Sample report · Mexico

Pig farm · Pig slurry: 33,250 t/yr · Pig slurry: 11,880 t/yr

A sample Extended Report for a modelled project. Your report has the same structure (the Standard Report has fewer sections) and uses your own data.

Business situation

A Yucatán pig integrator covers its lagoons and runs generators to replace CFE power. More than 100 commercial farms in Yucatán have digesters and about half have gensets; research shows many are poorly operated and recover their investment only under good conditions.

Operating assumptions

  • Pig slurry: 33,250 t/yr · DM: 5.5 % · 12 months
  • Pig slurry: 11,880 t/yr · DM: 5.5 % · 12 months
  • Electricity: 3,000,000 kWh/yr · Electricity price on your bill (if known): 3 MXN/kWh
  • No heat needed
  • Land available for spreading digestate: 200 ha · Distance to the gas grid (for biomethane): —
  • Existing lagoon / store that could be covered: 40,000 m³
  • Grid connection? Yes

What to verify

Confirm the CFE tariff, generator operation and maintenance, H₂S control and how the lagoon effluent is handled given the karst aquifer.

Possible with conditions

It can pay off, but only if the key conditions hold — confirm them in a feasibility study.

  • Base NPV positive (US$940K), payback ≈ 5.0 yrs.
  • Conservative-case NPV is negative (-US$290K) — sensitive to key assumptions.

Largest benefit — “electricity savings (self-consumption)”: ≈ 88 % of all revenue and savings.

What would change the verdict
  • → Secure long-term heat and power offtake; benchmark CAPEX with 3–5 suppliers.

Subsidies and tariffs excluded from the verdict. Preliminary screening, not an engineering design.

How firm is this answer?

Grey zone: the answer flips between the conservative and the optimistic case. Before paying for a feasibility study, check these first:

NPV: conservative -US$290K · base US$940K · optimistic US$1.5M

The conservative case stacks every adverse assumption at once: a stress test, not the likely outcome. In 160 likely combinations the NPV was positive in > 99 % of cases.

  1. Feedstock potential −20 % (-US$500K)
  2. Get an offer for exported power (PPA or tariff) · Energy prices −20 % (-US$490K)
  3. Lab test of the methane yield (BMP) · CH₄ −20 % (-US$430K)

These are screening assumptions, not independently validated accuracy limits. Confirm BMP, supplier scope, grid connection and offtake terms before an investment decision.

To reach a bankable estimate (±15 %)
  1. Laboratory methane-potential (BMP) test of 2–3 feedstock samples — ≈ US$336–US$895 each
  2. 2–3 supplier quotes for the plant
  3. Grid or gas-network connection conditions from the operator
  4. Letters of intent for feedstock supply and for heat, power or biomethane offtake
  5. Then a feasibility study with permits and financing (±15 %)
From screening to construction

Key figures

Ranges: conservative — base — optimistic. We don't show fake precision.

Economics

Preliminary investment
US$950K – US$1.3M
≈ MX$20M (base)
Payback
3.6 yr – 12 yr
base: 5 yr · no subsidies
NPV (base)
US$940K
range: -US$290K … US$1.5M
Chosen route
CHP (power + heat)
Confidence: Medium

1 EUR = 1.1193 USD · ECB · 2026-11-09

Feedstock and energy

Feedstock potential
45,000 t/yr
energy ≈ 122 kWh CH₄/t
Biogas
700K – 970K Nm³/yr
≈ 112 Nm³/h (base)
Net energy
1,400 – 2,000 MWh/yr
useful heat: 0 MWh · ≈ 62 % of your electricity use
Candidate capacity
260 kWe
medium (0.25–1 MW)

How far you can rely on these numbers

Medium · 67/100
  • Backed by your data and our sources67
  • You can still add+23
  • Needs a feasibility study (lab, quotes, contracts)10

67/100: how much of what a screening can know about this project rests on your data and current sources. A missing input costs points in proportion to how far it could still move your result.

What you can add

  • Biggest gainLaboratory DM, VS and BMP results for every feedstock streamLarge effectSend a sample to a laboratory: dry matter and VS take a few days, BMP several weeksValues equal to the typical ones shown in the form do not count as a laboratory result.+15
  • Route-specific CAPEX lacks independent local validation — obtain comparable supplier quotations+8

With all of it: up to 90/100

High requires verified laboratory and project documents, so a screening stops at 90/100.

Model warnings
  • In this configuration the digestate is a cost rather than an asset.
  • CHP performance uses a 60 Hz biogas full-load catalogue reference (04/2025), interpolated between ratings; part-load and ambient derating require supplier confirmation.
  • Both digester types were assessed for this liquid feed and climate. Chosen: Covered anaerobic lagoon (unheated, ambient temperature) (NPV US$940K); alternative: Wet mesophilic digestion (CSTR) (NPV -US$190K, CAPEX US$2M). A covered lagoon is cheaper but gives ≈ 100 % of a heated tank's gas (EPA AgSTAR) and needs land.
Compared with the market
Our estimate: ≈ 4,100 USD/kW at ≈ 260 kW
  • 8,954–11,193 USD/kW — Cattle-manure plant, IEA Task 37 · below rangeIEA Bioenergy Task 37, presentation by P. Kornatz (DBFZ): ≈ €1.81 m for 200 kW · ≈2022–2023 · Single project
  • 3,806–8,395 USD/kW — Flexible plant, Germany · within rangeDBFZ / Fraunhofer IEE for BMWK (February 2024): €7,521 per kW rated (≈ €3,400 per kW installed) capacity · 2023 · Official study

Market figures are mostly trade press and supplier estimates, not audited budgets. Real prices come from 3–5 supplier quotes.

Country conditions
  • Warm climate allows covered lagoons for pig and dairy effluent.

Action plan: what would make it stronger

Changes tested on this project with the same model. Break-even values show how far each must go; the scenario assumptions are LOW-confidence judgements to replace with offers.

What separates this project from “Strong candidate”
  • The conservative case must stay profitable too (its NPV is -US$290K).
ChangeVerdictNPV (base)Δ NPVBreak-even
Sell the spare heat
A year-round heat buyer (drying, process heat, greenhouse or district heating) for ≈ 2,000 MWh a year, valued at ≈ MX$0.393 per kWh.
Possible with conditionsUS$1.3M+US$310Kheat ≥ MX$0.0878 per kWh
Pool manure with neighbours
100 % more manure from neighbouring farms, trucked ≈ 5 km, into one shared plant.
Possible with conditionsUS$450K-US$490K—
Take in food waste
≈ 4,200 t a year of source-separated food waste from ≈ 15 km away, with a gate fee of MX$130 per tonne.
Possible with conditionsUS$320K-US$630Kgate fee ≥ MX$425 per tonne
Order of action
  1. 1Find a heat buyer for ≈ 2,000 MWh a year (heat ≥ MX$0.0878 per kWh).
  2. 2Ask 3–5 suppliers for quotes: the project breaks even up to an investment of US$1.9M. →
Scenario assumptions
  • Co-substrate share of the organic matter (VS) after it is added: 30 % · ASSUMPTION · LOW · 2026-11-02 · Judgement: usual co-digestion share at manure plants; the model applies pasteurisation, rejects and inhibition checks to the new mix.
  • Haul distance of the co-substrate: 15 km · ASSUMPTION · LOW · 2026-11-02 · Judgement: food processors within a regional collection radius.
  • Gate fee received for source-separated food waste: US$6.72/t · ASSUMPTION · LOW · 2026-11-02 · Judgement, deliberately low. WRAP UK Gate Fees Report 2025/26 (3 July 2026): AD gate fees fell from 2024/25 and several councils paid £0 or less. The paid report gives the gate fee at which the scenario breaks even.
  • Haul distance of the neighbours' feedstock: 5 km · ASSUMPTION · LOW · 2026-11-02 · Judgement: neighbouring farms within a few kilometres; slurry hauled much further rarely pays (see the maximum distance per stream).

What to verify first

Inputs ranked by what exact knowledge is worth before you decide (expected value of perfect information). Each range is tested on its own; inputs you already supplied are not listed.

CheckNPV across the plausible rangeWorth knowing
Check how your bill splits energy and capacity chargesUS$510K … US$1.4M—
Get supplier quotes for the plantUS$570K … US$1.3M—
Verify the market priceUS$700K … US$1.1M—
Check the fertiliser value of the digestateUS$870K … US$1.1M—
How to check: Check how your bill splits energy and capacity charges
  1. Take the last 12 electricity invoices.
  2. Split each into the energy part (per kWh) and capacity, network and fixed charges; own generation saves mainly the energy part.

Then enter it in: Energy step: electricity price per kWh (energy part, excl. VAT)

How to check: Get supplier quotes for the plant
  1. Send the same request to at least three suppliers.
  2. Compare like for like: scope, exclusions, guaranteed gas output, own power use, availability and the O&M price.
Request to send
Request for quotation: turnkey biogas plant
Site: Mexico.
Feedstock (screening values, to be confirmed):
- pig slurry: 33,000 t/year, DM ≈ 5.5 %
- pig slurry: 12,000 t/year, DM ≈ 5.5 %
Design basis from the screening: raw biogas ≈ 110 Nm³/h at ≈ 62 % CH₄; digester working volume ≈ 5,200 m³; combined heat and power ≈ 260 kWe; new digestate storage ≈ 0 m³.
Please quote turnkey: feeding, digester(s), gas system with flare and desulphurisation, the gas-use equipment above, electrical and I&C, civil works, engineering and commissioning. List exclusions (grid connection, permits, land, digestate storage if separate). State the guaranteed gas output, own power and heat use, availability and the price of a full O&M contract.

Then enter it in: Step 3, “Optional: contracts and financing”: supplier quote and its technology

How to check: Verify the market price
  1. Check the official source shown for this price in the market-data table and compare it with your own contract.

Then enter it in: Energy step: your own price, if you have a contract

How to check: Check the fertiliser value of the digestate
  1. Ask neighbouring farms what they would pay per tonne of digestate, delivered and spread.
  2. Check the land available for spreading against the nitrogen limit.

Then enter it in: Site step: land available for digestate

Break-even prices

Each value on its own brings the base-case NPV to zero; everything else stays as calculated.

Electricity value at NPV = 0
US$0.0842/kWh
now US$0.137/kWh
Highest installed cost at NPV = 0
US$1.9M
now US$1.1M
Feedstock price headroom
US$2.06/t
can pay up to US$2.06 per tonne more for every input

Probability range (Monte Carlo)

160 draws of the scenario quantities (yield, dry matter, CAPEX, prices, heat use, operating hours…). Energy and biomethane prices move together, the rest independently. Not a forecast: it shows how often the project stays positive when the uncertainties do not all go wrong at once.

NPV P10 (1 in 10 worse)
US$450K
Median NPV
US$710K
NPV P90 (1 in 10 better)
US$930K
Chance that NPV > 0
> 99 %
Median payback
5.7 yr

Reality check: on 39 German farm plants with metered feed and methane (FNR Biogas-Messprogramm III), measured output was 1–1.3 × this model's estimate for 8 in 10 plants. The model sizes the plant itself and stays on the cautious side; with feedstock that is not lab-tested, one plant can still miss by more.

What could break the economics

Each stress test applied to the base case on its own.

Change in NPV vs base, USD (base: 940K)

  1. Feedstock potential −20 %-500K
  2. Energy prices −20 %-490K
  3. CH₄ −20 %-430K
  4. CHP downtime +10 pp-250K
  5. CAPEX +20 %-250K
  6. Maintenance +30 %-170K
  7. Useful heat (economic) −50 %0
  8. Feedstock transport +50 %0
NPV = 0 if CAPEX falls by
already positive
grant, leasing, cheaper equipment
NPV = 0 if energy prices rise by
already positive
relative to the base case

Scenarios

Route: CHP (power + heat). Scenarios bundle consistent assumptions (lower yield comes with higher CAPEX).

Revenue + savings / yrUS$290K
  • Electricity self-consumption savings250K
  • Incremental digestate value34K
OPEX / yrUS$76K
  • CHP service and overhaul reserve44K
  • Maintenance13K
  • Staff9.3K
  • Testing and monitoring5.6K
Operating margin (EBITDA)US$210K
ScenariosConservativeBaseOptimistic
Biogas, 1 000 Nm³/yr703.2894965.5
CAPEXUS$1.3MUS$1.1MUS$950K
OPEX / yrUS$80KUS$76KUS$73K
Revenue + savings / yrUS$190KUS$290KUS$340K
Operating margin (EBITDA)US$110KUS$210KUS$260K
Simple payback12 yr5 yr3.6 yr
Discounted paybackno payback6.7 yr4.7 yr
NPV-US$290KUS$940KUS$1.5M
IRR4 %18.9 %26.7 %
DSCR (min)0.92.33.1

Pre-tax, nominal USD, 15-year horizon, discount rate of the country or your own; a screening estimate, not a bankable feasibility study. DSCR = EBITDA ÷ debt service at 50 % debt (no taxes).

Cumulative cash flow, USD
-1.6M-220K1.1M2.4M3.8M03691215yearsConservativeBaseOptimistic

Biogas use routes compared

Base case. The model picks the route with the best NPV among technically sensible ones.

RouteCAPEXEBITDA / yrPaybackNPV (base)NPV low…high
CHP (power + heat) chosenUS$1.1MUS$210K5 yrUS$940K-US$290K … US$1.5M
Boiler (heat only) US$520K-US$22Kno payback-US$750K-US$1.1M … -US$580K
Biomethane US$1.9MUS$81K23.6 yr-US$1.2M-US$2.9M … US$300K
  • CHP pays when you use the power yourself and the heat is really used.
  • Biomethane: raw biogas ≈ 110 Nm³/h. The smallest upgrading units take ≈ 50–100 Nm³/h, and the cost per Nm³ falls steeply with size, so a small plant pays much more for each unit of gas.

Plant size

The same feedstock mix at other sizes, each option re-sized by the model. Extra feedstock is assumed on your terms (price, transport, disposal saving); CAPEX is the model's estimate, not your quote.

Sizet/yrBest optionkWeCAPEXNPV (base)
× 0.5 23,000CHP (power + heat)120US$610KUS$200K
× 0.75 34,000CHP (power + heat)190US$840KUS$560K
× 1 your input45,000CHP (power + heat)260US$1.1MUS$940K
× 1.5 68,000CHP (power + heat)400US$1.5MUS$1.5M
× 2 90,000CHP (power + heat)530US$1.9MUS$1.3M
× 3 140,000CHP (power + heat)860US$2.7MUS$1.1M

National support schemes — separate cases

Not in the verdict: tariffs get cut, auctions fail, grant calls close. Status and source shown for each.

Bottom line

There is no support for new projects that we could calculate — see the country overview

No support scheme for new projects is modelled for this country.

Country overviewchecked 30 Oct 2026

No operating support for biogas; the 2025 Electricity Sector Law raises the distributed-generation threshold to 0.7 MW and simplifies self-supply permits.

Support never changes the verdict. Each case is pre-tax, uses the scheme's published terms and assumes the support is awarded; it does not confirm eligibility or promise funding.

Where the energy goes

Heat produced ≠ useful heat. Heat without a user isn't income.

34/100

Of every 100 kWh of energy in the methane, 34 become a product that earns money or replaces a purchase.

100 % = 5,500 MWh of methane energy a year (LHV), base case. Every figure in this block is calculated by the model from your inputs.

Stream by stream

Calculated

Earns money

  • Electricity used on site1,900 MWh 34 %

Runs the plant

  • Plant’s own electricity170 MWh 3 %

Produced, not used

  • Heat with no buyer2,500 MWh 45 %

Losses

  • Conversion losses (engine, boiler)890 MWh 16 %
  • Gas sent to the flare52 MWh 0.9 %
  • Methane leaks83 MWh 1 %

What this means for the project

  • 2,500 MWh of heat a year has no buyer. A heat user nearby (drying, a greenhouse, process heat, a heating network) would turn it into income.
  • Methane leaks are 2 % of production in the base case: lost income and a greenhouse gas. Gas-tight digestate storage and regular leak checks keep them low.

What the figures rest on

Engine efficiency: electricity / heat
38 % / 50 %Assumption
Heat need
no heat userYour data
Site electricity use
3,000 MWhYour data
Methane leaks, base case
2 %Assumption
Main product, conservative – optimistic
1,400 – 2,000 MWhCalculated

How it works: from feedstock to products

  1. Feedstock45,000 t/yr
  2. Biogas890K Nm³/yr
  3. Electricity1,900 MWh
  4. Useful heat0 MWh
  5. Heat without demand2,500 MWh
  6. Digestate44,000 t/yr
Heat produced (gross)
2,470 MWh
Digester heat demand
0 MWh
Useful heat (economic)
0 MWh of 2,470
Power: own use / sold
1,857 / 0 MWh

Climate case (EU RED method)

EU Renewable Energy Directive default values for your feedstock mix, digestate storage and route. Separate from the verdict; outside the EU an indicative benchmark. Credits are valued only in the support cases where an official mechanism exists.

Emissions of the product
-223 g CO₂e/MJ
gas-tight digestate storage
Fossil comparator
183 g CO₂e/MJ
Greenhouse-gas saving
222 %
RED minimum: 80 %
Avoided emissions
2,714 t CO₂e
  • Meets the RED minimum.
  • Below 2 MW rated input the RED criteria do not apply by law; buyers and schemes may still ask for them.

Scores by dimension

No single magic number. The overall score comes with its explanation.

Feedstock fit
79/100
  • Energy equivalent ≈ 260 kWe (scale score 84/100)
  • Feedstock energy ≈ 122 kWh of methane per tonne (score 26/100)
  • Feedstock available 12 of 12 months
Energy fit
43/100
  • Own consumption absorbs 100 % of the electricity produced
  • Useful heat 0 MWh of 2470 MWh available after digester needs
Location & logistics
75/100
  • Not enough land for the digestate
Technical feasibility
100/100
  • Standard layout for this scale, no critical obstacles
Economics
88/100
  • Base-case simple payback ≈ 5.0 years
Regulatory complexity
5/100 risk
  • Number and weight of permitting / regulatory steps: 6 points (more = harder)
Environmental risk
39/100 risk
  • Expected methane loss 2.5 % (good practice ≤ 2 %)
  • Surplus digestate: risk of nitrogen over-application
Overall project viability
78/100
  • Weighted: economics 30 %, feedstock 20 %, energy 15 %, technical 10 %, location 10 %, regulatory 7.5 %, environment 7.5 %.
  • Strongest: Technical feasibility (100); weakest: Energy fit (43).

Calculation details

Feedstock & logistics
Streamt/yrDM, %Nm³ CH₄/tLogistics / energyMax. distance
Pig slurry33,2505.512.3on site≈ 23 km
Pig slurry11,8805.512.3on site≈ 23 km

Max. distance = where haulage eats half of a tonne's energy value. Low-energy feedstock (slurry) belongs next to the plant.

Technology & digester

Covered anaerobic lagoon (unheated, ambient temperature)

Lined lagoon with HDPE gas-tight cover, sludge removal and gas collection

Working volume
≈ 5,200 m³
Retention time
42.4 days
Loading rate
1 kg VS/(m³·d)
Digestate storage
≈ 3,700 m³
  • Warm climate (annual mean ≈ 27 °C) and a liquid feed (5.5 % DM): an unheated covered lagoon is the lowest-cost proven option.
  • Continuous feed — continuous operation gives steady gas and the simplest control.
  • Single stage plus a gas-tight digestate store as post-digester: sufficient at this scale.
Alternatives
  • Heated CSTR or UASB for higher, steadier gas yield per m³

Climate: Yucatán (Mérida), mean 26.9 °C, ≈ 0 heating degree-days. Closest climate analogues: Dresden (DE, east) (Δ 17.5 °C), Prague (CZ) (Δ 17.9 °C), Copenhagen (DK) (Δ 17.9 °C).

Monthly energy balance

Base case, chosen route. Gas energy is usable methane energy (LHV) after losses.

MonthFeedstock, tGas energy, MWhDigester heat, MWhUseful heat, MWhNet electricity, MWh
Jan3,83046200158
Feb3,49142100144
Mar3,83046200158
Apr3,70744700152
May3,83046200158
Jun3,70744700152
Jul3,83046200158
Aug3,83046200158
Sept3,70744700152
Oct3,83046200158
Nov3,70744700152
Dec3,83046200158
Σ45,1305,443001,857
CAPEX, OPEX, revenue (base case)
CAPEX (USD)
Digester160K
Covering existing storage96K
Feedstock reception and preparation22K
Gas handling and cleaning38K
CHP (power + heat)430K
Electrical systems and controls45K
Pipework30K
Civil works45K
Grid connection31K
Engineering and permits71K
Contingency96K
Total1.1M
OPEX / yr (USD)
Staff9.3K
CHP service and overhaul reserve44K
Maintenance13K
Insurance5.3K
Testing and monitoring5.6K
Total76K
Revenue + savings / yr (USD)
Electricity self-consumption savings250K
Incremental digestate value34K
Total290K

Unit costs are estimates. Replace them with supplier quotations.

Digestate: asset or liability

Status: liability / cost · 44,061 t/yr · nitrogen ≈ 214,368 kg/yr · land needed ≈ 1,261 ha (available 200 ha).

Incremental fertiliser value US$34K/yr, handling US$0/yr, net US$34K/yr.

  • Not enough land: ≈ 1261 ha needed at 170 kg N/ha. Surplus digestate is a cost (agreements with neighbours, separation, pelletising).
  • Digestate storage for 3 months for the closed spreading season; keep ≈ 150 days (incl. the digester) gas-tight, otherwise methane and N are lost.
  • Spread by injection or trailing hose (not splash plate): less odour and ammonia loss.
Methane losses & climate

Expected losses: 2.5 % of methane produced (range 1.5 % – 4 %) ≈ 268 t CO₂e/yr; fossil emissions displaced ≈ 880 t CO₂/yr. Losses vs benefit: 30 %.

  • Expected loss 2.5 % is above good practice (2 %): budget for monitoring.
  • Gas-tight covers on the digester and digestate storage (incl. lagoon covers) — the single most important measure.
  • Leak detection and repair (LDAR): optical gas imaging or tracer method at least yearly, plus an acceptance test after construction.
  • Continuous gas-holder pressure monitoring; a standby flare instead of venting.
  • CHP with an oxidation catalyst and tuning regime to cut methane slip.

Avoided emissions from open manure storage are not credited (conservative).

Permits & regulation (indicative)

Complexity: lower. “To verify” means a local lawyer or engineer must confirm the item during the feasibility study.

  • Construction permit and national environmental approval / EIA screening
    New installation · effort: medium · to verify
  • Gas-safety approval and hazardous-area classification (IECEx or national code)
    Methane in the gas phase · effort: medium · to verify
  • Effluent / digestate discharge or land-application permit
    Digestate or treated effluent leaves the site · effort: medium · to verify
Safety (risk register)
  • Methane: explosion and fire (flammable range ≈ 5–15 % in air) high
    • Hazardous-area (ATEX/IECEx or national) zoning and suitably rated equipment
    • Fixed gas detectors in the CHP room and near tanks
    • Flame arresters, over/under-pressure relief, safety flare
    • Ignition-source control and hot-work permits
  • Hydrogen sulphide (H₂S): acute toxicity, corrosion high
    • Biological / chemical desulphurisation of the biogas
    • Personal H₂S monitors, no lone working
    • H₂S monitoring upstream of the CHP (engine protection)
  • Confined spaces (digester, storage, pits): asphyxiation, toxic gases high
    • Entry only under permit, ventilation, standby person
    • Self-contained breathing apparatus for rescue
  • Over/under-pressure: membrane roof rupture, tank deformation medium
    • Liquid seals / relief valves venting to a safe location
    • Gas-holder level and pressure sensors
  • CHP: carbon monoxide, fire, high temperatures medium
    • CHP room ventilation, CO detectors
    • Emergency stop, fire suppression
  • Soil and water pollution: slurry/digestate spills, lagoon overflow high
    • Bund sized for the largest tank
    • Level sensors and a spill-response plan
    • Digestate storage covering the closed spreading season

Software does NOT replace a qualified process engineer and a process-safety engineer. Every final engineering design, hazardous-area classification and safe-operation programme must pass human professional review.

Assumptions used (145)

Every number has a source, date, country and confidence, and is tagged FACT / ASSUMPTION / CALCULATION / ESTIMATE. Full register: →

  • Support: No operating support for biogas; the 2025 Electricity Sector Law raises the distributed-generation threshold to 0.7 MW and simplifies self-supply permits.
  • Warm climate allows covered lagoons for pig and dairy effluent.
  • The verdict excludes subsidies; national support is shown as separate cases.
  • This is a preliminary (screening) assessment — not a detailed engineering design and not a commercial offer.
  • Financial results are pre-tax project cash flows. Depreciation, income taxes, working capital, financing fees and detailed debt covenants are not modelled; DSCR is an EBITDA-based screening ratio, not lender CFADS.
  • Parameter bounds are tested individually using the applicable market/CAPEX evidence. These engineering or tariff ranges are not statistical confidence intervals and do not replace supplier quotations or customer bills.

What could break the economics

Each stress test applied to the base case on its own.

chp: local CAPEX factor
0.546 … 1.014 —
NPV low…high: US$570K … US$1.3M
Discount rate (nominal, pre-tax, EUR-equivalent, incl. country risk)
0.066 … 0.096 —
NPV low…high: US$700K … US$1.1M
Mineral potassium price
0.7981 … 0.9065 USD/kg K₂O
NPV low…high: US$940K … US$940K
Mineral nitrogen price
1.17 … 2.035 USD/kg N
NPV low…high: US$870K … US$1.1M
Mineral phosphorus price
1.588 … 2.068 USD/kg P₂O₅
NPV low…high: US$940K … US$940K
Avoidable share of an unsplit customer electricity bill
0.7 … 1 —
NPV low…high: US$510K … US$1.4M
Every number has a source, date, country and confidence, and is tagged FACT / ASSUMPTION / CALCULATION / ESTIMATE. Full register:
Biomethane price without support, base: 0.4477 USD/Nm³ · CALCULATED_VALUE · LOW
National estimate (project team, 2026-10) — no official series found for this item; your own price overrides it; local market for biomethane / RNG without credits
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
chp: local CAPEX factor: 0.78 — · CALCULATED_VALUE · LOW
0.72 traded equipment + 0.28 × local/German labour cost (6.7/31.5 €/h); split after DBFZ/Fraunhofer 2024; supplier quotes needed
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Debt interest rate (EUR-equivalent): 0.061 — · CALCULATED_VALUE · MEDIUM
Discount rate − 1.5 pp (senior debt is cheaper than blended project capital); consistent with ECB MIR corporate loan rates + project margin; a bank term sheet replaces this
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Debt share for DSCR test: 0.5 — · ENGINEERING_ASSUMPTION · MEDIUM
Typical agri / project lending (KfW, EBRD, IFC practice)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Debt tenor: 7 a · ENGINEERING_ASSUMPTION · MEDIUM
Typical
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Digestate that has no adequate land: 4.444 USD/t · CALCULATED_VALUE · MEDIUM
Third-party export of digestate ≈ 2.5 €/t + 0.22 h/t × labour; ≈ 12 €/t in Germany, in line with manure-exchange prices in surplus regions (LWK Niedersachsen Nährstoffbericht: 10–20 €/t)
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Incremental digestate handling on adequate land: 1.948 USD/t · CALCULATED_VALUE · MEDIUM
Pumping & trailing-hose spreading ≈ 1.2 €/t machinery + 0.08 h/t × labour; ≈ 4.8 €/t in Germany, in line with KTBL contractor rates (3–6 €/m³)
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Discount rate (nominal, pre-tax, EUR-equivalent, incl. country risk): 0.076 — · CALCULATED_VALUE · MEDIUM
Nominal, pre-tax, EUR-equivalent: 6.0 % mature-market WACC + 0.6 × country risk premium 2.72 % (Baa3; Damodaran, 2026-07); not a bank offer
2026-07-01 · checked 2026-10-27 · Rating-based CRP; baseline WACC and lambda are engineering/financial assumptions
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Wholesale electricity price (market average): 0.04085 USD/kWh · CALCULATED_VALUE · MEDIUM
CENACE day-ahead market (MDA) zonal prices (PND), unweighted mean of 96 SIN load zones, Oct 2025 – Sep 2026: 760.45 MXN/MWh; converted at 20.8343 MXN/EUR (2026-11-09)
2026-09-30 · checked undated · Historical national/regional reference; latest publication and customer applicability require verification
WITHIN_REVIEW_WINDOW: Within the 60-day review policy; applicability and latest publication must still be checked
Documented nominal reference (may include estimated adders): 0.7605 MXN (ENGINEERING_ASSUMPTION); FX (2026-11-09): 20.83 MXN/EUR (MARKET_DATA)
Annual escalation of energy prices (nominal EUR): 0.02 — · ENGINEERING_ASSUMPTION · MEDIUM
At the ECB/Fed inflation target — no real energy-price growth assumed (conservative)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Share of the wholesale price realised for surplus power: 0.85 — · ENGINEERING_ASSUMPTION · MEDIUM
15 % profile & balancing discount for a small seller (assumption, same for all markets)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Mineral potassium price: 0.8519 USD/kg K₂O · CALCULATED_VALUE · MEDIUM
World Bank Pink Sheet, 12-month mean 2025M10–2026M09; ÷ nutrient share × 1.35 farm-gate markup
2025M10 / 2026M09 · checked 2026-10-27 · World commodity reference; actual digestate nutrient substitution and local fertiliser price require confirmation
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Trailing-year commodity reference: 378.6 USD/t product (MARKET_DATA); Latest-month reference (2026-09): 367.5 USD/t product (MARKET_DATA); FX (2026-11-09): 1.119 USD/EUR (MARKET_DATA); Farm-gate markup: 1.35 — (ENGINEERING_ASSUMPTION)
Mineral nitrogen price: 1.489 USD/kg N · CALCULATED_VALUE · MEDIUM
World Bank Pink Sheet, 12-month mean 2025M10–2026M09; ÷ nutrient share × 1.35 farm-gate markup
2025M10 / 2026M09 · checked 2026-10-27 · World commodity reference; actual digestate nutrient substitution and local fertiliser price require confirmation
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Trailing-year commodity reference: 507.3 USD/t product (MARKET_DATA); Latest-month reference (2026-09): 407.5 USD/t product (MARKET_DATA); FX (2026-11-09): 1.119 USD/EUR (MARKET_DATA); Farm-gate markup: 1.35 — (ENGINEERING_ASSUMPTION)
Mineral phosphorus price: 1.878 USD/kg P₂O₅ · CALCULATED_VALUE · MEDIUM
World Bank Pink Sheet, 12-month mean 2025M10–2026M09; ÷ nutrient share × 1.35 farm-gate markup
2025M10 / 2026M09 · checked 2026-10-27 · World commodity reference; actual digestate nutrient substitution and local fertiliser price require confirmation
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Trailing-year commodity reference: 639.8 USD/t product (MARKET_DATA); Latest-month reference (2026-09): 690 USD/t product (MARKET_DATA); FX (2026-11-09): 1.119 USD/EUR (MARKET_DATA); Farm-gate markup: 1.35 — (ENGINEERING_ASSUMPTION)
Exchange rate: 18.61 MXN/USD · MARKET_DATA · HIGH
Official EUR reference rate, 2026-11-09
2026-11-09 · checked 2026-11-10 · MXN per EUR; dated reference, not a guaranteed transaction rate
WITHIN_REVIEW_WINDOW: Within the 7-day review policy; applicability and latest publication must still be checked
Value of useful heat (displaced gas / boiler efficiency): 0.02109 USD/kWh th · CALCULATED_VALUE · MEDIUM
Business gas 16.95792012865184 €/MWh LHV ÷ 0.9
2025-12-31 · checked undated · Historical national/regional reference; latest publication and customer applicability require verification
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Documented nominal reference (may include estimated adders): 17.1 USD (ENGINEERING_ASSUMPTION); FX (2026-11-09): 1.119 USD/EUR (MARKET_DATA)
Evaluation horizon: 15 a · ENGINEERING_ASSUMPTION · MEDIUM
Shorter than the 20-year technical life — conservative
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Official hourly labour cost, economy-wide (wages + employer costs): 7.546 USD/h · CALCULATED_VALUE · MEDIUM
IMSS/STPS: average daily contribution salary Sep 2026 666.0 MXN × 365 × 1.30 employer contributions ÷ 2 250 h; converted at 20.8343 MXN/EUR (2026-11-09)
2026-09-30 · checked undated · Historical national/regional reference; latest publication and customer applicability require verification
WITHIN_REVIEW_WINDOW: Within the 730-day review policy; applicability and latest publication must still be checked
Documented nominal reference (may include estimated adders): 140.5 MXN (ENGINEERING_ASSUMPTION); FX (2026-11-09): 20.83 MXN/EUR (MARKET_DATA)
Plant operator wage relative to the economy-wide average: 1 — · ENGINEERING_ASSUMPTION · MEDIUM
Plant operator ≈ economy-wide average (middle-income economy; no premium)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Annual escalation of operating costs (nominal EUR): 0.025 — · ENGINEERING_ASSUMPTION · MEDIUM
Inflation target + 0.5 pp wage drift
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Road transport of organic feedstock: 0.08954 USD/(t·km) · CALCULATED_VALUE · MEDIUM
0.06 €/t·km vehicle & fuel + 0.003 × driver labour cost (€/h); matches KTBL slurry haulage ≈ 0.12–0.16 €/t·km in Germany
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Loading/unloading per tonne: 0.8171 USD/t · CALCULATED_VALUE · MEDIUM
0.6 €/t pump & loader + 0.02 h/t × labour cost (KTBL Betriebsplanung machine-cost norms, scaled by national labour cost)
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Avoidable share of an unsplit customer electricity bill: 0.85 — · ENGINEERING_ASSUMPTION · LOW
Engineering judgement, no published value: energy share of an unsplit bill; customer tariff sheet takes precedence
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Customer electricity price (invoice split not verified): 0.1612 USD/kWh · USER_INPUT · MEDIUM
USER_INPUT 3 MXN/kWh / FX 20.8343; Official EUR reference rate, 2026-11-09. Invoice date not supplied; energy/demand split assumed separately.
REVIEW_REQUIRED: Customer input; invoice date, contract and validity not independently verified
pig_slurry: dry matter: 5.5 % FM · MEASURED · MEDIUM
MEASURED laboratory report; replaces the catalogue value for this stream. Not independently verified.
REVIEW_REQUIRED: Customer measurement; sample, date and laboratory not independently verified
pig_slurry: volatile solids: 77 % DM · MEASURED · MEDIUM
MEASURED laboratory report; replaces the catalogue value for this stream. Not independently verified.
REVIEW_REQUIRED: Customer measurement; sample, date and laboratory not independently verified
pig_slurry: BMP (scenarios ± inter-laboratory spread): 290 L CH₄/kg VS · MEASURED · MEDIUM
MEASURED laboratory BMP test; replaces the catalogue value for this stream. Not independently verified.
REVIEW_REQUIRED: Customer measurement; sample, date and laboratory not independently verified
pig_slurry: dry matter: 5.5 % FM · MEASURED · MEDIUM
MEASURED laboratory report; replaces the catalogue value for this stream. Not independently verified.
REVIEW_REQUIRED: Customer measurement; sample, date and laboratory not independently verified
pig_slurry: volatile solids: 77 % DM · MEASURED · MEDIUM
MEASURED laboratory report; replaces the catalogue value for this stream. Not independently verified.
REVIEW_REQUIRED: Customer measurement; sample, date and laboratory not independently verified
pig_slurry: BMP (scenarios ± inter-laboratory spread): 290 L CH₄/kg VS · MEASURED · MEDIUM
MEASURED laboratory BMP test; replaces the catalogue value for this stream. Not independently verified.
REVIEW_REQUIRED: Customer measurement; sample, date and laboratory not independently verified