Sample report · France

Beef / mixed cattle · Dairy cows: 220 · Young / beef cattle: 180 · Catch crop silage (intermediate crop): 4,500 t/yr

A sample Extended Report for a modelled project. Your report has the same structure (the Standard Report has fewer sections) and uses your own data.

Business situation

A livestock farm in Pays de la Loire co-digests its manure with intermediate-crop silage and injects biomethane into the distribution grid — the most common model of French farm méthanisation. New farm units inject roughly 100–200 Nm³/h.

Operating assumptions

  • Dairy cows: 220 · Housed all year
  • Young / beef cattle: 180 · Housed all year
  • Catch crop silage (intermediate crop): 4,500 t/yr · DM: 25 % · 12 months · Other / don't know · Delivered from another site: 3 km · Purchase price / gate fee: 35 EUR/t
  • Electricity: 180,000 kWh/yr · Electricity price on your bill (if known): 0.155 EUR/kWh
  • No heat needed
  • Land available for spreading digestate: 380 ha · Distance to the gas grid (for biomethane): 2 km
  • Existing lagoon / store that could be covered: 3,000 m³
  • Grid connection? Yes

What to verify

Confirm the grid operator's injection capacity and connection cost, the purchase-tariff conditions and the CIVE rotation and yields.

Weak economics

Under current conditions the investment won't pay back in a reasonable time. Below is what could change that.

  • Base-case operating margin does not cover costs.
  • Even the optimistic case has a negative NPV (-€2.9M).

Main reason — ≈ 100 % of the heat has no user, so half of the plant's energy earns nothing.

What would change the verdict
  • → Lower CAPEX alone does not fix it — additional revenue streams are needed.

Subsidies and tariffs excluded from the verdict. Preliminary screening, not an engineering design.

How firm is this answer?

A clear no under these conditions: even the optimistic case does not pay back. Don't spend money on a feasibility study unless one of the changes above happens.

NPV: conservative -€4.5M · base -€3.5M · optimistic -€2.9M

The conservative case stacks every adverse assumption at once: a stress test, not the likely outcome. In 160 likely combinations the NPV was positive in < 1 % of cases.

These are screening assumptions, not independently validated accuracy limits. Confirm BMP, supplier scope, grid connection and offtake terms before an investment decision.

Key figures

Ranges: conservative — base — optimistic. We don't show fake precision.

Economics

Preliminary investment
€1.6M – €2.1M
Payback
no payback
base: no payback · no subsidies
NPV (base)
-€3.5M
range: -€4.5M … -€2.9M
Chosen route
CHP (power + heat)
Confidence: Medium

Feedstock and energy

Feedstock potential
9,500 t/yr
energy ≈ 406 kWh CH₄/t
Biogas
570K – 770K Nm³/yr
≈ 91 Nm³/h (base)
Net energy
1,000 – 1,400 MWh/yr
useful heat: 0 MWh · ≈ 85 % of your electricity use
Candidate capacity
190 kWe
small (50–250 kW)

How far you can rely on these numbers

Medium · 75/100
  • Backed by your data and our sources75
  • You can still add+15
  • Needs a feasibility study (lab, quotes, contracts)10

75/100: how much of what a screening can know about this project rests on your data and current sources. A missing input costs points in proportion to how far it could still move your result.

What you can add

  • Biggest gainLaboratory DM, VS and BMP results for every feedstock streamLarge effectSend a sample to a laboratory: dry matter and VS take a few days, BMP several weeks+15

With all of it: up to 90/100

High requires verified laboratory and project documents, so a screening stops at 90/100.

Model warnings
  • "catch crop silage (intermediate crop)": enter the harvested fresh mass that goes into the clamp; 9 % of its dry matter is lost during ensiling (KTBL) and a clamp silo is costed. If you buy finished silage out of another farm's clamp, the loss and the clamp are the seller's and this result is conservative.
  • CHP performance uses a 50 Hz biogas full-load catalogue reference (03/2025), interpolated between ratings; part-load and ambient derating require supplier confirmation.
Country conditions
  • Collective farm 'méthanisation' with grid injection is the dominant model; units under 200 kWe rarely justify upgrading on their own.

Action plan: what would make it stronger

Changes tested on this project with the same model. Break-even values show how far each must go; the scenario assumptions are LOW-confidence judgements to replace with offers.

