A sample Extended Report for a modelled project. Your report has the same structure (the Standard Report has fewer sections) and uses your own data.

Business situation

An English merchant AD developer considers 50,000 t/year of separately collected commercial food waste, with grid injection as a candidate outlet.

Operating assumptions

  • Source-separated food waste: 50,000 t/yr · DM: 24 % · 12 months · Other / don't know · Delivered from another site: 25 km · Purchase price / gate fee: -30 GBP/t
  • Electricity: 1,500,000 kWh/yr · Electricity price on your bill (if known): 0.245 GBP/kWh
  • No heat needed
  • Land available for spreading digestate: 2,000 ha · Distance to the gas grid (for biomethane): 1 km
  • Grid connection? Yes

What to verify

Secure tonnage, contamination limits and gate-fee contracts. Quote depackaging, methane recovery, connection capacity, gas quality and digestate certification.

Possible with conditions

It can pay off, but only if the key conditions hold — confirm them in a feasibility study.

  • Base NPV positive (€13M), payback ≈ 4.7 yrs.
  • Conservative-case NPV is negative (-€1.2M) — sensitive to key assumptions.

Largest benefit — “surplus electricity sold”: ≈ 69 % of all revenue and savings.

What would change the verdict
  • → Secure long-term heat and power offtake; benchmark CAPEX with 3–5 suppliers.

Subsidies and tariffs excluded from the verdict. Preliminary screening, not an engineering design.

How firm is this answer?

Grey zone: the answer flips between the conservative and the optimistic case. Before paying for a feasibility study, check these first:

NPV: conservative -€1.2M · base €13M · optimistic €19M

The conservative case stacks every adverse assumption at once: a stress test, not the likely outcome. In 160 likely combinations the NPV was positive in > 99 % of cases.

  1. Secure the feedstock supply in writing · Feedstock potential −20 % (-€4.9M)
  2. Get an offer for exported power (PPA or tariff) · Energy prices −20 % (-€3.6M)
  3. Lab test of the methane yield (BMP) · CH₄ −20 % (-€2.8M)

These are screening assumptions, not independently validated accuracy limits. Confirm BMP, supplier scope, grid connection and offtake terms before an investment decision.

To reach a bankable estimate (±15 %)
  1. Laboratory methane-potential (BMP) test of 2–3 feedstock samples — ≈ €300–800 each
  2. 2–3 supplier quotes for the plant
  3. Grid or gas-network connection conditions from the operator
  4. Letters of intent for feedstock supply and for heat, power or biomethane offtake
  5. Then a feasibility study with permits and financing (±15 %)
From screening to construction

Key figures

Ranges: conservative — base — optimistic. We don't show fake precision.

Economics

Preliminary investment
€10M – €13M
≈ £9.2M (base)
Payback
3.5 yr – 11.2 yr
base: 4.7 yr · no subsidies
NPV (base)
€13M
range: -€1.2M … €19M
Chosen route
CHP (power + heat)
Confidence: Medium

Feedstock and energy

Feedstock potential
50,000 t/yr
energy ≈ 905 kWh CH₄/t
Biogas
5.8M – 8.6M Nm³/yr
≈ 946 Nm³/h (base)
Net energy
13,000 – 18,000 MWh/yr
useful heat: 0 MWh · ≈ 85 % of your electricity use
Candidate capacity
2,400 kWe
large (1–5 MW)

How far you can rely on these numbers

Medium · 75/100
  • Backed by your data and our sources75
  • You can still add+15
  • Needs a feasibility study (lab, quotes, contracts)10

75/100: how much of what a screening can know about this project rests on your data and current sources. A missing input costs points in proportion to how far it could still move your result.

What you can add

  • Biggest gainLaboratory DM, VS and BMP results for every feedstock streamLarge effectSend a sample to a laboratory: dry matter and VS take a few days, BMP several weeks+15

With all of it: up to 90/100

High requires verified laboratory and project documents, so a screening stops at 90/100.

Model warnings
  • Animal by-products (Cat. 3) → pasteurisation and veterinary approval required.
  • In this configuration the digestate is a cost rather than an asset.
  • CHP performance uses a 50 Hz biogas full-load catalogue reference (03/2025), interpolated between ratings; part-load and ambient derating require supplier confirmation.
  • CHP rating is outside the 20–2,300 kW reference curve; endpoint efficiency is only a proxy. Obtain a multi-engine or equipment-specific design.
  • Market data require review (econ.electricity_spot_eur_kwh). Observation dates and validity are shown in the evidence; these are not verified current customer quotations.
Country conditions
  • High electricity prices make on-site CHP for own use attractive; policy favours food waste over manure.

Action plan: what would make it stronger

Changes tested on this project with the same model. Break-even values show how far each must go; the scenario assumptions are LOW-confidence judgements to replace with offers.

