Sample report · Ukraine

Layer farm, 200 000 hens

A sample Extended Report for a modelled project. Your report has the same structure (the Standard Report has fewer sections) and uses your own data.

Business situation

A Ukrainian egg producer with 200,000 layers considers mono-digestion of poultry manure. High solids and nitrogen make this an operating-risk case.

Operating assumptions

  • Laying hens: 200,000
  • Electricity: 2,200,000 kWh/yr · Electricity price on your bill (if known): 8.5 UAH/kWh
  • Winter: space heating · Heat needed per year (if known): 600,000 kWh/yr
  • Land available for spreading digestate: 500 ha · Distance to the gas grid (for biomethane): 4 km
  • Grid connection? Yes

What to verify

Analyse TAN, free ammonia, grit and BMP; pilot-test loading and dilution. Quote ammonia management and digestate export before procurement.

Weak economics

Under current conditions the investment won't pay back in a reasonable time. Below is what could change that.

  • Simple payback ≈ 18.0 yrs; base NPV -€810K (well below zero at the country discount rate).
  • Even the optimistic case has a negative NPV (-€510K).

Main reason — small scale: the feedstock supports only ≈ 90 kW, while the plant costs ≈ €13K per kW. Digester, storage and CHP are expensive even at small capacity.

What would change the verdict
  • → NPV = 0 with ≈ 59 % lower CAPEX (or an equivalent grant).
  • → NPV = 0 with ≈ 118 % higher energy prices.

Subsidies and tariffs excluded from the verdict. Preliminary screening, not an engineering design.

How firm is this answer?

A clear no under these conditions: even the optimistic case does not pay back. Don't spend money on a feasibility study unless one of the changes above happens.

NPV: conservative -€1.4M · base -€810K · optimistic -€510K

The conservative case stacks every adverse assumption at once: a stress test, not the likely outcome. In 160 likely combinations the NPV was positive in < 1 % of cases.

These are screening assumptions, not independently validated accuracy limits. Confirm BMP, supplier scope, grid connection and offtake terms before an investment decision.

Key figures

Ranges: conservative — base — optimistic. We don't show fake precision.

Economics

Preliminary investment
€1.1M – €1.4M
≈ UAH 61M (base)
Payback
11.4 yr – > 25 yr
base: 18 yr · no subsidies
NPV (base)
-€810K
range: -€1.4M … -€510K
Chosen route
CHP (power + heat)
Confidence: Low

Feedstock and energy

Feedstock potential
6,900 t/yr
energy ≈ 296 kWh CH₄/t
Biogas
260K – 390K Nm³/yr
≈ 43 Nm³/h (base)
Net energy
470 – 670 MWh/yr
useful heat: 160 – 380 MWh · ≈ 29 % of your electricity use
Candidate capacity
90 kWe
small (50–250 kW)

How far you can rely on these numbers

Low · 55/100
  • Backed by your data and our sources55
  • You can still add+35
  • Needs a feasibility study (lab, quotes, contracts)10

55/100: how much of what a screening can know about this project rests on your data and current sources. A missing input costs points in proportion to how far it could still move your result.

What you can add

  • Biggest gainLaboratory DM, VS and BMP results for every feedstock streamLarge effectSend a sample to a laboratory: dry matter and VS take a few days, BMP several weeks+27
  • Route-specific CAPEX lacks independent local validation — obtain comparable supplier quotations+8

With all of it: up to 90/100

High requires verified laboratory and project documents, so a screening stops at 90/100.

Model warnings
  • Poultry manure is 100 % of the organic matter: risk of ammonia inhibition. The model cuts the yield by 26 %; dilution or a co-substrate is needed.
  • Parameters for "laying-hen manure" have low confidence — a laboratory analysis (BMP) is needed.
  • Poultry manure: limit its share, dilute, or use ammonia stripping — otherwise the process is inhibited.
  • CHP performance uses a 50 Hz biogas full-load catalogue reference (03/2025), interpolated between ratings; part-load and ambient derating require supplier confirmation.
Compared with the market
Our estimate: ≈ 13,000 €/kW at ≈ 90 kW
  • 6,500–10,000 EUR/kW — Small manure plants, Germany · above rangeFachverband Biogas (via biomasse-nutzung.de); C.A.R.M.E.N. e.V. (updated 2025): "up to €10,000/kW is realistic"; LWK Niedersachsen: 75 kW ≈ €0.5–0.75 m (≈2014) · 2014–2025 · Trade press
  • 8,000–10,000 EUR/kW — Cattle-manure plant, IEA Task 37 · above rangeIEA Bioenergy Task 37, presentation by P. Kornatz (DBFZ): ≈ €1.81 m for 200 kW · ≈2022–2023 · Single project

Market figures are mostly trade press and supplier estimates, not audited budgets. Real prices come from 3–5 supplier quotes.

Country conditions
  • No subsidy for new small plants: the case rests on own electricity and heat, avoided disposal and energy resilience. Biomethane export to the EU (ISCC) is open to large producers.