What separates this project from “Possible with conditions”
  • The base-case NPV is negative (-€3.5M).
  • Payback in the base case is no payback; it needs to be 10 yr or less.
ChangeVerdictNPV (base)Δ NPVBreak-even
Sell the spare heat
A year-round heat buyer (drying, process heat, greenhouse or district heating) for ≈ 1,100 MWh a year, valued at ≈ €0.0747 per kWh.
Weak economics-€2.7M+€770Kheat ≥ €0.309 per kWh
Take in food waste
≈ 3,000 t a year of source-separated food waste from ≈ 15 km away, with a gate fee of €6 per tonne.
Weak economics
Biomethane
-€4.3M-€790Kgate fee ≥ €145 per tonne
Order of action
  1. 1Find a heat buyer for ≈ 1,100 MWh a year (heat ≥ €0.309 per kWh).
Scenario assumptions
  • Co-substrate share of the organic matter (VS) after it is added: 30 % · ASSUMPTION · LOW · 2026-11-02 · Judgement: usual co-digestion share at manure plants; the model applies pasteurisation, rejects and inhibition checks to the new mix.
  • Haul distance of the co-substrate: 15 km · ASSUMPTION · LOW · 2026-11-02 · Judgement: food processors within a regional collection radius.
  • Gate fee received for source-separated food waste: €6/t · ASSUMPTION · LOW · 2026-11-02 · Judgement, deliberately low. WRAP UK Gate Fees Report 2025/26 (3 July 2026): AD gate fees fell from 2024/25 and several councils paid £0 or less. The paid report gives the gate fee at which the scenario breaks even.

What to verify first

Inputs ranked by what exact knowledge is worth before you decide (expected value of perfect information). Each range is tested on its own; inputs you already supplied are not listed.

CheckNPV across the plausible rangeWorth knowing
Get supplier quotes for the plant-€4.1M … -€2.8M—
Fix feedstock prices and gate fees in contracts-€3.9M … -€3M—
Secure the feedstock supply in writing-€3.5M … -€3.1M—
Verify the market price-€3.6M … -€3.3M—
Weigh or meter the manure actually collected-€3.6M … -€3.4M—
Check the fertiliser value of the digestate-€3.5M … -€3.4M—
How to check: Get supplier quotes for the plant
  1. Send the same request to at least three suppliers.
  2. Compare like for like: scope, exclusions, guaranteed gas output, own power use, availability and the O&M price.
Request to send
Request for quotation: turnkey biogas plant
Site: France.
Feedstock (screening values, to be confirmed):
- dairy cattle slurry: 4,000 t/year, DM ≈ 11.4 %
- beef / young cattle slurry: 1,500 t/year, DM ≈ 7.5 %
- catch crop silage (intermediate crop): 4,100 t/year, DM ≈ 25.0 %
Design basis from the screening: raw biogas ≈ 91 Nm³/h at ≈ 53 % CH₄; digester working volume ≈ 1,100 m³; combined heat and power ≈ 190 kWe; new digestate storage ≈ 1,300 m³.
Please quote turnkey: feeding, digester(s), gas system with flare and desulphurisation, the gas-use equipment above, electrical and I&C, civil works, engineering and commissioning. List exclusions (grid connection, permits, land, digestate storage if separate). State the guaranteed gas output, own power and heat use, availability and the price of a full O&M contract.

Then enter it in: Step 3, “Optional: contracts and financing”: supplier quote and its technology

How to check: Fix feedstock prices and gate fees in contracts
  1. For every purchased stream and every gate fee, note today's price and its range over the last three years.
  2. Fix prices or gate fees with indexation for the loan period, and check that the plan still pays with prices 25 % worse.
Request to send
Request for a feedstock supply agreement
Site: France. A biogas plant would take:
- catch crop silage (intermediate crop): 4,100 t/year, DM ≈ 25.0 %
Please confirm the tonnes per month you can deliver, the dry matter, the delivery season, the price or gate fee per tonne with its indexation, and the term you can commit to.

Then enter it in: Feedstock step: quantity and price of each delivered stream

How to check: Secure the feedstock supply in writing
  1. List every stream you do not produce yourself: supplier, tonnes per month, season and contract term.
  2. Get letters of intent or contracts for at least the loan period, and size the plant on the tonnage that is signed, not promised.
Request to send
Request for a feedstock supply agreement
Site: France. A biogas plant would take:
- catch crop silage (intermediate crop): 4,100 t/year, DM ≈ 25.0 %
Please confirm the tonnes per month you can deliver, the dry matter, the delivery season, the price or gate fee per tonne with its indexation, and the term you can commit to.

Then enter it in: Feedstock step: quantity and price of each delivered stream

How to check: Verify the market price
  1. Check the official source shown for this price in the market-data table and compare it with your own contract.

Then enter it in: Energy step: your own price, if you have a contract

How to check: Weigh or meter the manure actually collected
  1. Count animals by group and housing period for the last 12 months.
  2. Measure slurry pit levels over 30 days (or weigh loads) and take three DM samples.

Then enter it in: Feedstock step: quantity and DM of each stream

How to check: Check the fertiliser value of the digestate
  1. Ask neighbouring farms what they would pay per tonne of digestate, delivered and spread.
  2. Check the land available for spreading against the nitrogen limit.

Then enter it in: Site step: land available for digestate

Break-even prices

Each value on its own brings the base-case NPV to zero; everything else stays as calculated.

Electricity value at NPV = 0
€0.317/kWh
now €0.0728/kWh
Highest installed cost at NPV = 0
not reachable
now €1.8M
Feedstock price headroom
€33/t
needs €33 per tonne less cost, or a gate fee, on every input

Probability range (Monte Carlo)

160 draws of the scenario quantities (yield, dry matter, CAPEX, prices, heat use, operating hours…). Energy and biomethane prices move together, the rest independently. Not a forecast: it shows how often the project stays positive when the uncertainties do not all go wrong at once.

NPV P10 (1 in 10 worse)
-€3.9M
Median NPV
-€3.6M
NPV P90 (1 in 10 better)
-€3.4M
Chance that NPV > 0
< 1 %
Median payback
no payback

Reality check: on 41 operating US farm digesters, reported power output was 0.3–1.6 × this model's estimate for 8 in 10 plants (EPA AgSTAR, self-reported). Until feedstock is weighed and lab-tested, one plant can miss the forecast by that much — more than the range above shows.

What could break the economics

Each stress test applied to the base case on its own.

Change in NPV vs base, € (base: -3.5M)

  1. CAPEX +20 %-430K
  2. Energy prices −20 %-210K
  3. Maintenance +30 %-190K
  4. CH₄ −20 %-130K
  5. CHP downtime +10 pp-75K
  6. Feedstock transport +50 %-42K
  7. Useful heat (economic) −50 %0
  8. Feedstock potential −20 %190K
NPV = 0 if CAPEX falls by
not reachable
grant, leasing, cheaper equipment
NPV = 0 if energy prices rise by
not reachable
relative to the base case

Scenarios

Route: CHP (power + heat). Scenarios bundle consistent assumptions (lower yield comes with higher CAPEX).

Revenue + savings / yr€130K
  • Electricity sales79K
  • Incremental digestate value35K
  • Electricity self-consumption savings20K
OPEX / yr€280K
  • Feedstock purchase, net of gate fees160K
  • CHP service and overhaul reserve31K
  • Staff31K
  • Maintenance28K
Operating margin (EBITDA)-€150K
ScenariosConservativeBaseOptimistic
Biogas, 1 000 Nm³/yr569.2728774.9
CAPEX€2.1M€1.8M€1.6M
OPEX / yr€300K€280K€270K
Revenue + savings / yr€88K€130K€160K
Operating margin (EBITDA)-€210K-€150K-€110K
Simple paybackno paybackno paybackno payback
Discounted paybackno paybackno paybackno payback
NPV-€4.5M-€3.5M-€2.9M
IRR———
DSCR (min)-1.5-1.3-1.1

Pre-tax, nominal EUR, 15-year horizon, discount rate of the country or your own; a screening estimate, not a bankable feasibility study. DSCR = EBITDA ÷ debt service at 65 % debt (no taxes).

Cumulative cash flow, €
-6.3M-4.7M-3M-1.3M360K03691215yearsConservativeBaseOptimistic

Biogas use routes compared

Base case. The model picks the route with the best NPV among technically sensible ones.

RouteCAPEXEBITDA / yrPaybackNPV (base)NPV low…high
CHP (power + heat) chosen€1.8M-€150Kno payback-€3.5M-€4.5M … -€2.9M
Boiler (heat only) €1.3M-€230Kno payback-€3.8M-€4.4M … -€3.4M
Biomethane €2.7M-€82Kno payback-€3.8M-€5.8M … -€1.9M
  • CHP pays when you use the power yourself and the heat is really used.
  • Biomethane: raw biogas ≈ 82 Nm³/h. The smallest upgrading units take ≈ 50–100 Nm³/h, and the cost per Nm³ falls steeply with size, so a small plant pays much more for each unit of gas.

Plant size

The same feedstock mix at other sizes, each option re-sized by the model. Extra feedstock is assumed on your terms (price, transport, disposal saving); CAPEX is the model's estimate, not your quote.

Sizet/yrBest optionkWeCAPEXNPV (base)
× 0.5 4,800CHP (power + heat)85€980K-€2M
× 0.75 7,200CHP (power + heat)140€1.4M-€2.7M
× 1 your input9,500CHP (power + heat)190€1.8M-€3.5M
× 1.5 14,000Biomethane258€3.6M-€5.2M
× 2 19,000Biomethane344€4.8M-€6.5M
× 3 29,000Biomethane516€6.4M-€9M

National support schemes — separate cases

Not in the verdict: tariffs get cut, auctions fail, grant calls close. Status and source shown for each.

Bottom line

There is a scheme your project can apply for

It improves the NPV, but the project still does not pay back its investment.

Best option: Obligation d'achat biométhane injecté Details ↓

NPV change
+€1.1M
NPV with support
-€2.3M
Payback
> 25 yr
IRR
-9.5 %

Next step: Intake is closing: check the deadline in the scheme terms and file a complete application in time.

Country overviewchecked 30 Oct 2026

Small biomethane injection tariff (≤ 13 GWh/yr, ≈ 1.1–1.25 €/Nm³) for complete requests filed by 31.12.2026; from 2027 new plants go through tenders or biogas production certificates.

Open for applications (1)

You can apply now on the published terms.

Obligation d'achat biométhane injecté

Closing soon
Biomethane support
Meets every condition we checked
NPV change
+€1.1M
NPV with support
-€2.3M
Payback
> 25 yr
IRR
-9.5 %
Conditions
  • met: Energy crops grown as a main crop: at most 15 % of fresh mass (project 0 %)
  • met: Biomethane up to 13 GWh HHV a year (project ≈ 3.8 GWh)
  • met: Biomethane injected into the gas grid (included in the case)
  • met: Raw biogas for upgrading from 60 Nm³/h (project ≈ 82 Nm³/h)
What the case uses
  • Route: Biomethane
  • Biomethane price: €1.15/Nm³
Scheme terms

11.6 → 10.1 c€/kWh HHV for 5–13 GWh/yr, indexed 1 Jan and 1 Jul; a complete request filed by 31.12.2026 keeps the right to a contract.

Next step: Intake is closing: check the deadline in the scheme terms and file a complete application in time.

Source: Arrêté 10.08.2026 (JORF 14.08.2026) amending arrêté 10.06.2023 · checked 30 Oct 2026 · Data confidence: Medium

Support never changes the verdict. Each case is pre-tax, uses the scheme's published terms and assumes the support is awarded; it does not confirm eligibility or promise funding.

Where the energy goes

Heat produced ≠ useful heat. Heat without a user isn't income.

35/100

Of every 100 kWh of energy in the methane, 35 become a product that earns money or replaces a purchase.

100 % = 3,900 MWh of methane energy a year (LHV), base case. Every figure in this block is calculated by the model from your inputs.

Stream by stream

Calculated

Earns money

  • Electricity sold to the grid1,200 MWh 31 %
  • Electricity used on site150 MWh 4 %

Runs the plant

  • Plant’s own electricity120 MWh 3 %
  • Digester heating300 MWh 8 %

Produced, not used

  • Heat with no buyer1,400 MWh 36 %

Losses

  • Conversion losses (engine, boiler)640 MWh 16 %
  • Gas sent to the flare26 MWh 0.7 %
  • Methane leaks58 MWh 1 %

What this means for the project

  • 1,400 MWh of heat a year has no buyer. A heat user nearby (drying, a greenhouse, process heat, a heating network) would turn it into income.
  • Methane leaks are 2 % of production in the base case: lost income and a greenhouse gas. Gas-tight digestate storage and regular leak checks keep them low.

What the figures rest on

Engine efficiency: electricity / heat
39 % / 48 %Assumption
Heat need
no heat userYour data
Site electricity use
180 MWhYour data
Methane leaks, base case
2 %Assumption
Main product, conservative – optimistic
1,000 – 1,400 MWhCalculated

Season: how much the digester takes for itself

In January heating the digester needs heat equal to 9 % of that month’s methane energy, in July 6 %.

January: methane energy 320 MWh · digester heating 30 MWh (9 %) · heat for a user 0 MWh

  • Methane energy of the month
  • Digester heating

How it works: from feedstock to products

  1. Feedstock9,500 t/yr
  2. Biogas730K Nm³/yr
  3. Electricity1,400 MWh
  4. Useful heat0 MWh
  5. Heat without demand1,400 MWh
  6. Digestate8,600 t/yr
Heat produced (gross)
1,674 MWh
Digester heat demand
296 MWh
Useful heat (economic)
0 MWh of 1,378
Power: own use / sold
153 / 1,209 MWh

Climate case (EU RED method)

EU Renewable Energy Directive default values for your feedstock mix, digestate storage and route. Separate from the verdict; outside the EU an indicative benchmark. Credits are valued only in the support cases where an official mechanism exists.