What separates this project from “Strong candidate”
  • The conservative case must stay profitable too (its NPV is -€1.2M).
ChangeVerdictNPV (base)Δ NPVBreak-even
Sell the spare heat
A year-round heat buyer (drying, process heat, greenhouse or district heating) for ≈ 13,000 MWh a year, valued at ≈ £0.0497 per kWh.
Strong candidate€21M+€7.4Mheat ≥ £0.00276 per kWh
Order of action
  1. 1Find a heat buyer for ≈ 13,000 MWh a year (heat ≥ £0.00276 per kWh).
  2. 2Ask 3–5 suppliers for quotes: the project breaks even up to an investment of €22M. →

What to verify first

Inputs ranked by what exact knowledge is worth before you decide (expected value of perfect information). Each range is tested on its own; inputs you already supplied are not listed.

CheckNPV across the plausible rangeWorth knowing
Fix feedstock prices and gate fees in contracts€8.3M … €18M—
Get supplier quotes for the plant€9.1M … €17M—
Secure the feedstock supply in writing€5.4M … €13M—
Verify the market price€10M … €15M—
Lab test of the methane yield (BMP)€10M … €13M—
Check the fertiliser value of the digestate€13M … €14M—
How to check: Fix feedstock prices and gate fees in contracts
  1. For every purchased stream and every gate fee, note today's price and its range over the last three years.
  2. Fix prices or gate fees with indexation for the loan period, and check that the plan still pays with prices 25 % worse.
Request to send
Request for a feedstock supply agreement
Site: United Kingdom. A biogas plant would take:
- source-separated food waste: 50,000 t/year, DM ≈ 24.0 %
Please confirm the tonnes per month you can deliver, the dry matter, the delivery season, the price or gate fee per tonne with its indexation, and the term you can commit to.

Then enter it in: Feedstock step: quantity and price of each delivered stream

How to check: Get supplier quotes for the plant
  1. Send the same request to at least three suppliers.
  2. Compare like for like: scope, exclusions, guaranteed gas output, own power use, availability and the O&M price.
Request to send
Request for quotation: turnkey biogas plant
Site: United Kingdom.
Feedstock (screening values, to be confirmed):
- source-separated food waste: 50,000 t/year, DM ≈ 24.0 %
Design basis from the screening: raw biogas ≈ 950 Nm³/h at ≈ 60 % CH₄; digester working volume ≈ 8,300 m³; combined heat and power ≈ 2,400 kWe; new digestate storage ≈ 20,000 m³.
Please quote turnkey: feeding, digester(s), gas system with flare and desulphurisation, the gas-use equipment above, electrical and I&C, civil works, engineering and commissioning. List exclusions (grid connection, permits, land, digestate storage if separate). State the guaranteed gas output, own power and heat use, availability and the price of a full O&M contract.

Then enter it in: Step 3, “Optional: contracts and financing”: supplier quote and its technology

How to check: Secure the feedstock supply in writing
  1. List every stream you do not produce yourself: supplier, tonnes per month, season and contract term.
  2. Get letters of intent or contracts for at least the loan period, and size the plant on the tonnage that is signed, not promised.
Request to send
Request for a feedstock supply agreement
Site: United Kingdom. A biogas plant would take:
- source-separated food waste: 50,000 t/year, DM ≈ 24.0 %
Please confirm the tonnes per month you can deliver, the dry matter, the delivery season, the price or gate fee per tonne with its indexation, and the term you can commit to.

Then enter it in: Feedstock step: quantity and price of each delivered stream

How to check: Verify the market price
  1. Check the official source shown for this price in the market-data table and compare it with your own contract.

Then enter it in: Energy step: your own price, if you have a contract

How to check: Lab test of the methane yield (BMP)
  1. Take 3–5 subsamples of each stream over 2–4 weeks, mix them, keep them at 4 °C and deliver within 24 h.
  2. Order dry matter (DM), volatile solids (VS) and a methane potential test (BMP, VDI 4630) with the cellulose control reported.
  3. A valid test reports cellulose at 340–395 NL CH₄/kg VS; ask for a repeat otherwise.
Request to send
Request for quotation: biogas potential analysis
Site: United Kingdom.
Feedstock (screening values, to be confirmed):
- source-separated food waste: 50,000 t/year, DM ≈ 24.0 %
Design basis from the screening: raw biogas ≈ 950 Nm³/h at ≈ 60 % CH₄; digester working volume ≈ 8,300 m³; combined heat and power ≈ 2,400 kWe; new digestate storage ≈ 20,000 m³.
Per sample please quote: dry matter (DM, % of fresh mass), volatile solids (VS, % of DM) and biochemical methane potential (BMP, NL CH₄ per kg VS) to VDI 4630, with the cellulose control result and the test duration. Please state price, turnaround time and sampling and shipping instructions.

Then enter it in: Feedstock step: DM, VS and BMP on each stream

How to check: Check the fertiliser value of the digestate
  1. Ask neighbouring farms what they would pay per tonne of digestate, delivered and spread.
  2. Check the land available for spreading against the nitrogen limit.

Then enter it in: Site step: land available for digestate

Break-even prices

Each value on its own brings the base-case NPV to zero; everything else stays as calculated.

Electricity value at NPV = 0
€0.0269/kWh
now €0.0991/kWh
Highest installed cost at NPV = 0
€22M
now €11M
Feedstock price headroom
€23.9/t
can pay up to €23.9 per tonne more for every input

Probability range (Monte Carlo)

160 draws of the scenario quantities (yield, dry matter, CAPEX, prices, heat use, operating hours…). Energy and biomethane prices move together, the rest independently. Not a forecast: it shows how often the project stays positive when the uncertainties do not all go wrong at once.

NPV P10 (1 in 10 worse)
€7.3M
Median NPV
€11M
NPV P90 (1 in 10 better)
€12M
Chance that NPV > 0
> 99 %
Median payback
5.4 yr

No real-plant check for this type of project yet: we have no open data on operating plants like this one to compare with the model. The range above shows only the model's own uncertainty; confirm the gas yield with a lab test (BMP) or a pilot first.

What could break the economics

Each stress test applied to the base case on its own.

Change in NPV vs base, € (base: 13M)

  1. Feedstock potential −20 %-4.9M
  2. Energy prices −20 %-3.6M
  3. CH₄ −20 %-2.8M
  4. CAPEX +20 %-2.7M
  5. CHP downtime +10 pp-1.7M
  6. Feedstock transport +50 %-1.2M
  7. Maintenance +30 %-1.2M
  8. Useful heat (economic) −50 %0
NPV = 0 if CAPEX falls by
already positive
grant, leasing, cheaper equipment
NPV = 0 if energy prices rise by
already positive
relative to the base case

Scenarios

Route: CHP (power + heat). Scenarios bundle consistent assumptions (lower yield comes with higher CAPEX).

Revenue + savings / yr€2M
  • Electricity sales1.4M
  • Electricity self-consumption savings320K
  • Incremental digestate value310K
OPEX / yr-€300K
  • Disposal of pre-treatment rejects500K
  • Feedstock transport220K
  • CHP service and overhaul reserve180K
  • Maintenance170K
Operating margin (EBITDA)€2.3M
ScenariosConservativeBaseOptimistic
Biogas, 1 000 Nm³/yr5,793.57,5688,624
CAPEX€13M€11M€10M
OPEX / yr€170K-€300K-€460K
Revenue + savings / yr€1.4M€2M€2.4M
Operating margin (EBITDA)€1.2M€2.3M€2.8M
Simple payback11.2 yr4.7 yr3.5 yr
Discounted paybackno payback6 yr4.4 yr
NPV-€1.2M€13M€19M
IRR5.1 %20.1 %27.4 %
DSCR (min)1.12.63.5

Pre-tax, nominal EUR, 15-year horizon, discount rate of the country or your own; a screening estimate, not a bankable feasibility study. DSCR = EBITDA ÷ debt service at 65 % debt (no taxes).

Cumulative cash flow, €
-16M-1.9M13M27M41M03691215yearsConservativeBaseOptimistic

Biogas use routes compared

Base case. The model picks the route with the best NPV among technically sensible ones.

RouteCAPEXEBITDA / yrPaybackNPV (base)NPV low…high
CHP (power + heat) chosen€11M€2.3M4.7 yr€13M-€1.2M … €19M
Boiler (heat only) €8.2M€400K20.2 yr-€4.2M-€13M … -€780K
Biomethane €12M€2.1M5.5 yr€9.8M-€11M … €26M
  • CHP pays when you use the power yourself and the heat is really used.
  • Biomethane: raw biogas ≈ 896 Nm³/h. The smallest upgrading units take ≈ 50–100 Nm³/h, and the cost per Nm³ falls steeply with size, so a small plant pays much more for each unit of gas.

Plant size

The same feedstock mix at other sizes, each option re-sized by the model. Extra feedstock is assumed on your terms (price, transport, disposal saving); CAPEX is the model's estimate, not your quote.

Sizet/yrBest optionkWeCAPEXNPV (base)
× 0.5 25,000CHP (power + heat)1,200€6.1M€6.9M
× 0.75 38,000CHP (power + heat)1,820€8.7M€10M
× 1 your input50,000CHP (power + heat)2,420€11M€13M
× 1.5 75,000CHP (power + heat)3,630€16M€17M
× 2 100,000CHP (power + heat)4,840€20M€21M
× 3 150,000CHP (power + heat)7,260€30M€28M

National support schemes — separate cases

Not in the verdict: tariffs get cut, auctions fail, grant calls close. Status and source shown for each.

Bottom line

There is a scheme your project can apply for

On the scheme's terms the NPV is above zero.

Best option: Green Gas Support Scheme Details ↓

NPV change
+€23M
NPV with support
€36M
Payback
2.5 yr
IRR
37.3 %

Next step: Confirm the current rate and conditions with the scheme operator (source below), then prepare the application.

Country overviewchecked 30 Oct 2026

GGSS pays 7.09 p/kWh (2026/27, Tier 1) for 15 years on injected biomethane (≥ 50 % waste feedstock); applications until March 2028, commissioning by March 2030; no CHP tariff for new plants.

Open for applications (1)

You can apply now on the published terms.

Green Gas Support Scheme

Open
Biomethane support
Meets every condition we checked
NPV change
+€23M
NPV with support
€36M
Payback
2.5 yr
IRR
37.3 %
Conditions
  • met: Wastes and residues: at least 50 % of biogas energy (project 100 %)
  • met: Biomethane injected into the gas grid (included in the case)
  • met: Raw biogas for upgrading from 60 Nm³/h (project ≈ 896 Nm³/h)
What the case uses
  • Route: Biomethane
  • Biomethane price: €1.18/Nm³
Scheme terms

Tier 1 7.09 p/kWh in 2026/27 (CPI-linked) + gas and certificate sales; 15 years, ≥ 50 % waste; budget-capped queue.

Next step: Confirm the current rate and conditions with the scheme operator (source below), then prepare the application.

Source: Ofgem GGSS tariff table 2026/27; Ofgem GGSS guidance v3.0 (13.10.2026) · checked 30 Oct 2026 · Data confidence: Medium

Support never changes the verdict. Each case is pre-tax, uses the scheme's published terms and assumes the support is awarded; it does not confirm eligibility or promise funding.

Where the energy goes

Heat produced ≠ useful heat. Heat without a user isn't income.

39/100

Of every 100 kWh of energy in the methane, 39 become a product that earns money or replaces a purchase.

100 % = 45,000 MWh of methane energy a year (LHV), base case. Every figure in this block is calculated by the model from your inputs.

Stream by stream

Calculated

Earns money

  • Electricity sold to the grid16,000 MWh 36 %
  • Electricity used on site1,300 MWh 3 %

Runs the plant

  • Plant’s own electricity1,400 MWh 3 %
  • Digester heating1,600 MWh 3 %

Produced, not used

  • Heat with no buyer16,000 MWh 35 %

Losses

  • Conversion losses (engine, boiler)7,300 MWh 16 %
  • Gas sent to the flare1,000 MWh 2 %
  • Methane leaks680 MWh 2 %

What this means for the project

  • 16,000 MWh of heat a year has no buyer. A heat user nearby (drying, a greenhouse, process heat, a heating network) would turn it into income.
  • Methane leaks are 2 % of production in the base case: lost income and a greenhouse gas. Gas-tight digestate storage and regular leak checks keep them low.

What the figures rest on

Engine efficiency: electricity / heat
43 % / 43 %Assumption
Heat need
no heat userYour data
Site electricity use
1,500 MWhYour data
Methane leaks, base case
2 %Assumption
Main product, conservative – optimistic
13,000 – 18,000 MWhCalculated

Season: how much the digester takes for itself

In January heating the digester needs heat equal to 4 % of that month’s methane energy, in July 3 %.

January: methane energy 3,800 MWh · digester heating 150 MWh (4 %) · heat for a user 0 MWh

  • Methane energy of the month
  • Digester heating

How it works: from feedstock to products

  1. Feedstock50,000 t/yr
  2. Biogas7.6M Nm³/yr
  3. Electricity17,000 MWh
  4. Useful heat0 MWh
  5. Heat without demand16,000 MWh
  6. Digestate41,000 t/yr
Heat produced (gross)
17,389 MWh
Digester heat demand
1,562 MWh
Useful heat (economic)
0 MWh of 15,828
Power: own use / sold
1,275 / 16,199 MWh

Climate case (EU RED method)

EU Renewable Energy Directive default values for your feedstock mix, digestate storage and route. Separate from the verdict; outside the EU an indicative benchmark. Credits are valued only in the support cases where an official mechanism exists.

Emissions of the product
101 g CO₂e/MJ
open digestate storage
Fossil comparator
183 g CO₂e/MJ
Greenhouse-gas saving
45 %
RED minimum: 80 %
Avoided emissions
5,134 t CO₂e
  • Below the RED minimum: a gas-tight digestate store, off-gas combustion or more manure in the mix raise the saving.
  • RED sustainability criteria apply (rated input ≥ 2 MW).

Scores by dimension

No single magic number. The overall score comes with its explanation.

Feedstock fit
97/100
  • Energy equivalent ≈ 2420 kWe (scale score 100/100)
  • Feedstock energy ≈ 905 kWh of methane per tonne (score 87/100)
  • Feedstock available 12 of 12 months
Energy fit
33/100
  • Own consumption absorbs 7 % of the electricity produced
  • Useful heat 0 MWh of 15828 MWh available after digester needs
Location & logistics
75/100
  • Not enough land for the digestate
Technical feasibility
90/100
  • ABP pasteurisation adds complexity
Economics
90/100
  • Base-case simple payback ≈ 4.7 years
Regulatory complexity
45/100 risk
  • Number and weight of permitting / regulatory steps: 15 points (more = harder)
Environmental risk
39/100 risk
  • Expected methane loss 2.5 % (good practice ≤ 2 %)
  • Surplus digestate: risk of nitrogen over-application
Overall project viability
77/100
  • Weighted: economics 30 %, feedstock 20 %, energy 15 %, technical 10 %, location 10 %, regulatory 7.5 %, environment 7.5 %.
  • Strongest: Feedstock fit (97); weakest: Energy fit (33).

Calculation details

Feedstock & logistics
Streamt/yrDM, %Nm³ CH₄/tLogistics / energyMax. distance
Source-separated food wastedelivered 25 km50,0002490.812 %≈ 126 km

Max. distance = where haulage eats half of a tonne's energy value. Low-energy feedstock (slurry) belongs next to the plant.

Technology & digester

Wet mesophilic digestion with solids feeding

CSTR with a solids feeder and recirculation, or horizontal plug-flow for dairy manure

Working volume
≈ 8,300 m³
Retention time
60.3 days
Loading rate
3.5 kg VS/(m³·d)
Digestate storage
≈ 20,000 m³
  • Dry matter 24 % is above the pumpable limit without a solids feeder (12 %).
  • Continuous feed — continuous operation gives steady gas and the simplest control.
  • Mesophilic (≈38 °C): more robust, less heat and complexity. Thermophilic (≈52 °C) only when the benefit outweighs the complexity — rarely at this scale.
  • Two-stage layout (main + post-digester) for stability with fats or larger flows.
Alternatives
  • Horizontal plug-flow (good for 10–14 % DM cattle manure)
  • Separate pasteurisation (70 °C / 1 h) ahead of a mesophilic digester instead of thermophilic operation

Climate: West Midlands / Shropshire, mean 10.8 °C, ≈ 2,620 heating degree-days. Closest climate analogues: Copenhagen (DK) (Δ 2.1 °C), Dresden (DE, east) (Δ 2.8 °C), Munich (DE, Bavaria) (Δ 3.2 °C).

Monthly energy balance

Base case, chosen route. Gas energy is usable methane energy (LHV) after losses.

MonthFeedstock, tGas energy, MWhDigester heat, MWhUseful heat, MWhNet electricity, MWh
Jan4,2443,78515001,483
Feb3,8673,44913401,352
Mar4,2443,78514401,483
Apr4,1073,66313401,435
May4,2443,78512701,483
Jun4,1073,66311401,435
Jul4,2443,78511301,483
Aug4,2443,78511401,483
Sept4,1073,66311801,435
Oct4,2443,78513101,483
Nov4,1073,66313701,435
Dec4,2443,78514601,483
Σ50,00044,5931,562017,474
CAPEX, OPEX, revenue (base case)
CAPEX (EUR)
Digester1.1M
New covered storage1.1M
New open storage580K
Feedstock reception and preparation2.2M
Pasteurisation (70 °C / 1 h)290K
Gas handling and cleaning130K
CHP (power + heat)2.4M
Backup boiler11K
Electrical systems and controls470K
Pipework320K
Civil works470K
Grid connection150K
Engineering and permits750K
Contingency1M
Total11M
OPEX / yr (EUR)
Staff140K
CHP service and overhaul reserve180K
Maintenance170K
Insurance55K
Testing and monitoring5K
Feedstock purchase, net of gate fees-1.7M
Feedstock transport220K
Disposal of pre-treatment rejects500K
Digestate handling140K
Total-300K
Revenue + savings / yr (EUR)
Electricity self-consumption savings320K
Electricity sales1.4M
Incremental digestate value310K
Total2M

Unit costs are estimates. Replace them with supplier quotations.

Digestate: asset or liability

Status: liability / cost · 40,759 t/yr · nitrogen ≈ 362,727 kg/yr · land needed ≈ 2,134 ha (available 2,000 ha).

Incremental fertiliser value €310K/yr, handling €140K/yr, net €170K/yr.

  • Not enough land: ≈ 2134 ha needed at 170 kg N/ha. Surplus digestate is a cost (agreements with neighbours, separation, pelletising).
  • Digestate storage for 6 months for the closed spreading season; keep ≈ 150 days (incl. the digester) gas-tight, otherwise methane and N are lost.
  • Spread by injection or trailing hose (not splash plate): less odour and ammonia loss.
Methane losses & climate

Expected losses: 2.5 % of methane produced (range 1.6 % – 4 %) ≈ 2,205 t CO₂e/yr; fossil emissions displaced ≈ 3,792 t CO₂/yr. Losses vs benefit: 58 %.

  • Methane losses could cancel the climate benefit. Do not claim emission reductions without measurements.
  • Expected loss 2.5 % is above good practice (2 %): budget for monitoring.
  • Gas-tight covers on the digester and digestate storage (incl. lagoon covers) — the single most important measure.
  • Leak detection and repair (LDAR): optical gas imaging or tracer method at least yearly, plus an acceptance test after construction.
  • Continuous gas-holder pressure monitoring; a standby flare instead of venting.
  • CHP with an oxidation catalyst and tuning regime to cut methane slip.

Avoided emissions from open manure storage are not credited (conservative).

Permits & regulation (indicative)

Complexity: medium. “To verify” means a local lawyer or engineer must confirm the item during the feasibility study.

  • Planning permission (local planning authority) incl. odour, traffic and landscape
    New installation · effort: high · to verify
  • Environmental Permit (Environment Agency / SEPA / NRW / NIEA): standard rules or bespoke
    Treatment of waste or manure · effort: high · to verify
  • DSEAR hazardous-area assessment
    Methane in the gas phase · effort: medium · confirmed
  • Nitrate Vulnerable Zone rules and Farming Rules for Water
    Digestate is spread on land · effort: medium · to verify
  • DNO connection offer (G99) and export agreement
    Electricity export · effort: medium · to verify
  • Animal by-products approval: pasteurisation 70 °C / 1 h (Cat. 3) or pressure sterilisation (Cat. 2), veterinary registration
    Slaughter / dairy / food residues in the feed · effort: high · to verify
Safety (risk register)
  • Methane: explosion and fire (flammable range ≈ 5–15 % in air) high
    • Hazardous-area (ATEX/IECEx or national) zoning and suitably rated equipment
    • Fixed gas detectors in the CHP room and near tanks
    • Flame arresters, over/under-pressure relief, safety flare
    • Ignition-source control and hot-work permits
  • Hydrogen sulphide (H₂S): acute toxicity, corrosion high
    • Biological / chemical desulphurisation of the biogas
    • Personal H₂S monitors, no lone working
    • H₂S monitoring upstream of the CHP (engine protection)
  • Confined spaces (digester, storage, pits): asphyxiation, toxic gases high
    • Entry only under permit, ventilation, standby person
    • Self-contained breathing apparatus for rescue
  • Over/under-pressure: membrane roof rupture, tank deformation medium
    • Liquid seals / relief valves venting to a safe location
    • Gas-holder level and pressure sensors
  • CHP: carbon monoxide, fire, high temperatures medium
    • CHP room ventilation, CO detectors
    • Emergency stop, fire suppression
  • Biological hazards: pathogens in animal by-products and food waste high
    Condition: Animal by-products / food waste in the mix
    • Pasteurisation 70 °C / 1 h (Cat. 3) with time–temperature control
    • Separate dirty and clean zones, vehicle disinfection
    • Veterinary supervision and traceability
  • Soil and water pollution: slurry/digestate spills, lagoon overflow high
    • Bund sized for the largest tank
    • Level sensors and a spill-response plan
    • Digestate storage covering the closed spreading season

Software does NOT replace a qualified process engineer and a process-safety engineer. Every final engineering design, hazardous-area classification and safe-operation programme must pass human professional review.

Assumptions used (164)

Every number has a source, date, country and confidence, and is tagged FACT / ASSUMPTION / CALCULATION / ESTIMATE. Full register: →

  • Support: GGSS pays 7.09 p/kWh (2026/27, Tier 1) for 15 years on injected biomethane (≥ 50 % waste feedstock); applications until March 2028, commissioning by March 2030; no CHP tariff for new plants.
  • High electricity prices make on-site CHP for own use attractive; policy favours food waste over manure.
  • The verdict excludes subsidies; national support is shown as separate cases.
  • This is a preliminary (screening) assessment — not a detailed engineering design and not a commercial offer.
  • Financial results are pre-tax project cash flows. Depreciation, income taxes, working capital, financing fees and detailed debt covenants are not modelled; DSCR is an EBITDA-based screening ratio, not lender CFADS.
  • Parameter bounds are tested individually using the applicable market/CAPEX evidence. These engineering or tariff ranges are not statistical confidence intervals and do not replace supplier quotations or customer bills.

What could break the economics

Each stress test applied to the base case on its own.

chp: local CAPEX factor
0.651 … 1.209 —
NPV low…high: €9.1M … €17M
Discount rate (nominal, pre-tax, EUR-equivalent, incl. country risk)
0.054 … 0.084 —
NPV low…high: €10M … €15M
Mineral potassium price
0.713 … 0.8099 EUR/kg K₂O
NPV low…high: €13M … €13M
Mineral nitrogen price
1.045 … 1.818 EUR/kg N
NPV low…high: €13M … €14M
Mineral phosphorus price
1.419 … 1.847 EUR/kg P₂O₅
NPV low…high: €13M … €13M
Avoidable share of an unsplit customer electricity bill
0.7 … 1 —
NPV low…high: €13M … €14M
Every number has a source, date, country and confidence, and is tagged FACT / ASSUMPTION / CALCULATION / ESTIMATE. Full register:
Biomethane price without support, base: 0.6 EUR/Nm³ · CALCULATED_VALUE · LOW
National estimate (project team, 2026-10) — no official series found for this item; your own price overrides it; local market for biomethane / RNG without credits
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
chp: local CAPEX factor: 0.93 — · CALCULATED_VALUE · MEDIUM
0.72 traded equipment + 0.28 × local/German labour cost (23.5/31.5 €/h); split after DBFZ/Fraunhofer 2024; supplier quotes needed
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Debt interest rate (EUR-equivalent): 0.049 — · CALCULATED_VALUE · MEDIUM
Discount rate − 1.5 pp (senior debt is cheaper than blended project capital); consistent with ECB MIR corporate loan rates + project margin; a bank term sheet replaces this
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Debt share for DSCR test: 0.65 — · ENGINEERING_ASSUMPTION · MEDIUM
Typical agri / project lending (KfW, EBRD, IFC practice)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Debt tenor: 10 a · ENGINEERING_ASSUMPTION · MEDIUM
Typical
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Digestate that has no adequate land: 7.67 EUR/t · CALCULATED_VALUE · MEDIUM
Third-party export of digestate ≈ 2.5 €/t + 0.22 h/t × labour; ≈ 12 €/t in Germany, in line with manure-exchange prices in surplus regions (LWK Niedersachsen Nährstoffbericht: 10–20 €/t)
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Incremental digestate handling on adequate land: 3.08 EUR/t · CALCULATED_VALUE · MEDIUM
Pumping & trailing-hose spreading ≈ 1.2 €/t machinery + 0.08 h/t × labour; ≈ 4.8 €/t in Germany, in line with KTBL contractor rates (3–6 €/m³)
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Discount rate (nominal, pre-tax, EUR-equivalent, incl. country risk): 0.064 — · CALCULATED_VALUE · MEDIUM
Nominal, pre-tax, EUR-equivalent: 6.0 % mature-market WACC + 0.6 × country risk premium 0.74 % (Aa3; Damodaran, 2026-07); not a bank offer
2026-07-01 · checked 2026-10-27 · Rating-based CRP; baseline WACC and lambda are engineering/financial assumptions
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Wholesale electricity price (market average): 0.1026 EUR/kWh · CALCULATED_VALUE · MEDIUM
Ofgem wholesale market indicators: GB day-ahead baseload, monthly average weighted by volume (broker data), Jul 2025 – Jun 2026 mean £85.63/MWh; converted at 0.8343 GBP/EUR (2026-11-09)
2026-06-30 · checked undated · Historical national/regional reference; latest publication and customer applicability require verification
REVIEW_REQUIRED: Observation is 132 days old; exceeds the 60-day review policy
Documented nominal reference (may include estimated adders): 0.08563 GBP (ENGINEERING_ASSUMPTION); FX (2026-11-09): 0.8343 GBP/EUR (MARKET_DATA)
Annual escalation of energy prices (nominal EUR): 0.02 — · ENGINEERING_ASSUMPTION · MEDIUM
At the ECB/Fed inflation target — no real energy-price growth assumed (conservative)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Share of the wholesale price realised for surplus power: 0.85 — · ENGINEERING_ASSUMPTION · MEDIUM
15 % profile & balancing discount for a small seller (assumption, same for all markets)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Mineral potassium price: 0.7611 EUR/kg K₂O · CALCULATED_VALUE · MEDIUM
World Bank Pink Sheet, 12-month mean 2025M10–2026M09; ÷ nutrient share × 1.35 farm-gate markup
2025M10 / 2026M09 · checked 2026-10-27 · World commodity reference; actual digestate nutrient substitution and local fertiliser price require confirmation
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Trailing-year commodity reference: 378.6 USD/t product (MARKET_DATA); Latest-month reference (2026-09): 367.5 USD/t product (MARKET_DATA); FX (2026-11-09): 1.119 USD/EUR (MARKET_DATA); Farm-gate markup: 1.35 — (ENGINEERING_ASSUMPTION)
Mineral nitrogen price: 1.33 EUR/kg N · CALCULATED_VALUE · MEDIUM
World Bank Pink Sheet, 12-month mean 2025M10–2026M09; ÷ nutrient share × 1.35 farm-gate markup
2025M10 / 2026M09 · checked 2026-10-27 · World commodity reference; actual digestate nutrient substitution and local fertiliser price require confirmation
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Trailing-year commodity reference: 507.3 USD/t product (MARKET_DATA); Latest-month reference (2026-09): 407.5 USD/t product (MARKET_DATA); FX (2026-11-09): 1.119 USD/EUR (MARKET_DATA); Farm-gate markup: 1.35 — (ENGINEERING_ASSUMPTION)
Mineral phosphorus price: 1.678 EUR/kg P₂O₅ · CALCULATED_VALUE · MEDIUM
World Bank Pink Sheet, 12-month mean 2025M10–2026M09; ÷ nutrient share × 1.35 farm-gate markup
2025M10 / 2026M09 · checked 2026-10-27 · World commodity reference; actual digestate nutrient substitution and local fertiliser price require confirmation
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Trailing-year commodity reference: 639.8 USD/t product (MARKET_DATA); Latest-month reference (2026-09): 690 USD/t product (MARKET_DATA); FX (2026-11-09): 1.119 USD/EUR (MARKET_DATA); Farm-gate markup: 1.35 — (ENGINEERING_ASSUMPTION)
Exchange rate: 0.8343 GBP/EUR · MARKET_DATA · HIGH
Official EUR reference rate, 2026-11-09
2026-11-09 · checked 2026-11-10 · GBP per EUR; dated reference, not a guaranteed transaction rate
WITHIN_REVIEW_WINDOW: Within the 7-day review policy; applicability and latest publication must still be checked
Value of useful heat (displaced gas / boiler efficiency): 0.05957 EUR/kWh th · CALCULATED_VALUE · MEDIUM
Business gas 53.61740381157857 €/MWh LHV ÷ 0.9
2026-06-30 · checked undated · Historical national/regional reference; latest publication and customer applicability require verification
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Documented nominal reference (may include estimated adders): 40.3 GBP (ENGINEERING_ASSUMPTION); FX (2026-11-09): 0.8343 GBP/EUR (MARKET_DATA)
Evaluation horizon: 15 a · ENGINEERING_ASSUMPTION · MEDIUM
Shorter than the 20-year technical life — conservative
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Official hourly labour cost, economy-wide (wages + employer costs): 33.56 EUR/h · CALCULATED_VALUE · MEDIUM
ONS ASHE 2026 (provisional, Apr 2026): full-time median hourly pay £20.81 × 1.17 mean/median × 1.15 employer NI (15 %) and pension ≈ £28.0/h; converted at 0.8343 GBP/EUR (2026-11-09)
2026-04-30 · checked undated · Historical national/regional reference; latest publication and customer applicability require verification
WITHIN_REVIEW_WINDOW: Within the 730-day review policy; applicability and latest publication must still be checked
Documented nominal reference (may include estimated adders): 28 GBP (ENGINEERING_ASSUMPTION); FX (2026-11-09): 0.8343 GBP/EUR (MARKET_DATA)
Plant operator wage relative to the economy-wide average: 0.7 — · ENGINEERING_ASSUMPTION · MEDIUM
Plant operator ≈ 70 % of the economy-wide average hourly cost (high-income economy)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Annual escalation of operating costs (nominal EUR): 0.025 — · ENGINEERING_ASSUMPTION · MEDIUM
Inflation target + 0.5 pp wage drift
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Road transport of organic feedstock: 0.131 EUR/(t·km) · CALCULATED_VALUE · MEDIUM
0.06 €/t·km vehicle & fuel + 0.003 × driver labour cost (€/h); matches KTBL slurry haulage ≈ 0.12–0.16 €/t·km in Germany
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Loading/unloading per tonne: 1.07 EUR/t · CALCULATED_VALUE · MEDIUM
0.6 €/t pump & loader + 0.02 h/t × labour cost (KTBL Betriebsplanung machine-cost norms, scaled by national labour cost)
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Avoidable share of an unsplit customer electricity bill: 0.85 — · ENGINEERING_ASSUMPTION · LOW
Engineering judgement, no published value: energy share of an unsplit bill; customer tariff sheet takes precedence
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Customer electricity price (invoice split not verified): 0.2937 EUR/kWh · USER_INPUT · MEDIUM
USER_INPUT 0.245 GBP/kWh / FX 0.8343; Official EUR reference rate, 2026-11-09. Invoice date not supplied; energy/demand split assumed separately.
REVIEW_REQUIRED: Customer input; invoice date, contract and validity not independently verified
food_waste: dry matter: 24 % FM · MEASURED · MEDIUM
MEASURED laboratory report; replaces the catalogue value for this stream. Not independently verified.
REVIEW_REQUIRED: Customer measurement; sample, date and laboratory not independently verified