Action plan: what would make it stronger

Changes tested on this project with the same model. Break-even values show how far each must go; the scenario assumptions are LOW-confidence judgements to replace with offers.

What separates this project from “Possible with conditions”
  • The base-case NPV is negative (-€810K).
  • Payback in the base case is 18 yr; it needs to be 10 yr or less.
ChangeVerdictNPV (base)Δ NPVBreak-even
Sell the spare heat
A year-round heat buyer (drying, process heat, greenhouse or district heating) for ≈ 220 MWh a year, valued at ≈ UAH 3.11 per kWh.
Weak economics-€720K+€84Kheat ≥ UAH 14.3 per kWh
Pool manure with neighbours
100 % more manure from neighbouring farms, trucked ≈ 5 km, into one shared plant.
Weak economics-€980K-€170K—
Take in food waste
≈ 2,800 t a year of source-separated food waste from ≈ 15 km away, with a gate fee of UAH 300 per tonne.
Weak economics-€1.1M-€250Kgate fee ≥ UAH 3,390 per tonne
Order of action
  1. 1Find a heat buyer for ≈ 220 MWh a year (heat ≥ UAH 14.3 per kWh).
  2. 2Ask 3–5 suppliers for quotes: the project breaks even up to an investment of €490K. →
Scenario assumptions
  • Co-substrate share of the organic matter (VS) after it is added: 30 % · ASSUMPTION · LOW · 2026-11-02 · Judgement: usual co-digestion share at manure plants; the model applies pasteurisation, rejects and inhibition checks to the new mix.
  • Haul distance of the co-substrate: 15 km · ASSUMPTION · LOW · 2026-11-02 · Judgement: food processors within a regional collection radius.
  • Gate fee received for source-separated food waste: €6/t · ASSUMPTION · LOW · 2026-11-02 · Judgement, deliberately low. WRAP UK Gate Fees Report 2025/26 (3 July 2026): AD gate fees fell from 2024/25 and several councils paid £0 or less. The paid report gives the gate fee at which the scenario breaks even.
  • Haul distance of the neighbours' feedstock: 5 km · ASSUMPTION · LOW · 2026-11-02 · Judgement: neighbouring farms within a few kilometres; slurry hauled much further rarely pays (see the maximum distance per stream).

What to verify first

Inputs ranked by what exact knowledge is worth before you decide (expected value of perfect information). Each range is tested on its own; inputs you already supplied are not listed.

CheckNPV across the plausible rangeWorth knowing
Get supplier quotes for the plant-€1.2M … -€390K—
Weigh or meter the manure actually collected-€1M … -€800K—
Check how your bill splits energy and capacity charges-€900K … -€710K—
Lab test of the methane yield (BMP)-€940K … -€810K—
Verify the market price-€840K … -€780K—
Confirm a reliable heat buyer and demand-€830K … -€780K—
How to check: Get supplier quotes for the plant
  1. Send the same request to at least three suppliers.
  2. Compare like for like: scope, exclusions, guaranteed gas output, own power use, availability and the O&M price.
Request to send
Request for quotation: turnkey biogas plant
Site: Ukraine.
Feedstock (screening values, to be confirmed):
- laying-hen manure: 6,900 t/year, DM ≈ 25.0 %
Design basis from the screening: raw biogas ≈ 43 Nm³/h at ≈ 60 % CH₄; digester working volume ≈ 1,400 m³; combined heat and power ≈ 90 kWe; new digestate storage ≈ 3,300 m³.
Please quote turnkey: feeding, digester(s), gas system with flare and desulphurisation, the gas-use equipment above, electrical and I&C, civil works, engineering and commissioning. List exclusions (grid connection, permits, land, digestate storage if separate). State the guaranteed gas output, own power and heat use, availability and the price of a full O&M contract.

Then enter it in: Step 3, “Optional: contracts and financing”: supplier quote and its technology

How to check: Weigh or meter the manure actually collected
  1. Count animals by group and housing period for the last 12 months.
  2. Measure slurry pit levels over 30 days (or weigh loads) and take three DM samples.

Then enter it in: Feedstock step: quantity and DM of each stream

How to check: Check how your bill splits energy and capacity charges
  1. Take the last 12 electricity invoices.
  2. Split each into the energy part (per kWh) and capacity, network and fixed charges; own generation saves mainly the energy part.

Then enter it in: Energy step: electricity price per kWh (energy part, excl. VAT)

How to check: Lab test of the methane yield (BMP)
  1. Take 3–5 subsamples of each stream over 2–4 weeks, mix them, keep them at 4 °C and deliver within 24 h.
  2. Order dry matter (DM), volatile solids (VS) and a methane potential test (BMP, VDI 4630) with the cellulose control reported.
  3. A valid test reports cellulose at 340–395 NL CH₄/kg VS; ask for a repeat otherwise.
Request to send
Request for quotation: biogas potential analysis
Site: Ukraine.
Feedstock (screening values, to be confirmed):
- laying-hen manure: 6,900 t/year, DM ≈ 25.0 %
Design basis from the screening: raw biogas ≈ 43 Nm³/h at ≈ 60 % CH₄; digester working volume ≈ 1,400 m³; combined heat and power ≈ 90 kWe; new digestate storage ≈ 3,300 m³.
Per sample please quote: dry matter (DM, % of fresh mass), volatile solids (VS, % of DM) and biochemical methane potential (BMP, NL CH₄ per kg VS) to VDI 4630, with the cellulose control result and the test duration. Please state price, turnaround time and sampling and shipping instructions.

Then enter it in: Feedstock step: DM, VS and BMP on each stream

How to check: Verify the market price
  1. Check the official source shown for this price in the market-data table and compare it with your own contract.

Then enter it in: Energy step: your own price, if you have a contract

How to check: Confirm a reliable heat buyer and demand
  1. Confirm the buyer's monthly heat demand and the temperature they need.
  2. Agree a price per kWh linked to their current fuel, and a term of at least the loan period.
Request to send
Offer of renewable heat
Site: Ukraine. A biogas plant can supply ≈ 660 MWh of heat a year (hot water, ≈ 80–90 °C) all year round. Please tell us your monthly heat use, the temperature you need, your current fuel and its price, and the price per kWh and term you would accept.

Then enter it in: Energy step: price the heat buyer pays per kWh

Break-even prices

Each value on its own brings the base-case NPV to zero; everything else stays as calculated.

Electricity value at NPV = 0
€0.344/kWh
now €0.142/kWh
Highest installed cost at NPV = 0
€490K
now €1.2M
Feedstock price headroom
€17.2/t
needs €17.2 per tonne less cost, or a gate fee, on every input

Probability range (Monte Carlo)

160 draws of the scenario quantities (yield, dry matter, CAPEX, prices, heat use, operating hours…). Energy and biomethane prices move together, the rest independently. Not a forecast: it shows how often the project stays positive when the uncertainties do not all go wrong at once.

NPV P10 (1 in 10 worse)
-€1M
Median NPV
-€920K
NPV P90 (1 in 10 better)
-€780K
Chance that NPV > 0
< 1 %
Median payback
22 yr

Reality check: on 41 operating US farm digesters, reported power output was 0.3–1.6 × this model's estimate for 8 in 10 plants (EPA AgSTAR, self-reported). Until feedstock is weighed and lab-tested, one plant can miss the forecast by that much — more than the range above shows.

What could break the economics

Each stress test applied to the base case on its own.

Change in NPV vs base, € (base: -810K)

  1. CAPEX +20 %-270K
  2. Energy prices −20 %-140K
  3. Feedstock potential −20 %-130K
  4. CH₄ −20 %-120K
  5. Maintenance +30 %-79K
  6. CHP downtime +10 pp-69K
  7. Useful heat (economic) −50 %-58K
  8. Feedstock transport +50 %0
NPV = 0 if CAPEX falls by
59 %
grant, leasing, cheaper equipment
NPV = 0 if energy prices rise by
118 %
relative to the base case

Scenarios

Route: CHP (power + heat). Scenarios bundle consistent assumptions (lower yield comes with higher CAPEX).

Revenue + savings / yr€120K
  • Electricity self-consumption savings91K
  • Useful heat (economic)19K
  • Incremental digestate value11K
OPEX / yr€54K
  • Maintenance20K
  • CHP service and overhaul reserve19K
  • Insurance6K
  • Testing and monitoring5K
Operating margin (EBITDA)€66K
ScenariosConservativeBaseOptimistic
Biogas, 1 000 Nm³/yr259.9343389.7
CAPEX€1.4M€1.2M€1.1M
OPEX / yr€62K€54K€50K
Revenue + savings / yr€72K€120K€140K
Operating margin (EBITDA)€10K€66K€94K
Simple payback> 25 yr18 yr11.4 yr
Discounted paybackno paybackno paybackno payback
NPV-€1.4M-€810K-€510K
IRR-25.2 %-1.4 %4.6 %
DSCR (min)0.10.50.9

Pre-tax, nominal EUR, 15-year horizon, discount rate of the country or your own; a screening estimate, not a bankable feasibility study. DSCR = EBITDA ÷ debt service at 50 % debt (no taxes).

Cumulative cash flow, €
-1.6M-1M-480K50K580K03691215yearsConservativeBaseOptimistic

Biogas use routes compared

Base case. The model picks the route with the best NPV among technically sensible ones.

RouteCAPEXEBITDA / yrPaybackNPV (base)NPV low…high
CHP (power + heat) chosen€1.2M€66K18 yr-€810K-€1.4M … -€510K
Boiler (heat only) €870K-€1.6Kno payback-€900K-€1.2M … -€720K
Biomethane €1.7M€33K> 25 yr-€1.5M-€2.4M … -€930K
  • CHP pays when you use the power yourself and the heat is really used.
  • Biomethane: raw biogas ≈ 36 Nm³/h. The smallest upgrading units take ≈ 50–100 Nm³/h, and the cost per Nm³ falls steeply with size, so a small plant pays much more for each unit of gas.

