matter: 5 % FM · MEASURED · MEDIUM
MEASURED laboratory report; replaces the catalogue value for this stream. Not independently verified.
REVIEW_REQUIRED: Customer measurement; sample, date and laboratory not independently verified
pome: volatile solids: 80 % DM · MEASURED · MEDIUM
MEASURED laboratory report; replaces the catalogue value for this stream. Not independently verified.
REVIEW_REQUIRED: Customer measurement; sample, date and laboratory not independently verified
pome: BMP (scenarios ± inter-laboratory spread): 350 L CH₄/kg VS · MEASURED · MEDIUM
MEASURED laboratory BMP test; replaces the catalogue value for this stream. Not independently verified.
REVIEW_REQUIRED: Customer measurement; sample, date and laboratory not independently verified