Sample report · United Kingdom
Food manufacturing and bakeries · Existing biogas (incl. a running plant)
Business situation
A gas-use scenario using the supplier's December 2014 Fawdon reference: 167 Nm³/h with 50% methane. It does not reproduce the entire factory or combine that design phase with later operating announcements. Current quotations are not disclosed.
Operating assumptions
- Operating days: 330 d/a
- Active months: 12 1–12
- Starting month: 1 1–12
- Scenario uncertainty: 50 %
- Q (biogas): 167 Nm³/h
- CH₄: 50 % vol
- Gas supply availability: 95 %
- Annual gas decline: 0 %/a
- Biogas purchase price: 0 GBP/Nm³
- N₂: 1 % vol
- O₂: 0.2 % vol
- H₂S: 500 ppmv
- Upgrading · η CH₄: 98 % CH₄
- Upgrading · kWh/Nm³: 0.3 kWh/Nm³ raw
- Upgrading → CH₄: 97 % CH₄
- Electricity: — · Electricity price on your bill (if known): —
- All year: hot water, steam, process
- Land available for spreading digestate: — · Distance to the gas grid (for biomethane): —
- Grid connection? Yes
What to verify
Confirm present gas availability, standard conditions, contaminants, actual auxiliary loads, installed conversion costs and gas ownership. Historical grants, tariffs, commissioning costs and quoted CHP capacities are not today's revenue or price data.
Reference data: Clearfleau — Fawdon reference, conference presentation, December 2014
GB; Fawdon (model climate profile is not the original site) · 2014-12 · Source checked: 2026-10-29
| Parameter | Value | Type |
|---|---|---|
| Q (biogas) | 167 Nm³/h | Reported |
| CH₄ | 50 % vol | Reported |
| CHP | ≤ 305 kWe | Design limit |
Process references
Insufficient data
Not enough data for a conclusion — fill in the missing items.
- The gas estimate is available, but project costs or auxiliary loads are unknown. An economic conclusion cannot be established.
Largest benefit — “biomethane sales”: ≈ 100 % of all revenue and savings.
- → Verify the inlet analysis and operating history, seasonal availability, and a supplier guarantee for the proposed treatment train.
- → Confirm complete installed-cost quotations, residuals disposal, final effluent treatment and the energy offtake contract. Check the downside case before investment.
- → Obtain site-specific permits and grid gas-quality requirements; extend this pre-tax screening to tax, working capital and lender cash-flow modelling.
- Project budgets, residuals disposal and auxiliary energy
Subsidies and tariffs excluded from the verdict. Preliminary screening, not an engineering design.
Key figures
Ranges: conservative — base — optimistic. We don't show fake precision.
Feedstock and energy
How far you can rely on these numbers
Low · 44/100- Backed by your data and our sources44
- You can still add+46
- Needs a feasibility study (lab, quotes, contracts)10
44/100: how much of what a screening can know about this project rests on your data and current sources. A missing input costs points in proportion to how far it could still move your result.
What you can add
- Biggest gainHeat needed per year (if known) (kWh)Large effectFuel bills for one year: gas m³ or kWh of heat+14
- Annual electricity consumption — savings from self-consumption cannot be counted without it (kWh)Large effectAdd up the kWh on your last 12 electricity bills+12
- Project budgets, residuals disposal and auxiliary energy+8
- At least one price affecting this route relies on an unconfirmed market proxy or uncontracted offtake — confirm the applicable tariff or buyer contract+6
- Electricity price on your bill (if known) (GBP/kWh)Large effectTotal of one bill divided by the kWh on it+6
With all of it: up to 90/100
High requires verified laboratory and project documents, so a screening stops at 90/100.
- CAPEX
- OPEX
- Residuals disposal cost
- Upstream electricity use
- Additional process heat
- Upgrading · CAPEX
Enter the project budget for the upstream process, including pretreatment, logistics, storage and final treatment. Gas conversion equipment and energy are calculated separately. Enter zero only for a confirmed zero cost. Exclude from this budget; calculated separately: residuals disposal cost, biogas purchase price.
- Upstream budgets must include pretreatment, logistics, storage and final treatment; they are not independently verified installed quotations.
- The treatment quotation and recovery must cover the actual H2S, siloxanes, moisture, N2 and O2. Entered product purity is a design requirement, not demonstrated gas-grid compliance.
- Market data require review (econ.electricity_spot_eur_kwh). Observation dates and validity are shown in the evidence; these are not verified current customer quotations.
- High electricity prices make on-site CHP for own use attractive; policy favours food waste over manure.
Where the energy goes
Heat produced ≠ useful heat. Heat without a user isn't income.