Emissions of the product
99 g CO₂e/MJ
open digestate storage
Fossil comparator
183 g CO₂e/MJ
Greenhouse-gas saving
46 %
RED minimum: 80 %
Avoided emissions
412 t CO₂e
  • Below the RED minimum: a gas-tight digestate store, off-gas combustion or more manure in the mix raise the saving.
  • Below 2 MW rated input the RED criteria do not apply by law; buyers and schemes may still ask for them.
  • Residues other than manure, maize and food waste use the RED biowaste values.

Scores by dimension

No single magic number. The overall score comes with its explanation.

Feedstock fit
84/100
  • Energy equivalent ≈ 190 kWe (scale score 79/100)
  • Feedstock energy ≈ 406 kWh of methane per tonne (score 65/100)
  • Feedstock available 12 of 12 months
Energy fit
32/100
  • Own consumption absorbs 11 % of the electricity produced
  • Useful heat 0 MWh of 1378 MWh available after digester needs
Location & logistics
100/100
  • No critical site constraints found from your answers
Technical feasibility
100/100
  • Standard layout for this scale, no critical obstacles
Economics
0/100
  • Operating margin ≤ 0 — no payback
  • Base-case NPV is negative
  • Minimum DSCR -1.28 — below the usual bank threshold of 1.2–1.3
Regulatory complexity
14/100 risk
  • Number and weight of permitting / regulatory steps: 8 points (more = harder)
Environmental risk
24/100 risk
  • Expected methane loss 2.5 % (good practice ≤ 2 %)
Overall project viability
40/100
  • Weighted: economics 30 %, feedstock 20 %, energy 15 %, technical 10 %, location 10 %, regulatory 7.5 %, environment 7.5 %.
  • Capped at 40: weak economics is not offset by other factors.
  • Strongest: Location & logistics (100); weakest: Economics (0).

Calculation details

Feedstock & logistics
Streamt/yrDM, %Nm³ CH₄/tLogistics / energyMax. distance
Dairy cattle slurry3,96011.418.2on site≈ 7 km
Beef / young-stock slurry1,5077.511.4on site≈ 2 km
Catch crop silage (intermediate crop)delivered 3 km4,0822573.49 %≈ 54 km

Max. distance = where haulage eats half of a tonne's energy value. Low-energy feedstock (slurry) belongs next to the plant.

Technology & digester

Wet mesophilic digestion with solids feeding

CSTR with a solids feeder and recirculation, or horizontal plug-flow for dairy manure

Working volume
≈ 1,100 m³
Retention time
40.7 days
Loading rate
3.5 kg VS/(m³·d)
Digestate storage
≈ 4,300 m³
  • Dry matter 17 % is above the pumpable limit without a solids feeder (12 %).
  • Continuous feed — continuous operation gives steady gas and the simplest control.
  • Mesophilic (≈38 °C): more robust, less heat and complexity. Thermophilic (≈52 °C) only when the benefit outweighs the complexity — rarely at this scale.
  • Single stage plus a gas-tight digestate store as post-digester: sufficient at this scale.
Alternatives
  • Horizontal plug-flow (good for 10–14 % DM cattle manure)

Climate: Pays de la Loire (Angers), mean 13.1 °C, ≈ 1,994 heating degree-days. Closest climate analogues: Dresden (DE, east) (Δ 3.4 °C), Copenhagen (DK) (Δ 3.7 °C), Prague (CZ) (Δ 3.8 °C).

Monthly energy balance

Base case, chosen route. Gas energy is usable methane energy (LHV) after losses.

MonthFeedstock, tGas energy, MWhDigester heat, MWhUseful heat, MWhNet electricity, MWh
Jan810324300116
Feb738296260105
Mar810324280116
Apr784314250112
May810324240116
Jun784314210112
Jul810324200116
Aug810324200116
Sept784314220112
Oct810324250116
Nov784314270112
Dec810324290116
Σ9,5483,82129601,362
CAPEX, OPEX, revenue (base case)
CAPEX (EUR)
Digester230K
Covering existing storage77K
New open storage78K
Feedstock reception and preparation95K
Bunker silo for the crop harvest350K
Gas handling and cleaning41K
CHP (power + heat)390K
Backup boiler2.3K
Electrical systems and controls75K
Pipework50K
Civil works75K
Grid connection31K
Engineering and permits120K
Contingency160K
Total1.8M
OPEX / yr (EUR)
Staff31K
CHP service and overhaul reserve31K
Maintenance28K
Insurance8.9K
Testing and monitoring5K
Feedstock purchase, net of gate fees160K
Feedstock transport7.6K
Digestate handling14K
Total280K
Revenue + savings / yr (EUR)
Electricity self-consumption savings20K
Electricity sales79K
Incremental digestate value35K
Total130K

Unit costs are estimates. Replace them with supplier quotations.

