Sample report · Spain

Retail, wholesale markets & supermarket chains · Source-separated food waste: 12,000 t/yr

A sample Extended Report for a modelled project. Your report has the same structure (the Standard Report has fewer sections) and uses your own data.

Business situation

A Barcelona-type wholesale food market collects unsold produce and organic waste from hundreds of traders and pays an external facility to treat it. Here the market company digests it on site and uses the power for its cold stores. Mercabarna reported about 30,000 t of commercial waste a year (2016).

Operating assumptions

  • Source-separated food waste: 12,000 t/yr · DM: 14 % · 12 months · We pay for collection / disposal · What you pay for disposal: 55 EUR/t
  • Electricity: 9,000,000 kWh/yr · Electricity price on your bill (if known): 0.133 EUR/kWh
  • All year: hot water, steam, process · Heat needed per year (if known): 2,500,000 kWh/yr
  • Land available for spreading digestate: 0 ha · Distance to the gas grid (for biomethane): 0.5 km
  • Grid connection? Yes

What to verify

Confirm tonnage and composition by month, the current treatment contract, space and odour control on site, and the digestate outlet.

Strong candidate

Worth detailed work: the project holds up even under conservative assumptions.

  • Simple payback ≈ 4.2 yrs (base) and ≈ 9.8 yrs in the conservative case; base NPV €4M; minimum DSCR 2.85.

Largest benefit — “avoided waste-disposal cost”: ≈ 63 % of all revenue and savings.

What would change the verdict
  • → Confirm with a laboratory feedstock analysis (BMP) and real energy invoices.

Subsidies and tariffs excluded from the verdict. Preliminary screening, not an engineering design.

How firm is this answer?

Robust: profitable even in the conservative case (lower gas yield, higher CAPEX, lower prices). The next step is worth paying for.

NPV: conservative €65K · base €4M · optimistic €5.6M

The conservative case stacks every adverse assumption at once: a stress test, not the likely outcome. In 160 likely combinations the NPV was positive in > 99 % of cases.

Biggest drivers of the result (stress tests):
  1. Feedstock potential −20 % (-€1.6M)
  2. Lab test of the methane yield (BMP) · CH₄ −20 % (-€750K)
  3. Get an offer for exported power (PPA or tariff) · Energy prices −20 % (-€750K)

These are screening assumptions, not independently validated accuracy limits. Confirm BMP, supplier scope, grid connection and offtake terms before an investment decision.

To reach a bankable estimate (±15 %)
  1. Laboratory methane-potential (BMP) test of 2–3 feedstock samples — ≈ €300–800 each
  2. 2–3 supplier quotes for the plant
  3. Grid or gas-network connection conditions from the operator
  4. Letters of intent for feedstock supply and for heat, power or biomethane offtake
  5. Then a feasibility study with permits and financing (±15 %)
From screening to construction

Key figures

Ranges: conservative — base — optimistic. We don't show fake precision.

Economics

Preliminary investment
€2.5M – €3.4M
Payback
3.1 yr – 9.8 yr
base: 4.2 yr · no subsidies
NPV (base)
€4M
range: €65K … €5.6M
Chosen route
CHP (power + heat)
Confidence: Medium

Feedstock and energy

Feedstock potential
12,000 t/yr
energy ≈ 528 kWh CH₄/t
Biogas
810K – 1.2M Nm³/yr
≈ 132 Nm³/h (base)
Net energy
1,700 – 2,400 MWh/yr
useful heat: 980 – 2,300 MWh · ≈ 26 % of your electricity use
Candidate capacity
320 kWe
medium (0.25–1 MW)

How far you can rely on these numbers

Medium · 75/100
  • Backed by your data and our sources75
  • You can still add+15
  • Needs a feasibility study (lab, quotes, contracts)10

75/100: how much of what a screening can know about this project rests on your data and current sources. A missing input costs points in proportion to how far it could still move your result.

What you can add

  • Biggest gainLaboratory DM, VS and BMP results for every feedstock streamLarge effectSend a sample to a laboratory: dry matter and VS take a few days, BMP several weeks+15

With all of it: up to 90/100

High requires verified laboratory and project documents, so a screening stops at 90/100.

Model warnings
  • Animal by-products (Cat. 3) → pasteurisation and veterinary approval required.
  • In this configuration the digestate is a cost rather than an asset.
  • CHP performance uses a 50 Hz biogas full-load catalogue reference (03/2025), interpolated between ratings; part-load and ambient derating require supplier confirmation.
Compared with the market
Our estimate: ≈ 8,800 €/kW at ≈ 320 kW
  • 3,400–7,500 EUR/kW — Flexible plant, Germany · above rangeDBFZ / Fraunhofer IEE for BMWK (February 2024): €7,521 per kW rated (≈ €3,400 per kW installed) capacity · 2023 · Official study
  • 2,800–7,000 EUR/kW — Agricultural plants, Poland · above rangePolish trade press 2023–2024 (PLN 7–20 m for 500 kW; PLN 12–16 m for 1 MW); IOŚ-PIB: ≈ PLN 30 m for 1 MW · 2023–2024 · Trade press

Market figures are mostly trade press and supplier estimates, not audited budgets. Real prices come from 3–5 supplier quotes.

Country conditions
  • Pig-dense regions (Catalonia, Aragón) face nitrate pressure: digestate treatment can be as important as energy.

Action plan: what would make it stronger

Changes tested on this project with the same model. Break-even values show how far each must go; the scenario assumptions are LOW-confidence judgements to replace with offers.

Order of action
  1. 1Ask 3–5 suppliers for quotes: the project breaks even up to an investment of €6M. →

What to verify first

Inputs ranked by what exact knowledge is worth before you decide (expected value of perfect information). Each range is tested on its own; inputs you already supplied are not listed.

CheckNPV across the plausible rangeWorth knowing
Get supplier quotes for the plant€3M … €5M—
Verify the market price€3.1M … €4.5M—
Check how your bill splits energy and capacity charges€3.5M … €4.4M—
Lab test of the methane yield (BMP)€3.2M … €4M—
Confirm a reliable heat buyer and demand€3.7M … €4.2M—
How to check: Get supplier quotes for the plant
  1. Send the same request to at least three suppliers.
  2. Compare like for like: scope, exclusions, guaranteed gas output, own power use, availability and the O&M price.
Request to send
Request for quotation: turnkey biogas plant
Site: Spain.
Feedstock (screening values, to be confirmed):
- source-separated food waste: 12,000 t/year, DM ≈ 14.0 %
Design basis from the screening: raw biogas ≈ 130 Nm³/h at ≈ 60 % CH₄; digester working volume ≈ 1,200 m³; combined heat and power ≈ 320 kWe; new digestate storage ≈ 5,400 m³.
Please quote turnkey: feeding, digester(s), gas system with flare and desulphurisation, the gas-use equipment above, electrical and I&C, civil works, engineering and commissioning. List exclusions (grid connection, permits, land, digestate storage if separate). State the guaranteed gas output, own power and heat use, availability and the price of a full O&M contract.

Then enter it in: Step 3, “Optional: contracts and financing”: supplier quote and its technology

How to check: Verify the market price
  1. Check the official source shown for this price in the market-data table and compare it with your own contract.

Then enter it in: Energy step: your own price, if you have a contract

How to check: Check how your bill splits energy and capacity charges
  1. Take the last 12 electricity invoices.
  2. Split each into the energy part (per kWh) and capacity, network and fixed charges; own generation saves mainly the energy part.

Then enter it in: Energy step: electricity price per kWh (energy part, excl. VAT)

How to check: Lab test of the methane yield (BMP)
  1. Take 3–5 subsamples of each stream over 2–4 weeks, mix them, keep them at 4 °C and deliver within 24 h.
  2. Order dry matter (DM), volatile solids (VS) and a methane potential test (BMP, VDI 4630) with the cellulose control reported.
  3. A valid test reports cellulose at 340–395 NL CH₄/kg VS; ask for a repeat otherwise.
Request to send
Request for quotation: biogas potential analysis
Site: Spain.
Feedstock (screening values, to be confirmed):
- source-separated food waste: 12,000 t/year, DM ≈ 14.0 %
Design basis from the screening: raw biogas ≈ 130 Nm³/h at ≈ 60 % CH₄; digester working volume ≈ 1,200 m³; combined heat and power ≈ 320 kWe; new digestate storage ≈ 5,400 m³.
Per sample please quote: dry matter (DM, % of fresh mass), volatile solids (VS, % of DM) and biochemical methane potential (BMP, NL CH₄ per kg VS) to VDI 4630, with the cellulose control result and the test duration. Please state price, turnaround time and sampling and shipping instructions.

Then enter it in: Feedstock step: DM, VS and BMP on each stream

How to check: Confirm a reliable heat buyer and demand
  1. Confirm the buyer's monthly heat demand and the temperature they need.
  2. Agree a price per kWh linked to their current fuel, and a term of at least the loan period.
Request to send
Offer of renewable heat
Site: Spain. A biogas plant can supply ≈ 2,300 MWh of heat a year (hot water, ≈ 80–90 °C) all year round. Please tell us your monthly heat use, the temperature you need, your current fuel and its price, and the price per kWh and term you would accept.

Then enter it in: Energy step: price the heat buyer pays per kWh

Break-even prices

Each value on its own brings the base-case NPV to zero; everything else stays as calculated.

Electricity value at NPV = 0
positive even if the product earns nothing
now €0.113/kWh
Highest installed cost at NPV = 0
€6M
now €2.8M
Feedstock price headroom
€31.2/t
can pay up to €31.2 per tonne more for every input

Probability range (Monte Carlo)

160 draws of the scenario quantities (yield, dry matter, CAPEX, prices, heat use, operating hours…). Energy and biomethane prices move together, the rest independently. Not a forecast: it shows how often the project stays positive when the uncertainties do not all go wrong at once.

NPV P10 (1 in 10 worse)
€2.3M
Median NPV
€3.2M
NPV P90 (1 in 10 better)
€3.7M
Chance that NPV > 0
> 99 %
Median payback
4.9 yr

No real-plant check for this type of project yet: we have no open data on operating plants like this one to compare with the model. The range above shows only the model's own uncertainty; confirm the gas yield with a lab test (BMP) or a pilot first.

What could break the economics

Each stress test applied to the base case on its own.

Change in NPV vs base, € (base: 4M)

  1. Feedstock potential −20 %-1.6M
  2. CH₄ −20 %-750K
  3. Energy prices −20 %-750K
  4. CAPEX +20 %-690K
  5. Useful heat (economic) −50 %-560K
  6. CHP downtime +10 pp-410K
  7. Maintenance +30 %-290K
  8. Feedstock transport +50 %0
NPV = 0 if CAPEX falls by
already positive
grant, leasing, cheaper equipment
NPV = 0 if energy prices rise by
already positive
relative to the base case

Scenarios

Route: CHP (power + heat). Scenarios bundle consistent assumptions (lower yield comes with higher CAPEX).

Revenue + savings / yr€1M
  • Avoided disposal cost630K
  • Electricity self-consumption savings260K
  • Useful heat (economic)110K
OPEX / yr€330K
  • Disposal of pre-treatment rejects120K
  • Digestate handling70K
  • Maintenance46K
  • CHP service and overhaul reserve45K
Operating margin (EBITDA)€670K
ScenariosConservativeBaseOptimistic
Biogas, 1 000 Nm³/yr811.11,059.51,207.4
CAPEX€3.4M€2.8M€2.5M
OPEX / yr€340K€330K€310K
Revenue + savings / yr€690K€1M€1.1M
Operating margin (EBITDA)€340K€670K€810K
Simple payback9.8 yr4.2 yr3.1 yr
Discounted payback14.6 yr5.3 yr3.9 yr
NPV€65K€4M€5.6M
IRR7.2 %23.2 %31 %
DSCR (min)1.22.93.8

Pre-tax, nominal EUR, 15-year horizon, discount rate of the country or your own; a screening estimate, not a bankable feasibility study. DSCR = EBITDA ÷ debt service at 65 % debt (no taxes).

Cumulative cash flow, €
-4.2M-120K4M8.1M12M03691215yearsConservativeBaseOptimistic

Biogas use routes compared

Base case. The model picks the route with the best NPV among technically sensible ones.

RouteCAPEXEBITDA / yrPaybackNPV (base)NPV low…high
CHP (power + heat) chosen€2.8M€670K4.2 yr€4M€65K … €5.6M
Boiler (heat only) €2.2M€450K4.9 yr€2.4M-€370K … €3.5M
Biomethane €3.5M€640K5.4 yr€3M-€1.4M … €5.9M
  • CHP pays when you use the power yourself and the heat is really used.
  • Biomethane: raw biogas ≈ 123 Nm³/h. The smallest upgrading units take ≈ 50–100 Nm³/h, and the cost per Nm³ falls steeply with size, so a small plant pays much more for each unit of gas.

Plant size

The same feedstock mix at other sizes, each option re-sized by the model. Extra feedstock is assumed on your terms (price, transport, disposal saving); CAPEX is the model's estimate, not your quote.

Sizet/yrBest optionkWeCAPEXNPV (base)
× 0.5 6,000CHP (power + heat)150€1.7M€1.5M
× 0.75 9,000CHP (power + heat)240€2.2M€2.7M
× 1 your input12,000CHP (power + heat)320€2.8M€4M
× 1.5 18,000CHP (power + heat)470€3.9M€6M
× 2 24,000CHP (power + heat)670€5M€8.3M
× 3 36,000Biomethane843€7.6M€13M

National support schemes — separate cases

Not in the verdict: tariffs get cut, auctions fail, grant calls close. Status and source shown for each.

Bottom line

There is no support for new projects that we could calculate — see the country overview

No support scheme for new projects is modelled for this country.

Country overviewchecked 30 Oct 2026

No open support: IDAE biogas grants have no active call, and a biomethane quota (0.5 % in 2028 → 6 % in 2035) is still a draft decree.

Support never changes the verdict. Each case is pre-tax, uses the scheme's published terms and assumes the support is awarded; it does not confirm eligibility or promise funding.

Where the energy goes

Heat produced ≠ useful heat. Heat without a user isn't income.

65/100

Of every 100 kWh of energy in the methane, 65 become a product that earns money or replaces a purchase.

100 % = 6,300 MWh of methane energy a year (LHV), base case. Every figure in this block is calculated by the model from your inputs.

Stream by stream

Calculated

Earns money

  • Electricity used on site2,300 MWh 36 %
  • Heat for a user1,800 MWh 29 %

Runs the plant

  • Plant’s own electricity200 MWh 3 %
  • Digester heating330 MWh 5 %

Produced, not used

  • Heat with no buyer460 MWh 7 %

Losses

  • Conversion losses (engine, boiler)1,100 MWh 18 %
  • Methane leaks95 MWh 2 %

What this means for the project

  • 460 MWh of heat a year has no buyer. A heat user nearby (drying, a greenhouse, process heat, a heating network) would turn it into income. At the heat value used in this case that is about €28K a year.
  • Methane leaks are 2 % of production in the base case: lost income and a greenhouse gas. Gas-tight digestate storage and regular leak checks keep them low.

What the figures rest on

Engine efficiency: electricity / heat
40 % / 46 %Assumption
Heat need
2,500 MWhYour data
Site electricity use
9,000 MWhYour data
Methane leaks, base case
2 %Assumption
Main product, conservative – optimistic
1,700 – 2,400 MWhCalculated

Season: how much the digester takes for itself

In January heating the digester needs heat equal to 7 % of that month’s methane energy, in July 4 %.

January: methane energy 530 MWh · digester heating 35 MWh (7 %) · heat for a user 150 MWh

  • Methane energy of the month
  • Digester heating
  • Heat for a user

How it works: from feedstock to products

  1. Feedstock12,000 t/yr
  2. Biogas1.1M Nm³/yr
  3. Electricity2,300 MWh
  4. Useful heat1,800 MWh
  5. Heat without demand460 MWh
  6. Digestate11,000 t/yr
Heat produced (gross)
2,619 MWh
Digester heat demand
333 MWh
Useful heat (economic)
1,828 MWh of 2,285
Power: own use / sold
2,298 / 0 MWh

Climate case (EU RED method)

EU Renewable Energy Directive default values for your feedstock mix, digestate storage and route. Separate from the verdict; outside the EU an indicative benchmark. Credits are valued only in the support cases where an official mechanism exists.

Emissions of the product
87 g CO₂e/MJ
open digestate storage
Fossil comparator
183 g CO₂e/MJ
Greenhouse-gas saving
52 %
RED minimum: 80 %
Avoided emissions
1,114 t CO₂e
  • Below the RED minimum: a gas-tight digestate store, off-gas combustion or more manure in the mix raise the saving.
  • Below 2 MW rated input the RED criteria do not apply by law; buyers and schemes may still ask for them.

Scores by dimension

No single magic number. The overall score comes with its explanation.

Feedstock fit
89/100
  • Energy equivalent ≈ 320 kWe (scale score 87/100)
  • Feedstock energy ≈ 528 kWh of methane per tonne (score 71/100)
  • Feedstock available 12 of 12 months
Energy fit
90/100
  • Own consumption absorbs 100 % of the electricity produced
  • Useful heat 1828 MWh of 2285 MWh available after digester needs
Location & logistics
50/100
  • Neighbours within 300 m: odour, traffic, safety distances
  • Not enough land for the digestate
Technical feasibility
90/100
  • ABP pasteurisation adds complexity
Economics
98/100
  • Base-case simple payback ≈ 4.2 years
  • NPV positive even in the conservative case
Regulatory complexity
32/100 risk
  • Number and weight of permitting / regulatory steps: 12 points (more = harder)
Environmental risk
59/100 risk
  • Expected methane loss 2.5 % (good practice ≤ 2 %)
  • Neighbours within 300 m: odour and incident exposure
  • Surplus digestate: risk of nitrogen over-application
Overall project viability
83/100
  • Weighted: economics 30 %, feedstock 20 %, energy 15 %, technical 10 %, location 10 %, regulatory 7.5 %, environment 7.5 %.
  • Strongest: Economics (98); weakest: Environmental risk (41).

Calculation details

Feedstock & logistics
Streamt/yrDM, %Nm³ CH₄/tLogistics / energyMax. distance
Source-separated food waste12,0001453on site≈ 128 km

Max. distance = where haulage eats half of a tonne's energy value. Low-energy feedstock (slurry) belongs next to the plant.

Technology & digester

Wet mesophilic digestion with solids feeding

CSTR with a solids feeder and recirculation, or horizontal plug-flow for dairy manure

Working volume
≈ 1,200 m³
Retention time
35.2 days
Loading rate
3.5 kg VS/(m³·d)
Digestate storage
≈ 5,400 m³
  • Dry matter 14 % is above the pumpable limit without a solids feeder (12 %).
  • Continuous feed — continuous operation gives steady gas and the simplest control.
  • Mesophilic (≈38 °C): more robust, less heat and complexity. Thermophilic (≈52 °C) only when the benefit outweighs the complexity — rarely at this scale.
  • Two-stage layout (main + post-digester) for stability with fats or larger flows.
Alternatives
  • Horizontal plug-flow (good for 10–14 % DM cattle manure)
  • Separate pasteurisation (70 °C / 1 h) ahead of a mesophilic digester instead of thermophilic operation

Climate: Catalonia (Lleida), mean 17.6 °C, ≈ 1,202 heating degree-days. Closest climate analogues: Dresden (DE, east) (Δ 7.5 °C), Prague (CZ) (Δ 7.7 °C), Copenhagen (DK) (Δ 8.2 °C).

Monthly energy balance

Base case, chosen route. Gas energy is usable methane energy (LHV) after losses.

MonthFeedstock, tGas energy, MWhDigester heat, MWhUseful heat, MWhNet electricity, MWh
Jan1,01853035150195
Feb92848330138178
Mar1,01853031153195
Apr98651328150189
May1,01853026157195
Jun98651323153189
Jul1,01853023159195
Aug1,01853023159195
Sept98651324153189
Oct1,01853027156195
Nov98651330148189
Dec1,01853034151195
Σ12,0006,2433331,8282,298
CAPEX, OPEX, revenue (base case)
CAPEX (EUR)
Digester220K
New covered storage360K
New open storage100K
Feedstock reception and preparation610K
Pasteurisation (70 °C / 1 h)110K
Gas handling and cleaning40K
CHP (power + heat)510K
Heat network54K
Backup boiler2.4K
Electrical systems and controls120K
Pipework80K
Civil works120K
Grid connection34K
Engineering and permits190K
Contingency250K
Total2.8M
OPEX / yr (EUR)
Staff26K
CHP service and overhaul reserve45K
Maintenance46K
Insurance14K
Testing and monitoring5K
Disposal of pre-treatment rejects120K
Digestate handling70K
Total330K
Revenue + savings / yr (EUR)
Electricity self-consumption savings260K
Useful heat (economic)110K
Avoided disposal cost630K
Total1M

Unit costs are estimates. Replace them with supplier quotations.

Digestate: asset or liability

Status: liability / cost · 10,706 t/yr · nitrogen ≈ 50,782 kg/yr · land needed ≈ 299 ha (available 0 ha).

Incremental fertiliser value €0/yr, handling €70K/yr, net -€70K/yr.

  • Not enough land: ≈ 299 ha needed at 170 kg N/ha. Surplus digestate is a cost (agreements with neighbours, separation, pelletising).
  • Digestate storage for 6 months for the closed spreading season; keep ≈ 150 days (incl. the digester) gas-tight, otherwise methane and N are lost.
  • Spread by injection or trailing hose (not splash plate): less odour and ammonia loss.
Methane losses & climate

Expected losses: 2.5 % of methane produced (range 1.6 % – 4 %) ≈ 306 t CO₂e/yr; fossil emissions displaced ≈ 723 t CO₂/yr. Losses vs benefit: 42 %.

  • Expected loss 2.5 % is above good practice (2 %): budget for monitoring.
  • Gas-tight covers on the digester and digestate storage (incl. lagoon covers) — the single most important measure.
  • Leak detection and repair (LDAR): optical gas imaging or tracer method at least yearly, plus an acceptance test after construction.
  • Continuous gas-holder pressure monitoring; a standby flare instead of venting.
  • CHP with an oxidation catalyst and tuning regime to cut methane slip.

Avoided emissions from open manure storage are not credited (conservative).

Permits & regulation (indicative)

Complexity: lower. “To verify” means a local lawyer or engineer must confirm the item during the feasibility study.

  • Building permit and environmental permit; EIA screening (Directive 2011/92/EU as transposed)
    New installation · effort: medium · to verify
  • Nitrates Directive (91/676/EEC): 170 kg N/ha from organic manures in vulnerable zones; closed spreading periods
    Digestate is spread on land · effort: medium · confirmed
  • ATEX hazardous-area zoning (Directives 2014/34/EU, 1999/92/EC)
    Methane in the gas phase · effort: medium · confirmed
  • Animal by-products approval: pasteurisation 70 °C / 1 h (Cat. 3) or pressure sterilisation (Cat. 2), veterinary registration
    Slaughter / dairy / food residues in the feed · effort: high · to verify
  • Setback distances, odour assessment and community consultation
    Housing within 300 m · effort: high · to verify
Safety (risk register)
  • Methane: explosion and fire (flammable range ≈ 5–15 % in air) high
    • Hazardous-area (ATEX/IECEx or national) zoning and suitably rated equipment
    • Fixed gas detectors in the CHP room and near tanks
    • Flame arresters, over/under-pressure relief, safety flare
    • Ignition-source control and hot-work permits
  • Hydrogen sulphide (H₂S): acute toxicity, corrosion high
    • Biological / chemical desulphurisation of the biogas
    • Personal H₂S monitors, no lone working
    • H₂S monitoring upstream of the CHP (engine protection)
  • Confined spaces (digester, storage, pits): asphyxiation, toxic gases high
    • Entry only under permit, ventilation, standby person
    • Self-contained breathing apparatus for rescue
  • Over/under-pressure: membrane roof rupture, tank deformation medium
    • Liquid seals / relief valves venting to a safe location
    • Gas-holder level and pressure sensors
  • CHP: carbon monoxide, fire, high temperatures medium
    • CHP room ventilation, CO detectors
    • Emergency stop, fire suppression
  • Biological hazards: pathogens in animal by-products and food waste high
    Condition: Animal by-products / food waste in the mix
    • Pasteurisation 70 °C / 1 h (Cat. 3) with time–temperature control
    • Separate dirty and clean zones, vehicle disinfection
    • Veterinary supervision and traceability
  • Soil and water pollution: slurry/digestate spills, lagoon overflow high
    • Bund sized for the largest tank
    • Level sensors and a spill-response plan
    • Digestate storage covering the closed spreading season
  • Odour and noise for neighbours; blast exposure medium
    Condition: Housing within 300 m
    • Enclosed reception and storage, injection spreading
    • Community consultation before design; consequence assessment

Software does NOT replace a qualified process engineer and a process-safety engineer. Every final engineering design, hazardous-area classification and safe-operation programme must pass human professional review.

Assumptions used (163)

Every number has a source, date, country and confidence, and is tagged FACT / ASSUMPTION / CALCULATION / ESTIMATE. Full register: →

  • Support: No open support: IDAE biogas grants have no active call, and a biomethane quota (0.5 % in 2028 → 6 % in 2035) is still a draft decree.
  • Pig-dense regions (Catalonia, Aragón) face nitrate pressure: digestate treatment can be as important as energy.
  • The verdict excludes subsidies; national support is shown as separate cases.
  • This is a preliminary (screening) assessment — not a detailed engineering design and not a commercial offer.
  • Financial results are pre-tax project cash flows. Depreciation, income taxes, working capital, financing fees and detailed debt covenants are not modelled; DSCR is an EBITDA-based screening ratio, not lender CFADS.
  • Parameter bounds are tested individually using the applicable market/CAPEX evidence. These engineering or tariff ranges are not statistical confidence intervals and do not replace supplier quotations or customer bills.

What could break the economics

Each stress test applied to the base case on its own.

chp: local CAPEX factor
0.616 … 1.144 —
NPV low…high: €3M … €5M
Discount rate (nominal, pre-tax, EUR-equivalent, incl. country risk)
0.059 … 0.089 —
NPV low…high: €3.1M … €4.5M
Avoidable share of an unsplit customer electricity bill
0.7 … 1 —
NPV low…high: €3.5M … €4.4M
Every number has a source, date, country and confidence, and is tagged FACT / ASSUMPTION / CALCULATION / ESTIMATE. Full register:
Biomethane price without support, base: 0.6925 EUR/Nm³ · CALCULATED_VALUE · LOW
CALCULATION: TTF 46.49 €/MWh HHV × 1.11 HHV/LHV + 20 €/MWh LHV green-gas premium (engineering assumption, no official GO price); World Bank Pink Sheet (2026-10-02), Natural gas Europe (TTF), mean Q4 2025 – Q3 2026 15.25 $/mmbtu GCV ÷ 0.2931 MWh/mmbtu at 1.1193 USD/EUR; × 9.6709 kWh LHV/Nm³. No guaranteed offtake or certificate eligibility.
2025-10 / 2026-09 · checked 2026-11-11 · Grid-injected biomethane, HHV prices converted to LHV; without feed-in tariffs, quotas or tax relief
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
chp: local CAPEX factor: 0.88 — · CALCULATED_VALUE · MEDIUM
0.72 traded equipment + 0.28 × local/German labour cost (18.5/31.5 €/h); split after DBFZ/Fraunhofer 2024; supplier quotes needed
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Debt interest rate (EUR-equivalent): 0.054 — · CALCULATED_VALUE · MEDIUM
Discount rate − 1.5 pp (senior debt is cheaper than blended project capital); consistent with ECB MIR corporate loan rates + project margin; a bank term sheet replaces this
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Debt share for DSCR test: 0.65 — · ENGINEERING_ASSUMPTION · MEDIUM
Typical agri / project lending (KfW, EBRD, IFC practice)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Debt tenor: 10 a · ENGINEERING_ASSUMPTION · MEDIUM
Typical
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Digestate that has no adequate land: 6.57 EUR/t · CALCULATED_VALUE · MEDIUM
Third-party export of digestate ≈ 2.5 €/t + 0.22 h/t × labour; ≈ 12 €/t in Germany, in line with manure-exchange prices in surplus regions (LWK Niedersachsen Nährstoffbericht: 10–20 €/t)
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Incremental digestate handling on adequate land: 2.68 EUR/t · CALCULATED_VALUE · MEDIUM
Pumping & trailing-hose spreading ≈ 1.2 €/t machinery + 0.08 h/t × labour; ≈ 4.8 €/t in Germany, in line with KTBL contractor rates (3–6 €/m³)
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Discount rate (nominal, pre-tax, EUR-equivalent, incl. country risk): 0.069 — · CALCULATED_VALUE · MEDIUM
Nominal, pre-tax, EUR-equivalent: 6.0 % mature-market WACC + 0.6 × country risk premium 1.48 % (A3; Damodaran, 2026-07); not a bank offer
2026-07-01 · checked 2026-10-27 · Rating-based CRP; baseline WACC and lambda are engineering/financial assumptions
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Wholesale electricity price (market average): 0.07351 EUR/kWh · MARKET_DATA · HIGH
ENTSO-E day-ahead (via Energy-Charts), zone ES, average 73.5 €/MWh, 2025-10-01 – 2026-10-01
2025-10-01 / 2026-10-01 · checked 2026-10-31 · Wholesale bidding zone ES; not a guaranteed export PPA
WITHIN_REVIEW_WINDOW: Within the 60-day review policy; applicability and latest publication must still be checked
Annual escalation of energy prices (nominal EUR): 0.02 — · ENGINEERING_ASSUMPTION · MEDIUM
At the ECB/Fed inflation target — no real energy-price growth assumed (conservative)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Share of the wholesale price realised for surplus power: 0.85 — · ENGINEERING_ASSUMPTION · MEDIUM
15 % profile & balancing discount for a small seller (assumption, same for all markets)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Mineral potassium price: 0.7611 EUR/kg K₂O · CALCULATED_VALUE · MEDIUM
World Bank Pink Sheet, 12-month mean 2025M10–2026M09; ÷ nutrient share × 1.35 farm-gate markup
2025M10 / 2026M09 · checked 2026-10-27 · World commodity reference; actual digestate nutrient substitution and local fertiliser price require confirmation
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Trailing-year commodity reference: 378.6 USD/t product (MARKET_DATA); Latest-month reference (2026-09): 367.5 USD/t product (MARKET_DATA); FX (2026-11-09): 1.119 USD/EUR (MARKET_DATA); Farm-gate markup: 1.35 — (ENGINEERING_ASSUMPTION)
Mineral nitrogen price: 1.33 EUR/kg N · CALCULATED_VALUE · MEDIUM
World Bank Pink Sheet, 12-month mean 2025M10–2026M09; ÷ nutrient share × 1.35 farm-gate markup
2025M10 / 2026M09 · checked 2026-10-27 · World commodity reference; actual digestate nutrient substitution and local fertiliser price require confirmation
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Trailing-year commodity reference: 507.3 USD/t product (MARKET_DATA); Latest-month reference (2026-09): 407.5 USD/t product (MARKET_DATA); FX (2026-11-09): 1.119 USD/EUR (MARKET_DATA); Farm-gate markup: 1.35 — (ENGINEERING_ASSUMPTION)
Mineral phosphorus price: 1.678 EUR/kg P₂O₅ · CALCULATED_VALUE · MEDIUM
World Bank Pink Sheet, 12-month mean 2025M10–2026M09; ÷ nutrient share × 1.35 farm-gate markup
2025M10 / 2026M09 · checked 2026-10-27 · World commodity reference; actual digestate nutrient substitution and local fertiliser price require confirmation
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Trailing-year commodity reference: 639.8 USD/t product (MARKET_DATA); Latest-month reference (2026-09): 690 USD/t product (MARKET_DATA); FX (2026-11-09): 1.119 USD/EUR (MARKET_DATA); Farm-gate markup: 1.35 — (ENGINEERING_ASSUMPTION)
Exchange rate: 1 EUR/EUR · MARKET_DATA · HIGH
Euro
CONSTANT: EUR reporting currency; no currency conversion
Value of useful heat (displaced gas / boiler efficiency): 0.0608 EUR/kWh th · CALCULATED_VALUE · MEDIUM
Business gas 54.723 €/MWh LHV ÷ 0.9
2026-S1 · checked 2026-10-31 · GJ10000-99999; reference band, customer gas use unknown
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Evaluation horizon: 15 a · ENGINEERING_ASSUMPTION · MEDIUM
Shorter than the 20-year technical life — conservative
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Official hourly labour cost, economy-wide (wages + employer costs): 26.4 EUR/h · MARKET_DATA · HIGH
Eurostat lc_lci_lev: hourly labour cost (wages + employer costs), industry, construction & services, 2025
WITHIN_REVIEW_WINDOW: Within the 730-day review policy; applicability and latest publication must still be checked
Plant operator wage relative to the economy-wide average: 0.7 — · ENGINEERING_ASSUMPTION · MEDIUM
Plant operator ≈ 70 % of the economy-wide average hourly cost (high-income economy)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Annual escalation of operating costs (nominal EUR): 0.025 — · ENGINEERING_ASSUMPTION · MEDIUM
Inflation target + 0.5 pp wage drift
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Road transport of organic feedstock: 0.115 EUR/(t·km) · CALCULATED_VALUE · MEDIUM
0.06 €/t·km vehicle & fuel + 0.003 × driver labour cost (€/h); matches KTBL slurry haulage ≈ 0.12–0.16 €/t·km in Germany
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Loading/unloading per tonne: 0.97 EUR/t · CALCULATED_VALUE · MEDIUM
0.6 €/t pump & loader + 0.02 h/t × labour cost (KTBL Betriebsplanung machine-cost norms, scaled by national labour cost)
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Avoidable share of an unsplit customer electricity bill: 0.85 — · ENGINEERING_ASSUMPTION · LOW
Engineering judgement, no published value: energy share of an unsplit bill; customer tariff sheet takes precedence
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Customer electricity price (invoice split not verified): 0.133 EUR/kWh · USER_INPUT · MEDIUM
USER_INPUT 0.133 EUR/kWh / FX 1; Euro. Invoice date not supplied; energy/demand split assumed separately.
REVIEW_REQUIRED: Customer input; invoice date, contract and validity not independently verified
food_waste: dry matter: 14 % FM · MEASURED · MEDIUM
MEASURED laboratory report; replaces the catalogue value for this stream. Not independently verified.
REVIEW_REQUIRED: Customer measurement; sample, date and laboratory not independently verified