97/100
Of every 100 kWh of energy in the methane, 97 become a product that earns money or replaces a purchase.
100 % = 6,300 MWh of methane energy a year (LHV), base case. Every figure in this block is calculated by the model from your inputs.
Stream by stream
CalculatedEarns money
- Biomethane6,000 MWh 97 %
Losses
- Methane slip in upgrading120 MWh 2 %
- Methane leaks94 MWh 1 %
What this means for the project
- The plant buys 470 MWh of electricity a year (upgrading, pumps, mixers). It is a running cost, outside the methane balance.
- Methane leaks are 2 % of production in the base case: lost income and a greenhouse gas. Gas-tight digestate storage and regular leak checks keep them low.
What the figures rest on
- Methane leaks, base case
- 2 %Assumption
- Main product, conservative – optimistic
- 280K – 690K Nm³Calculated
How it works: from feedstock to products
- CH₄
- 628,254 Nm³/yr
- Biogas
- 1,256,508 Nm³/yr
Calculation details
Existing biogas (incl. a running plant)
Leave unknown costs and auxiliary loads blank. Economics require these inputs.
- CH₄ → CHP / Upgrading / Boiler
- 628,254 Nm³ CH₄/a
- CH₄ loss
- 0 Nm³ CH₄/a
- m residual
- 0 t/a
Enter the project budget for the upstream process, including pretreatment, logistics, storage and final treatment. Gas conversion equipment and energy are calculated separately. Enter zero only for a confirmed zero cost. Exclude from this budget; calculated separately: residuals disposal cost, biogas purchase price.
Technology & digester
Biogas / CHP / boiler
Climate: Yorkshire (York), mean 10.5 °C, ≈ 2,736 heating degree-days. Closest climate analogues: Copenhagen (DK) (Δ 1.8 °C), Dresden (DE, east) (Δ 2.6 °C), Munich (DE, Bavaria) (Δ 2.9 °C).
Monthly energy balance
Base case, chosen route. Gas energy is usable methane energy (LHV) after losses.
| Month | Feedstock, t | Gas energy, MWh | Digester heat, MWh | Useful heat, MWh | Net electricity, MWh |
|---|---|---|---|---|---|
| Jan | 0 | 524 | 0 | 0 | 0 |
| Feb | 0 | 477 | 0 | 0 | 0 |
| Mar | 0 | 524 | 0 | 0 | 0 |
| Apr | 0 | 507 | 0 | 0 | 0 |
| May | 0 | 524 | 0 | 0 | 0 |
| Jun | 0 | 507 | 0 | 0 | 0 |
| Jul | 0 | 524 | 0 | 0 | 0 |
| Aug | 0 | 524 | 0 | 0 | 0 |
| Sept | 0 | 507 | 0 | 0 | 0 |
| Oct | 0 | 524 | 0 | 0 | 0 |
| Nov | 0 | 507 | 0 | 0 | 0 |
| Dec | 0 | 524 | 0 | 0 | 0 |
| Σ | 0 | 6,170 | 0 | 0 | 0 |
Digestate and residues
No digestate: the project uses gas from an existing source; residues stay with the existing site.
Methane losses & climate
Expected losses: 3.5 % of methane produced (range 2.5 % – 4.9 %) ≈ 422 t CO₂e/yr; fossil emissions displaced ≈ 1,221 t CO₂/yr. Losses vs benefit: 35 %.
- Expected loss 3.5 % is above good practice (2 %): budget for monitoring.
- Gas-tight covers on the digester and digestate storage (incl. lagoon covers) — the single most important measure.
- Leak detection and repair (LDAR): optical gas imaging or tracer method at least yearly, plus an acceptance test after construction.
- Continuous gas-holder pressure monitoring; a standby flare instead of venting.
- CHP with an oxidation catalyst and tuning regime to cut methane slip.
Avoided emissions from open manure storage are not credited (conservative).
Permits & regulation (indicative)
Complexity: lower. “To verify” means a local lawyer or engineer must confirm the item during the feasibility study.