Digestate: asset or liability

Status: asset · 8,599 t/yr · nitrogen ≈ 56,061 kg/yr · land needed ≈ 330 ha (available 380 ha).

Incremental fertiliser value €35K/yr, handling €14K/yr, net €21K/yr.

  • Digestate storage for 6 months for the closed spreading season; keep ≈ 150 days (incl. the digester) gas-tight, otherwise methane and N are lost.
  • Spread by injection or trailing hose (not splash plate): less odour and ammonia loss.
Methane losses & climate

Expected losses: 2.5 % of methane produced (range 1.5 % – 4 %) ≈ 188 t CO₂e/yr; fossil emissions displaced ≈ 56 t CO₂/yr. Losses vs benefit: 336 %.

  • Methane losses could cancel the climate benefit. Do not claim emission reductions without measurements.
  • Expected loss 2.5 % is above good practice (2 %): budget for monitoring.
  • Gas-tight covers on the digester and digestate storage (incl. lagoon covers) — the single most important measure.
  • Leak detection and repair (LDAR): optical gas imaging or tracer method at least yearly, plus an acceptance test after construction.
  • Continuous gas-holder pressure monitoring; a standby flare instead of venting.
  • CHP with an oxidation catalyst and tuning regime to cut methane slip.

Avoided emissions from open manure storage are not credited (conservative).

Permits & regulation (indicative)

Complexity: lower. “To verify” means a local lawyer or engineer must confirm the item during the feasibility study.

  • Building permit and environmental permit; EIA screening (Directive 2011/92/EU as transposed)
    New installation · effort: medium · to verify
  • Nitrates Directive (91/676/EEC): 170 kg N/ha from organic manures in vulnerable zones; closed spreading periods
    Digestate is spread on land · effort: medium · confirmed
  • ATEX hazardous-area zoning (Directives 2014/34/EU, 1999/92/EC)
    Methane in the gas phase · effort: medium · confirmed
  • Grid-connection agreement with the DSO and generator registration
    Surplus electricity is exported · effort: medium · to verify
Safety (risk register)
  • Methane: explosion and fire (flammable range ≈ 5–15 % in air) high
    • Hazardous-area (ATEX/IECEx or national) zoning and suitably rated equipment
    • Fixed gas detectors in the CHP room and near tanks
    • Flame arresters, over/under-pressure relief, safety flare
    • Ignition-source control and hot-work permits
  • Hydrogen sulphide (H₂S): acute toxicity, corrosion high
    • Biological / chemical desulphurisation of the biogas
    • Personal H₂S monitors, no lone working
    • H₂S monitoring upstream of the CHP (engine protection)
  • Confined spaces (digester, storage, pits): asphyxiation, toxic gases high
    • Entry only under permit, ventilation, standby person
    • Self-contained breathing apparatus for rescue
  • Over/under-pressure: membrane roof rupture, tank deformation medium
    • Liquid seals / relief valves venting to a safe location
    • Gas-holder level and pressure sensors
  • CHP: carbon monoxide, fire, high temperatures medium
    • CHP room ventilation, CO detectors
    • Emergency stop, fire suppression
  • Soil and water pollution: slurry/digestate spills, lagoon overflow high
    • Bund sized for the largest tank
    • Level sensors and a spill-response plan
    • Digestate storage covering the closed spreading season

Software does NOT replace a qualified process engineer and a process-safety engineer. Every final engineering design, hazardous-area classification and safe-operation programme must pass human professional review.

Assumptions used (168)

Every number has a source, date, country and confidence, and is tagged FACT / ASSUMPTION / CALCULATION / ESTIMATE. Full register: →

  • Support: Small biomethane injection tariff (≤ 13 GWh/yr, ≈ 1.1–1.25 €/Nm³) for complete requests filed by 31.12.2026; from 2027 new plants go through tenders or biogas production certificates.
  • Collective farm 'méthanisation' with grid injection is the dominant model; units under 200 kWe rarely justify upgrading on their own.
  • The verdict excludes subsidies; national support is shown as separate cases.
  • This is a preliminary (screening) assessment — not a detailed engineering design and not a commercial offer.
  • Financial results are pre-tax project cash flows. Depreciation, income taxes, working capital, financing fees and detailed debt covenants are not modelled; DSCR is an EBITDA-based screening ratio, not lender CFADS.
  • Parameter bounds are tested individually using the applicable market/CAPEX evidence. These engineering or tariff ranges are not statistical confidence intervals and do not replace supplier quotations or customer bills.