Plant size

The same feedstock mix at other sizes, each option re-sized by the model. Extra feedstock is assumed on your terms (price, transport, disposal saving); CAPEX is the model's estimate, not your quote.

Sizet/yrBest optionkWeCAPEXNPV (base)
× 0.5 3,500Boiler (heat only)45€550K-€570K
× 0.75 5,200CHP (power + heat)65€970K-€720K
× 1 your input6,900CHP (power + heat)90€1.2M-€810K
× 1.5 10,000CHP (power + heat)150€1.6M-€930K
× 2 14,000CHP (power + heat)200€2M-€1M
× 3 21,000CHP (power + heat)310€2.8M-€1.4M

National support schemes — separate cases

Not in the verdict: tariffs get cut, auctions fail, grant calls close. Status and source shown for each.

Bottom line

There is a scheme, but support is awarded by competition

It pays no more than the market, so it does not improve the economics.

Best option: Аукціон з ринковою премією (інші ВДЕ) — market-premium auction Details ↓

NPV change
€0
NPV with support
-€810K
Payback
18 yr
IRR
-1.4 %

Next step: Prepare for the next round: permits are usually required before you bid, and an award is not guaranteed.

Country overviewchecked 30 Oct 2026

The only route for new plants is market-premium auctions (bid cap 12 €c/kWh; the 'other RES' lot of 30.10.2026 did not take place; indicative biogas quotas 21–29 MW a year for 2027–2030). The green tariff ends on 01.01.2030 and has no EUR floor for plants commissioned after 2024. Biomethane: export, no subsidy.

Running, awarded by competition (1)

Support goes to the winners of a round or auction. The case assumes an award at the stated value.

Аукціон з ринковою премією (інші ВДЕ) — market-premium auction

Competitive
Electricity tariff
Meets every condition we checked
NPV change
€0
NPV with support
-€810K
Payback
18 yr
IRR
-1.4 %
Conditions
  • met: CHP of a practical size, from 25 kW (project ≈ 90 kW)
What the case uses
  • Route: CHP (power + heat)
  • Tariff: €0.12/kWh
Scheme terms

Bid cap 12 €c/kWh; your own winning bid is guaranteed via a market premium. The 30.10.2026 lot did not take place (Prozorro).

Next step: Prepare for the next round: permits are usually required before you bid, and an award is not guaranteed.

Source: Guaranteed Buyer notice 03.09.2026 (150 MW, cap 12 €c); Prozorro: auction did not take place; CMU order 298-р (508-р); Law 555-IV Art. 9-3 · checked 30 Oct 2026 · Data confidence: Low

Support never changes the verdict. Each case is pre-tax, uses the scheme's published terms and assumes the support is awarded; it does not confirm eligibility or promise funding.

Where the energy goes

Heat produced ≠ useful heat. Heat without a user isn't income.

46/100

Of every 100 kWh of energy in the methane, 46 become a product that earns money or replaces a purchase.

100 % = 2,100 MWh of methane energy a year (LHV), base case. Every figure in this block is calculated by the model from your inputs.

Stream by stream

Calculated

Earns money

  • Electricity used on site640 MWh 31 %
  • Heat for a user300 MWh 15 %

Runs the plant

  • Plant’s own electricity65 MWh 3 %
  • Digester heating250 MWh 12 %

Produced, not used

  • Heat with no buyer350 MWh 17 %

Losses

  • Conversion losses (engine, boiler)360 MWh 18 %
  • Gas sent to the flare42 MWh 2 %
  • Methane leaks31 MWh 2 %

What this means for the project

  • 350 MWh of heat a year has no buyer. A heat user nearby (drying, a greenhouse, process heat, a heating network) would turn it into income. At the heat value used in this case that is about €22K a year.
  • Methane leaks are 2 % of production in the base case: lost income and a greenhouse gas. Gas-tight digestate storage and regular leak checks keep them low.

What the figures rest on

Engine efficiency: electricity / heat
36 % / 50 %Assumption
Heat need
600 MWhYour data
Site electricity use
2,200 MWhYour data
Methane leaks, base case
2 %Assumption
Main product, conservative – optimistic
470 – 670 MWhCalculated

Season: how much the digester takes for itself

In January heating the digester needs heat equal to 15 % of that month’s methane energy, in July 9 %.

January: methane energy 170 MWh · digester heating 26 MWh (15 %) · heat for a user 41 MWh

  • Methane energy of the month
  • Digester heating
  • Heat for a user

How it works: from feedstock to products

  1. Feedstock6,900 t/yr
  2. Biogas340K Nm³/yr
  3. Electricity640 MWh
  4. Useful heat300 MWh
  5. Heat without demand350 MWh
  6. Digestate6,500 t/yr
Heat produced (gross)
911 MWh
Digester heat demand
255 MWh
Useful heat (economic)
304 MWh of 657
Power: own use / sold
638 / 0 MWh

Climate case (EU RED method)

EU Renewable Energy Directive default values for your feedstock mix, digestate storage and route. Separate from the verdict; outside the EU an indicative benchmark. Credits are valued only in the support cases where an official mechanism exists.

Emissions of the product
7 g CO₂e/MJ
open digestate storage
Fossil comparator
183 g CO₂e/MJ
Greenhouse-gas saving
96 %
RED minimum: 80 %
Avoided emissions
488 t CO₂e
  • Meets the RED minimum.
  • Below 2 MW rated input the RED criteria do not apply by law; buyers and schemes may still ask for them.
  • Residues other than manure, maize and food waste use the RED biowaste values.

Scores by dimension

No single magic number. The overall score comes with its explanation.

Feedstock fit
65/100
  • Energy equivalent ≈ 90 kWe (scale score 61/100)
  • Feedstock energy ≈ 296 kWh of methane per tonne (score 55/100)
  • Feedstock available 12 of 12 months
  • Most feedstock has low-confidence parameters
  • Ammonia / fat inhibition risk lowers the yield
Energy fit
73/100
  • Own consumption absorbs 100 % of the electricity produced
  • Useful heat 304 MWh of 657 MWh available after digester needs
Location & logistics
100/100
  • No critical site constraints found from your answers
Technical feasibility
80/100
  • Ammonia / fat inhibition needs active process control
  • Dry digestion — fewer suppliers
Economics
4/100
  • Base-case simple payback ≈ 18.0 years
  • Base-case NPV is negative
  • Minimum DSCR 0.55 — below the usual bank threshold of 1.2–1.3
Regulatory complexity
27/100 risk
  • Number and weight of permitting / regulatory steps: 11 points (more = harder)
Environmental risk
24/100 risk
  • Expected methane loss 2.5 % (good practice ≤ 2 %)
Overall project viability
40/100
  • Weighted: economics 30 %, feedstock 20 %, energy 15 %, technical 10 %, location 10 %, regulatory 7.5 %, environment 7.5 %.
  • Capped at 40: weak economics is not offset by other factors.
  • Strongest: Location & logistics (100); weakest: Economics (4).

Calculation details

Feedstock & logistics
Streamt/yrDM, %Nm³ CH₄/tLogistics / energyMax. distance
Laying-hen manure6,9262540.2on site≈ 92 km

Max. distance = where haulage eats half of a tonne's energy value. Low-energy feedstock (slurry) belongs next to the plant.

Technology & digester

Dry (high-solids) digestion, mesophilic

Garage (box) batch digesters with percolate recirculation, or horizontal plug-flow

Working volume
≈ 1,400 m³
Retention time
73 days
Loading rate
2.5 kg VS/(m³·d)
Digestate storage
≈ 3,300 m³
  • Average mix dry matter 25 % ≥ 22 %: wet digestion would need dilution, increasing volume and heat losses.
  • Mesophilic (≈38 °C): more robust, less heat and complexity. Thermophilic (≈52 °C) only when the benefit outweighs the complexity — rarely at this scale.
  • Single stage plus a gas-tight digestate store as post-digester: sufficient at this scale.
Alternatives
  • Wet digestion diluted with slurry/effluent — cheaper equipment, larger digester

Climate: Ivano-Frankivsk oblast, mean 10.2 °C, ≈ 3,037 heating degree-days. Closest climate analogues: Prague (CZ) (Δ 0.7 °C), Dresden (DE, east) (Δ 0.9 °C), Kraków (PL) (Δ 0.9 °C).

Monthly energy balance

Base case, chosen route. Gas energy is usable methane energy (LHV) after losses.

MonthFeedstock, tGas energy, MWhDigester heat, MWhUseful heat, MWhNet electricity, MWh
Jan588172264154
Feb536156243749
Mar588172254254
Apr569166213752
May588172201754
Jun56916616052
Jul58817216054
Aug58817216054
Sept56916618952
Oct588172223954
Nov569166244052
Dec588172264154
Σ6,9262,021255304638
CAPEX, OPEX, revenue (base case)
CAPEX (EUR)
Digester280K
New covered storage140K
New open storage96K
Feedstock reception and preparation81K
Gas handling and cleaning30K
CHP (power + heat)190K
Heat network32K
Backup boiler1.8K
Electrical systems and controls51K
Pipework34K
Civil works51K
Grid connection22K
Engineering and permits80K
Contingency110K
Total1.2M
OPEX / yr (EUR)
Staff4.3K
CHP service and overhaul reserve19K
Maintenance20K
Insurance6K
Testing and monitoring5K
Total54K
Revenue + savings / yr (EUR)
Electricity self-consumption savings91K
Useful heat (economic)19K
Incremental digestate value11K
Total120K

Unit costs are estimates. Replace them with supplier quotations.

Digestate: asset or liability

Status: asset · 6,507 t/yr · nitrogen ≈ 78,132 kg/yr · land needed ≈ 460 ha (available 500 ha).

Incremental fertiliser value €11K/yr, handling €0/yr, net €11K/yr.

  • Digestate storage for 6 months for the closed spreading season; keep ≈ 150 days (incl. the digester) gas-tight, otherwise methane and N are lost.
  • Spread by injection or trailing hose (not splash plate): less odour and ammonia loss.
Methane losses & climate

Expected losses: 2.5 % of methane produced (range 1.6 % – 4 %) ≈ 100 t CO₂e/yr; fossil emissions displaced ≈ 221 t CO₂/yr. Losses vs benefit: 45 %.

  • Expected loss 2.5 % is above good practice (2 %): budget for monitoring.
  • Gas-tight covers on the digester and digestate storage (incl. lagoon covers) — the single most important measure.
  • Leak detection and repair (LDAR): optical gas imaging or tracer method at least yearly, plus an acceptance test after construction.
  • Continuous gas-holder pressure monitoring; a standby flare instead of venting.
  • CHP with an oxidation catalyst and tuning regime to cut methane slip.

Avoided emissions from open manure storage are not credited (conservative).

Permits & regulation (indicative)

Complexity: lower. “To verify” means a local lawyer or engineer must confirm the item during the feasibility study.

  • Urban-planning conditions and construction permit (consequence class to be confirmed)
    New installation · effort: medium · to verify
  • Environmental impact assessment / screening (thresholds to be confirmed)
    Biogas plant as an organic-waste facility · effort: medium · to verify
  • Registration of high-hazard equipment and gas-system expert review
    Gas holders, CHP under pressure · effort: medium · to verify
  • Fire safety and explosion-hazard zoning
    Methane in the gas phase · effort: medium · to verify
  • Air-emission permit for stationary sources (CHP, flare)
    Biogas combustion · effort: lower · to verify
  • Digestate use as fertiliser: status under the pesticides & agrochemicals law and application rules
    Digestate goes to fields · effort: medium · to verify
Safety (risk register)
  • Methane: explosion and fire (flammable range ≈ 5–15 % in air) high
    • Hazardous-area (ATEX/IECEx or national) zoning and suitably rated equipment
    • Fixed gas detectors in the CHP room and near tanks
    • Flame arresters, over/under-pressure relief, safety flare
    • Ignition-source control and hot-work permits
  • Hydrogen sulphide (H₂S): acute toxicity, corrosion high
    • Biological / chemical desulphurisation of the biogas
    • Personal H₂S monitors, no lone working
    • H₂S monitoring upstream of the CHP (engine protection)
  • Confined spaces (digester, storage, pits): asphyxiation, toxic gases high
    • Entry only under permit, ventilation, standby person
    • Self-contained breathing apparatus for rescue
  • Over/under-pressure: membrane roof rupture, tank deformation medium
    • Liquid seals / relief valves venting to a safe location
    • Gas-holder level and pressure sensors
  • CHP: carbon monoxide, fire, high temperatures medium
    • CHP room ventilation, CO detectors
    • Emergency stop, fire suppression
  • Ammonia (NH₃): toxicity and process inhibition medium
    Condition: Poultry manure in the mix
    • Limit the poultry share, dilute
    • Monitor NH₄-N in the digester, ventilate reception
  • Soil and water pollution: slurry/digestate spills, lagoon overflow high
    • Bund sized for the largest tank
    • Level sensors and a spill-response plan
    • Digestate storage covering the closed spreading season

Software does NOT replace a qualified process engineer and a process-safety engineer. Every final engineering design, hazardous-area classification and safe-operation programme must pass human professional review.

Assumptions used (163)

Every number has a source, date, country and confidence, and is tagged FACT / ASSUMPTION / CALCULATION / ESTIMATE. Full register: →

  • Support: The only route for new plants is market-premium auctions (bid cap 12 €c/kWh; the 'other RES' lot of 30.10.2026 did not take place; indicative biogas quotas 21–29 MW a year for 2027–2030). The green tariff ends on 01.01.2030 and has no EUR floor for plants commissioned after 2024. Biomethane: export, no subsidy.
  • No subsidy for new small plants: the case rests on own electricity and heat, avoided disposal and energy resilience. Biomethane export to the EU (ISCC) is open to large producers.
  • The verdict excludes subsidies; national support is shown as separate cases.
  • This is a preliminary (screening) assessment — not a detailed engineering design and not a commercial offer.
  • Financial results are pre-tax project cash flows. Depreciation, income taxes, working capital, financing fees and detailed debt covenants are not modelled; DSCR is an EBITDA-based screening ratio, not lender CFADS.
  • Parameter bounds are tested individually using the applicable market/CAPEX evidence. These engineering or tariff ranges are not statistical confidence intervals and do not replace supplier quotations or customer bills.

What could break the economics

Each stress test applied to the base case on its own.

CHP: local CAPEX factor
0.595 … 1.105 —
NPV low…high: -€1.2M … -€390K
Discount rate (nominal, pre-tax, EUR-equivalent, incl. country & war risk)
0.139 … 0.169 —
NPV low…high: -€840K … -€780K
Mineral potassium price
0.713 … 0.8099 EUR/kg K₂O
NPV low…high: -€810K … -€810K
Mineral nitrogen price
1.045 … 1.818 EUR/kg N
NPV low…high: -€820K … -€780K
Mineral phosphorus price
1.419 … 1.847 EUR/kg P₂O₅
NPV low…high: -€810K … -€810K
Avoidable share of an unsplit customer electricity bill
0.7 … 1 —
NPV low…high: -€900K … -€710K
Every number has a source, date, country and confidence, and is tagged FACT / ASSUMPTION / CALCULATION / ESTIMATE. Full register:
Biomethane price without support, base (EU export netback): 0.68 EUR/Nm³ · CALCULATED_VALUE · LOW
EU export: TTF 46.49 €/MWh HHV × 1.11 HHV/LHV + 20 €/MWh LHV green-gas premium (engineering assumption, no official GO price); World Bank Pink Sheet (2026-10-02), Natural gas Europe (TTF), mean Q4 2025 – Q3 2026 15.25 $/mmbtu GCV ÷ 0.2931 MWh/mmbtu at 1.1193 USD/EUR; minus Ukrainian GTS exit tariff 1.5113 EUR/MWh HHV (NEURC 2387); × 9.67 kWh/Nm³. EU entry, onward transport and certification not deducted; no guaranteed offtake
2025-07 / 2026-06 · checked 2026-11-11 · Unsupported biomethane: domestic gas parity (conservative) or EU export netback (base); exports were 65 % of Ukrainian biomethane in Q2 2026
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
CHP: local CAPEX factor: 0.85 — · CALCULATED_VALUE · LOW
Provisional fit to published Ukrainian CHP projects; no independent validation. Does not calibrate upgrading/injection costs or quantify war-risk construction premiums.
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Debt interest rate (EUR): 0.1 — · ENGINEERING_ASSUMPTION · LOW
Indicative financing assumption informed by EBRD / IFC-backed credit programmes; not a bank term sheet
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Debt share for DSCR test: 0.5 — · ENGINEERING_ASSUMPTION · MEDIUM
Typical EBRD/IFI-style lending for agrifood
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Debt tenor: 7 a · ENGINEERING_ASSUMPTION · MEDIUM
Typical for agri/energy credit lines (EBRD, IFC, EIB programmes)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Digestate that has no adequate land: 3.6 EUR/t · CALCULATED_VALUE · MEDIUM
2.5 €/t + 0.22 h/t × 4.9 €/h labour (same formula as every market)
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Incremental digestate handling on adequate land: 1.6 EUR/t · CALCULATED_VALUE · MEDIUM
1.2 €/t machinery + 0.08 h/t × 4.9 €/h labour (same formula as every market)
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Discount rate (nominal, pre-tax, EUR-equivalent, incl. country & war risk): 0.149 — · CALCULATED_VALUE · MEDIUM
Nominal, pre-tax, EUR-equivalent: 6.0 % mature-market WACC + 0.6 × country risk premium 14.85 % (Ca; Damodaran, 2026-07); not a bank offer
2026-07-01 · checked 2026-10-27 · Rating-based CRP; baseline WACC and lambda are engineering/financial assumptions
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Wholesale electricity price (market average): 0.1255 EUR/kWh · CALCULATED_VALUE · MEDIUM
Market Operator (OREE), DAM BASE index, IPS of Ukraine, mean of monthly values Oct 2025 – Sep 2026: 6 377 UAH/MWh excl. VAT; converted at 50.8152 UAH/EUR (2026-11-10)
2026-09-30 · checked undated · Historical national/regional reference; latest publication and customer applicability require verification
WITHIN_REVIEW_WINDOW: Within the 60-day review policy; applicability and latest publication must still be checked
Documented nominal reference (may include estimated adders): 6.377 UAH (ENGINEERING_ASSUMPTION); FX (2026-11-10): 50.82 UAH/EUR (MARKET_DATA)
Annual escalation of energy prices (nominal EUR): 0.02 — · ENGINEERING_ASSUMPTION · MEDIUM
Conservative; UAH price rises offset by depreciation (EUR terms)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Share of the wholesale price realised for surplus power: 0.7 — · ENGINEERING_ASSUMPTION · MEDIUM
30 % profile & balancing discount for a small seller (assumption)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Mineral potassium price: 0.7611 EUR/kg K₂O · CALCULATED_VALUE · MEDIUM
World Bank Pink Sheet, 12-month mean 2025M10–2026M09; ÷ nutrient share × 1.35 farm-gate markup
2025M10 / 2026M09 · checked 2026-10-27 · World commodity reference; actual digestate nutrient substitution and local fertiliser price require confirmation
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Trailing-year commodity reference: 378.6 USD/t product (MARKET_DATA); Latest-month reference (2026-09): 367.5 USD/t product (MARKET_DATA); FX (2026-11-09): 1.119 USD/EUR (MARKET_DATA); Farm-gate markup: 1.35 — (ENGINEERING_ASSUMPTION)
Mineral nitrogen price: 1.33 EUR/kg N · CALCULATED_VALUE · MEDIUM
World Bank Pink Sheet, 12-month mean 2025M10–2026M09; ÷ nutrient share × 1.35 farm-gate markup
2025M10 / 2026M09 · checked 2026-10-27 · World commodity reference; actual digestate nutrient substitution and local fertiliser price require confirmation
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Trailing-year commodity reference: 507.3 USD/t product (MARKET_DATA); Latest-month reference (2026-09): 407.5 USD/t product (MARKET_DATA); FX (2026-11-09): 1.119 USD/EUR (MARKET_DATA); Farm-gate markup: 1.35 — (ENGINEERING_ASSUMPTION)
Mineral phosphorus price: 1.678 EUR/kg P₂O₅ · CALCULATED_VALUE · MEDIUM
World Bank Pink Sheet, 12-month mean 2025M10–2026M09; ÷ nutrient share × 1.35 farm-gate markup
2025M10 / 2026M09 · checked 2026-10-27 · World commodity reference; actual digestate nutrient substitution and local fertiliser price require confirmation
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Trailing-year commodity reference: 639.8 USD/t product (MARKET_DATA); Latest-month reference (2026-09): 690 USD/t product (MARKET_DATA); FX (2026-11-09): 1.119 USD/EUR (MARKET_DATA); Farm-gate markup: 1.35 — (ENGINEERING_ASSUMPTION)
Exchange rate: 50.82 UAH/EUR · MARKET_DATA · HIGH
Official EUR reference rate, 2026-11-10
2026-11-10 · checked 2026-11-10 · UAH per EUR; dated reference, not a guaranteed transaction rate
WITHIN_REVIEW_WINDOW: Within the 7-day review policy; applicability and latest publication must still be checked
Value of useful heat (displaced industrial gas / boiler efficiency): 0.06111 EUR/kWh th · CALCULATED_VALUE · MEDIUM
Business gas price: NEURC gas market monitoring Q2 2026: non-household retail price, unregulated segment, 23 697 UAH/1 000 m³ excl. VAT, transmission and distribution + NEURC tariffs: transmission exit to distribution systems 501.97 UAH per 1 000 m³/day (resolution 2387 of 30.12.2024, flat load) + non-household distribution from 01.04.2026, median of 35 operators 2.35 UAH/m³ (range 0.46–3.92) = 26 549 UAH/1 000 m³ excl. VAT; converted at 50.8152 UAH/EUR (2026-11-10)
2026-06-30 · checked undated · Historical national/regional reference; latest publication and customer applicability require verification
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Documented nominal reference (may include estimated adders): 2,795 UAH (ENGINEERING_ASSUMPTION); FX (2026-11-10): 50.82 UAH/EUR (MARKET_DATA)
Evaluation horizon: 15 a · ENGINEERING_ASSUMPTION · MEDIUM
Shorter than the 20-y technical life — conservative
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Historical hourly labour-cost reference (wages + employer costs): 4.975 EUR/h · CALCULATED_VALUE · MEDIUM
Derzhstat: average wage of full-time employees Sep 2026 33 153 UAH/month × 1.22 employer contributions ÷ 160 h; skilled operator premium 1.14; converted at 50.8152 UAH/EUR (2026-11-10)
2026-09-30 · checked undated · Historical national/regional reference; latest publication and customer applicability require verification
WITHIN_REVIEW_WINDOW: Within the 730-day review policy; applicability and latest publication must still be checked
Documented nominal reference (may include estimated adders): 252.8 UAH (ENGINEERING_ASSUMPTION); FX (2026-11-10): 50.82 UAH/EUR (MARKET_DATA)
Plant operator wage relative to the economy-wide average: 1.14 — · ENGINEERING_ASSUMPTION · MEDIUM
Skilled plant operator ≈ 30 k UAH/month gross vs the 26.5 k average → ≈ 4.9 €/h operator cost
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Annual escalation of operating costs (nominal EUR): 0.03 — · ENGINEERING_ASSUMPTION · MEDIUM
Wage growth > CPI in UA (NBU inflation report)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Road transport of liquid/solid organic feedstock: 0.11 EUR/(t·km) · ENGINEERING_ASSUMPTION · LOW
Tanker/tipper rate incl. empty return; diesel-driven; TO VERIFY with 3 hauliers
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Loading/unloading per tonne: 0.7 EUR/t · CALCULATED_VALUE · MEDIUM
0.6 €/t pump & loader + 0.02 h/t × 4.9 €/h labour (same KTBL-based formula as every market)
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Avoidable share of an unsplit customer electricity bill: 0.85 — · ENGINEERING_ASSUMPTION · LOW
Engineering judgement, no published value: energy share of an unsplit bill; customer tariff sheet takes precedence
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Customer electricity price (invoice split not verified): 0.1673 EUR/kWh · USER_INPUT · MEDIUM
USER_INPUT 8.5 UAH/kWh / FX 50.8152; Official EUR reference rate, 2026-11-10. Invoice date not supplied; energy/demand split assumed separately.
REVIEW_REQUIRED: Customer input; invoice date, contract and validity not independently verified