- Planning permission (local planning authority) incl. odour, traffic and landscapeNew installation · effort: high · to verify
- Environmental Permit (Environment Agency / SEPA / NRW / NIEA): standard rules or bespokeTreatment of waste or manure · effort: high · to verify
- DSEAR hazardous-area assessmentMethane in the gas phase · effort: medium · confirmed
- Confirm gas transfer contract, inlet quality and approvals for the new gas-use equipmentProcess-specific site conditions; no automatic legal eligibility · effort: high · to verify
Safety (risk register)
- Methane: explosion and fire (flammable range ≈ 5–15 % in air) high
- Hazardous-area (ATEX/IECEx or national) zoning and suitably rated equipment
- Fixed gas detectors in the CHP room and near tanks
- Flame arresters, over/under-pressure relief, safety flare
- Ignition-source control and hot-work permits
- Hydrogen sulphide (H₂S): acute toxicity, corrosion high
- Biological / chemical desulphurisation of the biogas
- Personal H₂S monitors, no lone working
- H₂S monitoring upstream of the CHP (engine protection)
- Confined spaces (digester, storage, pits): asphyxiation, toxic gases high
- Entry only under permit, ventilation, standby person
- Self-contained breathing apparatus for rescue
- Over/under-pressure: membrane roof rupture, tank deformation medium
- Liquid seals / relief valves venting to a safe location
- Gas-holder level and pressure sensors
- CHP: carbon monoxide, fire, high temperatures medium
- CHP room ventilation, CO detectors
- Emergency stop, fire suppression
- Soil and water pollution: slurry/digestate spills, lagoon overflow high
- Bund sized for the largest tank
- Level sensors and a spill-response plan
- Digestate storage covering the closed spreading season
Software does NOT replace a qualified process engineer and a process-safety engineer. Every final engineering design, hazardous-area classification and safe-operation programme must pass human professional review.
Assumptions used (115)
Every number has a source, date, country and confidence, and is tagged FACT / ASSUMPTION / CALCULATION / ESTIMATE. Full register: →
- Support: GGSS pays 7.09 p/kWh (2026/27, Tier 1) for 15 years on injected biomethane (≥ 50 % waste feedstock); applications until March 2028, commissioning by March 2030; no CHP tariff for new plants.
- High electricity prices make on-site CHP for own use attractive; policy favours food waste over manure.
- The verdict excludes subsidies; national support is shown as separate cases.
- This is a preliminary (screening) assessment — not a detailed engineering design and not a commercial offer.
- Financial results are pre-tax project cash flows. Depreciation, income taxes, working capital, financing fees and detailed debt covenants are not modelled; DSCR is an EBITDA-based screening ratio, not lender CFADS.
- Parameter bounds are tested individually using the applicable market/CAPEX evidence. These engineering or tariff ranges are not statistical confidence intervals and do not replace supplier quotations or customer bills.
Published technical observations; unreported inputs are engineering assumptions. No current installed budget or upstream operating accounts disclosed.
- Operating days: 330 d/a · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · GB
- Active months: 12 1–12 · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · GB
- Starting month: 1 1–12 · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · GB
- Scenario uncertainty: 50 % · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · GB
- N₂: 1 % vol · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · GB
- O₂: 0.2 % vol · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · GB
- H₂S: 500 ppmv · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · GB
- Upgrading · η CH₄: 98 % CH₄ · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · GB
- Upgrading · kWh/Nm³: 0.3 kWh/Nm³ raw · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · GB
- Upgrading → CH₄: 97 % CH₄ · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · GB
- Q (biogas): 167 Nm³/h · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · GB
- CH₄: 50 % vol · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · GB
- Gas supply availability: 95 % · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · GB
- Annual gas decline: 0 %/a · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · GB
- Biogas purchase price: 0 GBP/Nm³ · ENGINEERING_ASSUMPTION · LOW · 2026-10-29 · GB
Every number has a source, date, country and confidence, and is tagged FACT / ASSUMPTION / CALCULATION / ESTIMATE. Full register:
- Biomethane price without support, base: 0.6 EUR/Nm³ · CALCULATED_VALUE · LOW
- National estimate (project team, 2026-10) — no official series found for this item; your own price overrides it; local market for biomethane / RNG without credits
- WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
- biomethane: local CAPEX factor: 0.93 — · CALCULATED_VALUE · MEDIUM
- 0.72 traded equipment + 0.28 × local/German labour cost (23.5/31.5 €/h); split after DBFZ/Fraunhofer 2024; supplier quotes needed
- ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
- Debt interest rate (EUR-equivalent): 0.049 — · CALCULATED_VALUE · MEDIUM