What could break the economics

Each stress test applied to the base case on its own.

chp: local CAPEX factor
0.7 … 1.3 —
NPV low…high: -€4.1M … -€2.8M
Discount rate (nominal, pre-tax, EUR-equivalent, incl. country risk)
0.054 … 0.084 —
NPV low…high: -€3.6M … -€3.3M
Mineral potassium price
0.713 … 0.8099 EUR/kg K₂O
NPV low…high: -€3.5M … -€3.5M
Mineral nitrogen price
1.045 … 1.818 EUR/kg N
NPV low…high: -€3.5M … -€3.4M
Mineral phosphorus price
1.419 … 1.847 EUR/kg P₂O₅
NPV low…high: -€3.5M … -€3.5M
Avoidable share of an unsplit customer electricity bill
0.7 … 1 —
NPV low…high: -€3.5M … -€3.4M
Every number has a source, date, country and confidence, and is tagged FACT / ASSUMPTION / CALCULATION / ESTIMATE. Full register:
Biomethane price without support, base: 0.7162 EUR/Nm³ · CALCULATED_VALUE · MEDIUM
CALCULATION: (TTF 46.49 + GO 20.23 €/MWh HHV) × 1.11 HHV/LHV; World Bank Pink Sheet (2026-10-02), Natural gas Europe (TTF), mean Q4 2025 – Q3 2026 15.25 $/mmbtu GCV ÷ 0.2931 MWh/mmbtu at 1.1193 USD/EUR; EEX auction of biomethane GOs for the French State, Aug 2026 (production Jan–Mar 2026); × 9.6709 kWh LHV/Nm³. No guaranteed offtake or certificate eligibility.
2025-10 / 2026-09; GO 2026-08 · checked 2026-11-11 · Grid-injected biomethane, HHV prices converted to LHV; without feed-in tariffs, quotas or tax relief
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
chp: local CAPEX factor: 1 — · CALCULATED_VALUE · MEDIUM
0.72 traded equipment + 0.28 × local/German labour cost (31/31.5 €/h); split after DBFZ/Fraunhofer 2024; supplier quotes needed
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Debt interest rate (EUR-equivalent): 0.049 — · CALCULATED_VALUE · MEDIUM
Discount rate − 1.5 pp (senior debt is cheaper than blended project capital); consistent with ECB MIR corporate loan rates + project margin; a bank term sheet replaces this
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Debt share for DSCR test: 0.65 — · ENGINEERING_ASSUMPTION · MEDIUM
Typical agri / project lending (KfW, EBRD, IFC practice)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Debt tenor: 10 a · ENGINEERING_ASSUMPTION · MEDIUM
Typical
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Digestate that has no adequate land: 9.32 EUR/t · CALCULATED_VALUE · MEDIUM
Third-party export of digestate ≈ 2.5 €/t + 0.22 h/t × labour; ≈ 12 €/t in Germany, in line with manure-exchange prices in surplus regions (LWK Niedersachsen Nährstoffbericht: 10–20 €/t)
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Incremental digestate handling on adequate land: 3.68 EUR/t · CALCULATED_VALUE · MEDIUM
Pumping & trailing-hose spreading ≈ 1.2 €/t machinery + 0.08 h/t × labour; ≈ 4.8 €/t in Germany, in line with KTBL contractor rates (3–6 €/m³)
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Discount rate (nominal, pre-tax, EUR-equivalent, incl. country risk): 0.064 — · CALCULATED_VALUE · MEDIUM
Nominal, pre-tax, EUR-equivalent: 6.0 % mature-market WACC + 0.6 × country risk premium 0.74 % (Aa3; Damodaran, 2026-07); not a bank offer
2026-07-01 · checked 2026-10-27 · Rating-based CRP; baseline WACC and lambda are engineering/financial assumptions
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Wholesale electricity price (market average): 0.07685 EUR/kWh · MARKET_DATA · HIGH
ENTSO-E day-ahead (via Energy-Charts), zone FR, average 76.9 €/MWh, 2025-10-01 – 2026-10-01
2025-10-01 / 2026-10-01 · checked 2026-10-30 · Wholesale bidding zone FR; not a guaranteed export PPA
WITHIN_REVIEW_WINDOW: Within the 60-day review policy; applicability and latest publication must still be checked
Annual escalation of energy prices (nominal EUR): 0.02 — · ENGINEERING_ASSUMPTION · MEDIUM
At the ECB/Fed inflation target — no real energy-price growth assumed (conservative)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Share of the wholesale price realised for surplus power: 0.85 — · ENGINEERING_ASSUMPTION · MEDIUM
15 % profile & balancing discount for a small seller (assumption, same for all markets)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Mineral potassium price: 0.7611 EUR/kg K₂O · CALCULATED_VALUE · MEDIUM
World Bank Pink Sheet, 12-month mean 2025M10–2026M09; ÷ nutrient share × 1.35 farm-gate markup
2025M10 / 2026M09 · checked 2026-10-27 · World commodity reference; actual digestate nutrient substitution and local fertiliser price require confirmation
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Trailing-year commodity reference: 378.6 USD/t product (MARKET_DATA); Latest-month reference (2026-09): 367.5 USD/t product (MARKET_DATA); FX (2026-11-09): 1.119 USD/EUR (MARKET_DATA); Farm-gate markup: 1.35 — (ENGINEERING_ASSUMPTION)
Mineral nitrogen price: 1.33 EUR/kg N · CALCULATED_VALUE · MEDIUM
World Bank Pink Sheet, 12-month mean 2025M10–2026M09; ÷ nutrient share × 1.35 farm-gate markup
2025M10 / 2026M09 · checked 2026-10-27 · World commodity reference; actual digestate nutrient substitution and local fertiliser price require confirmation
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Trailing-year commodity reference: 507.3 USD/t product (MARKET_DATA); Latest-month reference (2026-09): 407.5 USD/t product (MARKET_DATA); FX (2026-11-09): 1.119 USD/EUR (MARKET_DATA); Farm-gate markup: 1.35 — (ENGINEERING_ASSUMPTION)
Mineral phosphorus price: 1.678 EUR/kg P₂O₅ · CALCULATED_VALUE · MEDIUM
World Bank Pink Sheet, 12-month mean 2025M10–2026M09; ÷ nutrient share × 1.35 farm-gate markup
2025M10 / 2026M09 · checked 2026-10-27 · World commodity reference; actual digestate nutrient substitution and local fertiliser price require confirmation
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Trailing-year commodity reference: 639.8 USD/t product (MARKET_DATA); Latest-month reference (2026-09): 690 USD/t product (MARKET_DATA); FX (2026-11-09): 1.119 USD/EUR (MARKET_DATA); Farm-gate markup: 1.35 — (ENGINEERING_ASSUMPTION)
Exchange rate: 1 EUR/EUR · MARKET_DATA · HIGH
Euro
CONSTANT: EUR reporting currency; no currency conversion
Value of useful heat (displaced gas / boiler efficiency): 0.07474 EUR/kWh th · CALCULATED_VALUE · MEDIUM
Business gas 67.266 €/MWh LHV ÷ 0.9
2026-S1 · checked 2026-10-31 · GJ10000-99999; reference band, customer gas use unknown
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Evaluation horizon: 15 a · ENGINEERING_ASSUMPTION · MEDIUM
Shorter than the 20-year technical life — conservative
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Official hourly labour cost, economy-wide (wages + employer costs): 44.3 EUR/h · MARKET_DATA · HIGH
Eurostat lc_lci_lev: hourly labour cost (wages + employer costs), industry, construction & services, 2025
WITHIN_REVIEW_WINDOW: Within the 730-day review policy; applicability and latest publication must still be checked
Plant operator wage relative to the economy-wide average: 0.7 — · ENGINEERING_ASSUMPTION · MEDIUM
Plant operator ≈ 70 % of the economy-wide average hourly cost (high-income economy)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Annual escalation of operating costs (nominal EUR): 0.025 — · ENGINEERING_ASSUMPTION · MEDIUM
Inflation target + 0.5 pp wage drift
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Road transport of organic feedstock: 0.153 EUR/(t·km) · CALCULATED_VALUE · MEDIUM
0.06 €/t·km vehicle & fuel + 0.003 × driver labour cost (€/h); matches KTBL slurry haulage ≈ 0.12–0.16 €/t·km in Germany
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Loading/unloading per tonne: 1.22 EUR/t · CALCULATED_VALUE · MEDIUM
0.6 €/t pump & loader + 0.02 h/t × labour cost (KTBL Betriebsplanung machine-cost norms, scaled by national labour cost)
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Avoidable share of an unsplit customer electricity bill: 0.85 — · ENGINEERING_ASSUMPTION · LOW
Engineering judgement, no published value: energy share of an unsplit bill; customer tariff sheet takes precedence
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Customer electricity price (invoice split not verified): 0.155 EUR/kWh · USER_INPUT · MEDIUM
USER_INPUT 0.155 EUR/kWh / FX 1; Euro. Invoice date not supplied; energy/demand split assumed separately.
REVIEW_REQUIRED: Customer input; invoice date, contract and validity not independently verified