- Discount rate − 1.5 pp (senior debt is cheaper than blended project capital); consistent with ECB MIR corporate loan rates + project margin; a bank term sheet replaces this
- WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
- Debt share for DSCR test: 0.65 — · ENGINEERING_ASSUMPTION · MEDIUM
- Typical agri / project lending (KfW, EBRD, IFC practice)
- ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
- Debt tenor: 10 a · ENGINEERING_ASSUMPTION · MEDIUM
- Typical
- ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
- Discount rate (nominal, pre-tax, EUR-equivalent, incl. country risk): 0.064 — · CALCULATED_VALUE · MEDIUM
- Nominal, pre-tax, EUR-equivalent: 6.0 % mature-market WACC + 0.6 × country risk premium 0.74 % (Aa3; Damodaran, 2026-07); not a bank offer
- 2026-07-01 · checked 2026-10-27 · Rating-based CRP; baseline WACC and lambda are engineering/financial assumptions
- WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
- Business electricity reference, excl. VAT (default if the customer gives none): 0.2937 EUR/kWh · CALCULATED_VALUE · MEDIUM
- DESNZ Quarterly Energy Prices, table 3.4.1 (excl. CCL & VAT), medium non-domestic consumers, mean of 2025 Q3 – 2026 Q2 (24.5 p/kWh); converted at 0.8343 GBP/EUR (2026-11-09)
- 2026-06-30 · checked undated · Historical national/regional reference; latest publication and customer applicability require verification
- WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
- Documented nominal reference (may include estimated adders): 0.245 GBP (ENGINEERING_ASSUMPTION); FX (2026-11-09): 0.8343 GBP/EUR (MARKET_DATA)
- Wholesale electricity price (market average): 0.1026 EUR/kWh · CALCULATED_VALUE · MEDIUM
- Ofgem wholesale market indicators: GB day-ahead baseload, monthly average weighted by volume (broker data), Jul 2025 – Jun 2026 mean £85.63/MWh; converted at 0.8343 GBP/EUR (2026-11-09)
- 2026-06-30 · checked undated · Historical national/regional reference; latest publication and customer applicability require verification
- REVIEW_REQUIRED: Observation is 132 days old; exceeds the 60-day review policy
- Documented nominal reference (may include estimated adders): 0.08563 GBP (ENGINEERING_ASSUMPTION); FX (2026-11-09): 0.8343 GBP/EUR (MARKET_DATA)
- Annual escalation of energy prices (nominal EUR): 0.02 — · ENGINEERING_ASSUMPTION · MEDIUM
- At the ECB/Fed inflation target — no real energy-price growth assumed (conservative)
- ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
- Share of the wholesale price realised for surplus power: 0.85 — · ENGINEERING_ASSUMPTION · MEDIUM
- 15 % profile & balancing discount for a small seller (assumption, same for all markets)
- ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
- Exchange rate: 0.8343 GBP/EUR · MARKET_DATA · HIGH
- Official EUR reference rate, 2026-11-09
- 2026-11-09 · checked 2026-11-10 · GBP per EUR; dated reference, not a guaranteed transaction rate
- WITHIN_REVIEW_WINDOW: Within the 7-day review policy; applicability and latest publication must still be checked
- Value of useful heat (displaced gas / boiler efficiency): 0.05957 EUR/kWh th · CALCULATED_VALUE · MEDIUM
- Business gas 53.61740381157857 €/MWh LHV ÷ 0.9
- 2026-06-30 · checked undated · Historical national/regional reference; latest publication and customer applicability require verification
- WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
- Documented nominal reference (may include estimated adders): 40.3 GBP (ENGINEERING_ASSUMPTION); FX (2026-11-09): 0.8343 GBP/EUR (MARKET_DATA)
- Evaluation horizon: 15 a · ENGINEERING_ASSUMPTION · MEDIUM
- Shorter than the 20-year technical life — conservative
- ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
- Official hourly labour cost, economy-wide (wages + employer costs): 33.56 EUR/h · CALCULATED_VALUE · MEDIUM
- ONS ASHE 2026 (provisional, Apr 2026): full-time median hourly pay £20.81 × 1.17 mean/median × 1.15 employer NI (15 %) and pension ≈ £28.0/h; converted at 0.8343 GBP/EUR (2026-11-09)
- 2026-04-30 · checked undated · Historical national/regional reference; latest publication and customer applicability require verification
- WITHIN_REVIEW_WINDOW: Within the 730-day review policy; applicability and latest publication must still be checked
- Documented nominal reference (may include estimated adders): 28 GBP (ENGINEERING_ASSUMPTION); FX (2026-11-09): 0.8343 GBP/EUR (MARKET_DATA)
- Plant operator wage relative to the economy-wide average: 0.7 — · ENGINEERING_ASSUMPTION · MEDIUM
- Plant operator ≈ 70 % of the economy-wide average hourly cost (high-income economy)
- ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
- Annual escalation of operating costs (nominal EUR): 0.025 — · ENGINEERING_ASSUMPTION · MEDIUM
- Inflation target + 0.5 pp wage drift
- ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
- Share of the bill actually avoided by self-generation: 0.85 — · ENGINEERING_ASSUMPTION · MEDIUM
- TOU reference: energy/Ft portion only, demand/service charges retained. Else 85% engineering allowance. User invoice uses the generic allowance until its energy/demand split is known.
- ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity