Sample report · Germany

Potato processing · Potato processing residues: 80,000 t/yr

A sample Extended Report for a modelled project. Your report has the same structure (the Standard Report has fewer sections) and uses your own data.

Business situation

A Lower Saxony potato-starch factory runs a campaign from August to January and produces large amounts of wet potato pulp with only a low feed value. Starch drying needs a lot of steam, so biogas can replace factory gas.

Operating assumptions

  • Potato processing residues: 80,000 t/yr · DM: 13 % · 6 months · Season starts: August · We sell it (e.g. as feed) · What you sell it for today: 5 EUR/t
  • Electricity: 30,000,000 kWh/yr · Electricity price on your bill (if known): 0.21 EUR/kWh
  • All year: hot water, steam, process · We use natural gas: 10,000,000 m³/yr
  • Land available for spreading digestate: 3,000 ha · Distance to the gas grid (for biomethane): 1 km
  • Existing lagoon / store that could be covered: 40,000 m³
  • Grid connection? Yes

What to verify

Confirm the pulp's feed market and price, ensiling options, steam demand by month and whether potato fruit water can be co-treated.

Possible with conditions

It can pay off, but only if the key conditions hold — confirm them in a feasibility study.

  • Base NPV positive (€8.9M), payback ≈ 5.4 yrs.
  • Conservative-case NPV is negative (-€5.9M) — sensitive to key assumptions.

Largest benefit — “electricity savings (self-consumption)”: ≈ 75 % of all revenue and savings.

What would change the verdict
  • → Secure long-term heat and power offtake; benchmark CAPEX with 3–5 suppliers.

Subsidies and tariffs excluded from the verdict. Preliminary screening, not an engineering design.

How firm is this answer?

Grey zone: the answer flips between the conservative and the optimistic case. Before paying for a feasibility study, check these first:

NPV: conservative -€5.9M · base €8.9M · optimistic €17M

The conservative case stacks every adverse assumption at once: a stress test, not the likely outcome. In 160 likely combinations the NPV was positive in 99 % of cases.

  1. Get an offer for exported power (PPA or tariff) · Energy prices −20 % (-€6M)
  2. CH₄ −20 % · Already entered (-€5.9M)
  3. Feedstock potential −20 % (-€4.7M)

These are screening assumptions, not independently validated accuracy limits. Confirm BMP, supplier scope, grid connection and offtake terms before an investment decision.

To reach a bankable estimate (±15 %)
  1. Laboratory methane-potential (BMP) test of 2–3 feedstock samples — ≈ €300–800 each · Already entered
  2. 2–3 supplier quotes for the plant
  3. Grid or gas-network connection conditions from the operator
  4. Letters of intent for feedstock supply and for heat, power or biomethane offtake
  5. Then a feasibility study with permits and financing (±15 %)
From screening to construction

Key figures

Ranges: conservative — base — optimistic. We don't show fake precision.

Economics

Preliminary investment
€8.6M – €11M
Payback
3.6 yr – 19.7 yr
base: 5.4 yr · no subsidies
NPV (base)
€8.9M
range: -€5.9M … €17M
Chosen route
CHP (power + heat)
Confidence: Medium

Feedstock and energy

Feedstock potential
80,000 t/yr
energy ≈ 408 kWh CH₄/t
Biogas
4.9M – 6.7M Nm³/yr
≈ 773 Nm³/h (base)
Net energy
9,800 – 13,000 MWh/yr
useful heat: 4,600 – 10,000 MWh · ≈ 42 % of your electricity use
Candidate capacity
3,500 kWe
large (1–5 MW)

How far you can rely on these numbers

Medium · 90/100
  • Backed by your data and our sources90
  • Needs a feasibility study (lab, quotes, contracts)10

90/100: how much of what a screening can know about this project rests on your data and current sources. A missing input costs points in proportion to how far it could still move your result.

What you can add

You have entered everything this screening can use.

High requires verified laboratory and project documents, so a screening stops at 90/100.

Model warnings
  • "potato processing residues (peel, pulp)" is entered for 6 months only: the digester is sized for that peak and sits idle the rest of the year. If the stream can be stored (e.g. ensiled), feeding it year-round needs a plant about 2× smaller.
  • In this configuration the digestate is a cost rather than an asset.
  • CHP performance uses a 50 Hz biogas full-load catalogue reference (03/2025), interpolated between ratings; part-load and ambient derating require supplier confirmation.
  • CHP rating is outside the 20–2,300 kW reference curve; endpoint efficiency is only a proxy. Obtain a multi-engine or equipment-specific design.
Country conditions
  • Mature market (≈ 9 300 CHP plants): German economics are tariff-driven — compare the support case with the no-support verdict.

Action plan: what would make it stronger

Changes tested on this project with the same model. Break-even values show how far each must go; the scenario assumptions are LOW-confidence judgements to replace with offers.

What separates this project from “Strong candidate”
  • The conservative case must stay profitable too (its NPV is -€5.9M).
Order of action
  1. 1Ask 3–5 suppliers for quotes: the project breaks even up to an investment of €17M. →

What to verify first

Inputs ranked by what exact knowledge is worth before you decide (expected value of perfect information). Each range is tested on its own; inputs you already supplied are not listed.

CheckNPV across the plausible rangeWorth knowing
Check how your bill splits energy and capacity charges€4.6M … €13M—
Get supplier quotes for the plant€5.5M … €12M—
Verify the market price€6.5M … €10M—
Confirm a reliable heat buyer and demand€7.4M … €10M—
Fix feedstock prices and gate fees in contracts€7.8M … €10M—
Check the fertiliser value of the digestate€8.7M … €9.3M—
How to check: Check how your bill splits energy and capacity charges
  1. Take the last 12 electricity invoices.
  2. Split each into the energy part (per kWh) and capacity, network and fixed charges; own generation saves mainly the energy part.

Then enter it in: Energy step: electricity price per kWh (energy part, excl. VAT)

How to check: Get supplier quotes for the plant
  1. Send the same request to at least three suppliers.
  2. Compare like for like: scope, exclusions, guaranteed gas output, own power use, availability and the O&M price.
Request to send
Request for quotation: turnkey biogas plant
Site: Germany.
Feedstock (screening values, to be confirmed):
- potato processing residues (peel, pulp): 80,000 t/year, DM ≈ 13.0 %
Design basis from the screening: raw biogas ≈ 1,400 Nm³/h at ≈ 53 % CH₄; digester working volume ≈ 15,000 m³; combined heat and power ≈ 3,500 kWe; new digestate storage ≈ 0 m³.
Please quote turnkey: feeding, digester(s), gas system with flare and desulphurisation, the gas-use equipment above, electrical and I&C, civil works, engineering and commissioning. List exclusions (grid connection, permits, land, digestate storage if separate). State the guaranteed gas output, own power and heat use, availability and the price of a full O&M contract.

Then enter it in: Step 3, “Optional: contracts and financing”: supplier quote and its technology

How to check: Verify the market price
  1. Check the official source shown for this price in the market-data table and compare it with your own contract.

Then enter it in: Energy step: your own price, if you have a contract

How to check: Confirm a reliable heat buyer and demand
  1. Confirm the buyer's monthly heat demand and the temperature they need.
  2. Agree a price per kWh linked to their current fuel, and a term of at least the loan period.
Request to send
Offer of renewable heat
Site: Germany. A biogas plant can supply ≈ 10,000 MWh of heat a year (hot water, ≈ 80–90 °C) all year round. Please tell us your monthly heat use, the temperature you need, your current fuel and its price, and the price per kWh and term you would accept.

Then enter it in: Energy step: price the heat buyer pays per kWh

How to check: Fix feedstock prices and gate fees in contracts
  1. For every purchased stream and every gate fee, note today's price and its range over the last three years.
  2. Fix prices or gate fees with indexation for the loan period, and check that the plan still pays with prices 25 % worse.
Request to send
Request for a feedstock supply agreement
Site: Germany. A biogas plant would take:
- potato processing residues (peel, pulp): 80,000 t/year, DM ≈ 13.0 %
Please confirm the tonnes per month you can deliver, the dry matter, the delivery season, the price or gate fee per tonne with its indexation, and the term you can commit to.

Then enter it in: Feedstock step: quantity and price of each delivered stream

How to check: Check the fertiliser value of the digestate
  1. Ask neighbouring farms what they would pay per tonne of digestate, delivered and spread.
  2. Check the land available for spreading against the nitrogen limit.

Then enter it in: Site step: land available for digestate

Break-even prices

Each value on its own brings the base-case NPV to zero; everything else stays as calculated.

Electricity value at NPV = 0
€0.113/kWh
now €0.179/kWh
Highest installed cost at NPV = 0
€17M
now €9.6M
Feedstock price headroom
€9.84/t
can pay up to €9.84 per tonne more for every input

Probability range (Monte Carlo)

160 draws of the scenario quantities (yield, dry matter, CAPEX, prices, heat use, operating hours…). Energy and biomethane prices move together, the rest independently. Not a forecast: it shows how often the project stays positive when the uncertainties do not all go wrong at once.

NPV P10 (1 in 10 worse)
€3.3M
Median NPV
€6.6M
NPV P90 (1 in 10 better)
€8.8M
Chance that NPV > 0
99 %
Median payback
6.1 yr

Reality check: on 39 German farm plants with metered feed and methane (FNR Biogas-Messprogramm III), measured output was 1–1.3 × this model's estimate for 8 in 10 plants. The model sizes the plant itself and stays on the cautious side; with feedstock that is not lab-tested, one plant can still miss by more.

What could break the economics

Each stress test applied to the base case on its own.

Change in NPV vs base, € (base: 8.9M)

  1. Energy prices −20 %-6M
  2. CH₄ −20 %-5.9M
  3. Feedstock potential −20 %-4.7M
  4. CHP downtime +10 pp-3.6M
  5. Useful heat (economic) −50 %-2.9M
  6. CAPEX +20 %-2.3M
  7. Maintenance +30 %-800K
  8. Feedstock transport +50 %0
NPV = 0 if CAPEX falls by
already positive
grant, leasing, cheaper equipment
NPV = 0 if energy prices rise by
already positive
relative to the base case

Scenarios

Route: CHP (power + heat). Scenarios bundle consistent assumptions (lower yield comes with higher CAPEX).

Revenue + savings / yr€3M
  • Electricity self-consumption savings2.3M
  • Useful heat (economic)550K
  • Incremental digestate value190K
OPEX / yr€1.2M
  • Foregone alternative revenue400K
  • Digestate handling270K
  • Staff250K
  • Maintenance120K
Operating margin (EBITDA)€1.8M
ScenariosConservativeBaseOptimistic
Biogas, 1 000 Nm³/yr4,862.16,181.16,675.6
CAPEX€11M€9.6M€8.6M
OPEX / yr€1.3M€1.2M€1.1M
Revenue + savings / yr€1.9M€3M€3.6M
Operating margin (EBITDA)€580K€1.8M€2.4M
Simple payback19.7 yr5.4 yr3.6 yr
Discounted paybackno payback6.9 yr4.5 yr
NPV-€5.9M€8.9M€17M
IRR-2.9 %17 %26.7 %
DSCR (min)0.62.33.5

Pre-tax, nominal EUR, 15-year horizon, discount rate of the country or your own; a screening estimate, not a bankable feasibility study. DSCR = EBITDA ÷ debt service at 65 % debt (no taxes).

Cumulative cash flow, €
-14M-2M10M22M34M03691215yearsConservativeBaseOptimistic

Biogas use routes compared

Base case. The model picks the route with the best NPV among technically sensible ones.

RouteCAPEXEBITDA / yrPaybackNPV (base)NPV low…high
CHP (power + heat) chosen€9.6M€1.8M5.4 yr€8.9M-€5.9M … €17M
Boiler (heat only) €5.9M€440K13.3 yr-€1.8M-€13M … €6.6M
Biomethane €9.7M€510K18.9 yr-€5.1M-€18M … €5.6M
  • CHP pays when you use the power yourself and the heat is really used.
  • Biomethane: raw biogas ≈ 700 Nm³/h. The smallest upgrading units take ≈ 50–100 Nm³/h, and the cost per Nm³ falls steeply with size, so a small plant pays much more for each unit of gas.

Plant size

The same feedstock mix at other sizes, each option re-sized by the model. Extra feedstock is assumed on your terms (price, transport, disposal saving); CAPEX is the model's estimate, not your quote.

Sizet/yrBest optionkWeCAPEXNPV (base)
× 0.5 40,000CHP (power + heat)1,730€5.6M€3.1M
× 0.75 60,000CHP (power + heat)2,600€7.6M€5.8M
× 1 your input80,000CHP (power + heat)3,470€9.6M€8.9M
× 1.5 120,000CHP (power + heat)5,200€15M€7.8M
× 2 160,000CHP (power + heat)6,930€20M€5.9M
× 3 240,000CHP (power + heat)10,400€31M€2.2M

National support schemes — separate cases

Not in the verdict: tariffs get cut, auctions fail, grant calls close. Status and source shown for each.

Bottom line

Support may be possible, but eligibility is not confirmed

On the scheme's terms the NPV is above zero.

Best option: EEG Ausschreibung Biomasse Details ↓

NPV change
-€2.1M
NPV with support
€6.8M
Payback
5.3 yr
IRR
15.2 %

Next step: Ask the scheme operator in writing whether your project meets the conditions the model does not check.

Country overviewchecked 30 Oct 2026

Small manure plants ≤ 150 kW get a fixed EEG rate (≈ 20 ct/kWh, 20 years, ≥ 80 % manure); larger plants bid in tenders (2026 average award 18.5 ct/kWh) with a flexible-operation duty.

Open for applications (1)

You can apply now on the published terms.

EEG 2023 Güllekleinanlage

Open
Electricity tariff
Does not qualify
Manure other than poultry manure is 0 % of the fresh mass; the scheme requires at least 80 %.

Not calculated: the project does not meet the conditions.

Conditions
  • not met: Electrical capacity up to 150 kW (project ≈ 3,470 kW)
  • not met: Manure other than poultry manure: at least 80 % of fresh mass (project 0 %)
  • met: CHP of a practical size, from 25 kW (project ≈ 3,470 kW)
What the case uses
  • Route: CHP (power + heat)
  • Tariff: €0.202/kWh
Scheme terms

Commissioned 1.7.2026–30.6.2027: 21.67 ct (≤ 75 kW) / 18.72 ct (75–150 kW); 20 years; ≥ 80 % manure (no poultry); unpaid in negative-price hours.

Next step: Not available for the project as designed. Rely on it only if a design change removes the obstacle, and re-run the screening with that change.

Source: EEG 2023 §44, §44a (gesetze-im-internet.de): 22/19 ct − 0.5 % each 1 July from 2024 · checked 30 Oct 2026 · Data confidence: Medium

Running, awarded by competition (1)

Support goes to the winners of a round or auction. The case assumes an award at the stated value.

EEG Ausschreibung Biomasse

Competitive
Electricity tariff
Eligibility to confirm
Some conditions of this scheme are not checked by the model (see the note): shown "if eligible". Confirm them with the scheme operator.
NPV change
-€2.1M
NPV with support
€6.8M
Payback
5.3 yr
IRR
15.2 %
Conditions
  • met: Electrical capacity from 150 kW (project ≈ 3,470 kW)
  • met: Maize and cereal grain: at most 25 % of fresh mass (project 0 %)
  • met: CHP of a practical size, from 25 kW (project ≈ 3,470 kW)
Not checked by the model — confirm with the operator:
  • no data: Flexible design: engines and gas storage sized for the paid hours (extra CAPEX not costed)
What the case uses
  • Route: CHP (power + heat)
  • Tariff: €0.18/kWh
Scheme terms

Pay-as-bid; April 2026 average award 18.46 ct, ceiling 19.43 ct (new); paid only for 11 680 quarter-hours a year (≈ 2 920 full-load h; 16 000 ≈ 4 000 h up to 350 kW), the rest at market value; maize + grain ≤ 25 % by mass; the flexible design (extra engine capacity, gas storage) is not costed.

Next step: Ask the scheme operator in writing whether your project meets the conditions the model does not check.

Source: BNetzA press releases 2026-06-09 and 2026-11-03 (bid dates 01.04 / 01.10.2026; October average 18.75 ct, 13.95–19.80, undersubscribed); EEG §39 · checked 30 Oct 2026 · Data confidence: Medium

Support never changes the verdict. Each case is pre-tax, uses the scheme's published terms and assumes the support is awarded; it does not confirm eligibility or promise funding.

Where the energy goes

Heat produced ≠ useful heat. Heat without a user isn't income.

64/100

Of every 100 kWh of energy in the methane, 64 become a product that earns money or replaces a purchase.

100 % = 33,000 MWh of methane energy a year (LHV), base case. Every figure in this block is calculated by the model from your inputs.

Stream by stream

Calculated

Earns money

  • Electricity used on site13,000 MWh 39 %
  • Heat for a user8,200 MWh 25 %

Runs the plant

  • Plant’s own electricity1,000 MWh 3 %
  • Digester heating2,300 MWh 7 %

Produced, not used

  • Heat with no buyer2,000 MWh 6 %

Losses

  • Conversion losses (engine, boiler)5,200 MWh 16 %
  • Gas sent to the flare710 MWh 2 %
  • Methane leaks490 MWh 2 %

What this means for the project

  • 2,000 MWh of heat a year has no buyer. A heat user nearby (drying, a greenhouse, process heat, a heating network) would turn it into income. At the heat value used in this case that is about €140K a year.
  • Methane leaks are 2 % of production in the base case: lost income and a greenhouse gas. Gas-tight digestate storage and regular leak checks keep them low.

What the figures rest on

Engine efficiency: electricity / heat
43 % / 43 %Assumption
Heat need
10,000,000 m³Your data
Site electricity use
30,000 MWhYour data
Methane leaks, base case
2 %Assumption
Main product, conservative – optimistic
9,800 – 13,000 MWhCalculated

Season: how much the digester takes for itself

In January heating the digester needs heat equal to 8 % of that month’s methane energy, in August 6 %.

January: methane energy 5,400 MWh · digester heating 450 MWh (8 %) · heat for a user 1,300 MWh

  • Methane energy of the month
  • Digester heating
  • Heat for a user

How it works: from feedstock to products

  1. Feedstock80,000 t/yr
  2. Biogas6.2M Nm³/yr
  3. Electricity13,000 MWh
  4. Useful heat8,200 MWh
  5. Heat without demand2,000 MWh
  6. Digestate72,000 t/yr
Heat produced (gross)
12,561 MWh
Digester heat demand
2,337 MWh
Useful heat (economic)
8,180 MWh of 10,224
Power: own use / sold
12,624 / 0 MWh

Climate case (EU RED method)

EU Renewable Energy Directive default values for your feedstock mix, digestate storage and route. Separate from the verdict; outside the EU an indicative benchmark. Credits are valued only in the support cases where an official mechanism exists.

Emissions of the product
25 g CO₂e/MJ
gas-tight digestate storage
Fossil comparator
183 g CO₂e/MJ
Greenhouse-gas saving
86 %
RED minimum: 80 %
Avoided emissions
9,292 t CO₂e
  • Meets the RED minimum.
  • RED sustainability criteria apply (rated input ≥ 2 MW).
  • Residues other than manure, maize and food waste use the RED biowaste values.

Scores by dimension

No single magic number. The overall score comes with its explanation.

Feedstock fit
83/100
  • Energy equivalent ≈ 3470 kWe (scale score 100/100)
  • Feedstock energy ≈ 408 kWh of methane per tonne (score 65/100)
  • Feedstock available 6 of 12 months
Energy fit
91/100
  • Own consumption absorbs 100 % of the electricity produced
  • Useful heat 8180 MWh of 10224 MWh available after digester needs
Location & logistics
100/100
  • No critical site constraints found from your answers
Technical feasibility
85/100
  • Seasonal feedstock: equipment under-used
Economics
85/100
  • Base-case simple payback ≈ 5.4 years
Regulatory complexity
27/100 risk
  • Number and weight of permitting / regulatory steps: 11 points (more = harder)
Environmental risk
24/100 risk
  • Expected methane loss 2.5 % (good practice ≤ 2 %)
Overall project viability
85/100
  • Weighted: economics 30 %, feedstock 20 %, energy 15 %, technical 10 %, location 10 %, regulatory 7.5 %, environment 7.5 %.
  • Strongest: Location & logistics (100); weakest: Regulatory complexity (73).

Calculation details

Feedstock & logistics
Streamt/yrDM, %Nm³ CH₄/tLogistics / energyMax. distance
Potato processing residues80,0001341on site≈ 107 km

Max. distance = where haulage eats half of a tonne's energy value. Low-energy feedstock (slurry) belongs next to the plant.

Technology & digester

Wet mesophilic digestion with solids feeding

CSTR with a solids feeder and recirculation, or horizontal plug-flow for dairy manure

Working volume
≈ 15,000 m³
Retention time
33.4 days
Loading rate
3.5 kg VS/(m³·d)
Digestate storage
≈ 36,000 m³
  • Dry matter 13 % is above the pumpable limit without a solids feeder (12 %).
  • Feedstock is seasonal: a continuous plant would sit idle; a campaign-based or buffered design is more flexible.
  • Mesophilic (≈38 °C): more robust, less heat and complexity. Thermophilic (≈52 °C) only when the benefit outweighs the complexity — rarely at this scale.
  • Two-stage layout (main + post-digester) for stability with fats or larger flows.
Alternatives
  • Horizontal plug-flow (good for 10–14 % DM cattle manure)

Climate: Lower Saxony (Vechta), mean 10.9 °C, ≈ 2,637 heating degree-days. Closest climate analogues: Dresden (DE, east) (Δ 1.5 °C), Copenhagen (DK) (Δ 1.5 °C), Prague (CZ) (Δ 2 °C).

Monthly energy balance

Base case, chosen route. Gas energy is usable methane energy (LHV) after losses.

MonthFeedstock, tGas energy, MWhDigester heat, MWhUseful heat, MWhNet electricity, MWh
Jan13,4785,4204461,3362,127
Feb00000
Mar00000
Apr00000
May00000
Jun00000
Jul00000
Aug13,4785,4203211,4362,127
Sept13,0435,2453381,3682,058
Oct13,4785,4203821,3882,127
Nov13,0435,2454101,3102,058
Dec13,4785,4204401,3412,127
Σ80,00032,1722,3378,18012,624
CAPEX, OPEX, revenue (base case)
CAPEX (EUR)
Digester1.9M
Covering existing storage690K
Feedstock reception and preparation160K
Gas handling and cleaning200K
CHP (power + heat)3.4M
Heat network370K
Backup boiler35K
Electrical systems and controls400K
Pipework270K
Civil works400K
Grid connection230K
Engineering and permits640K
Contingency870K
Total9.6M
OPEX / yr (EUR)
Staff250K
CHP service and overhaul reserve110K
Maintenance120K
Insurance48K
Testing and monitoring5K
Foregone alternative revenue400K
Digestate handling270K
Total1.2M
Revenue + savings / yr (EUR)
Electricity self-consumption savings2.3M
Useful heat (economic)550K
Incremental digestate value190K
Total3M

Unit costs are estimates. Replace them with supplier quotations.

Digestate: asset or liability

Status: liability / cost · 71,908 t/yr · nitrogen ≈ 155,257 kg/yr · land needed ≈ 913 ha (available 3,000 ha).

Incremental fertiliser value €190K/yr, handling €270K/yr, net -€81K/yr.

  • Digestate storage for 6 months for the closed spreading season; keep ≈ 150 days (incl. the digester) gas-tight, otherwise methane and N are lost.
  • Spread by injection or trailing hose (not splash plate): less odour and ammonia loss.
Methane losses & climate

Expected losses: 2.5 % of methane produced (range 1.6 % – 4 %) ≈ 1,590 t CO₂e/yr; fossil emissions displaced ≈ 5,818 t CO₂/yr. Losses vs benefit: 27 %.

  • Expected loss 2.5 % is above good practice (2 %): budget for monitoring.
  • Gas-tight covers on the digester and digestate storage (incl. lagoon covers) — the single most important measure.
  • Leak detection and repair (LDAR): optical gas imaging or tracer method at least yearly, plus an acceptance test after construction.
  • Continuous gas-holder pressure monitoring; a standby flare instead of venting.
  • CHP with an oxidation catalyst and tuning regime to cut methane slip.

Avoided emissions from open manure storage are not credited (conservative).

Permits & regulation (indicative)

Complexity: lower. “To verify” means a local lawyer or engineer must confirm the item during the feasibility study.

  • Building permit and environmental permit; EIA screening (Directive 2011/92/EU as transposed)
    New installation · effort: medium · to verify
  • Industrial Emissions Directive (2010/75/EU) permit — anaerobic digestion of waste above ~100 t/day
    Throughput above the IED threshold · effort: high · to verify
  • Nitrates Directive (91/676/EEC): 170 kg N/ha from organic manures in vulnerable zones; closed spreading periods
    Digestate is spread on land · effort: medium · confirmed
  • ATEX hazardous-area zoning (Directives 2014/34/EU, 1999/92/EC)
    Methane in the gas phase · effort: medium · confirmed
  • Medium Combustion Plant Directive (2015/2193): registration and emission limits for CHP ≥ 1 MW thermal input
    CHP above 1 MWth input · effort: medium · to verify
Safety (risk register)
  • Methane: explosion and fire (flammable range ≈ 5–15 % in air) high
    • Hazardous-area (ATEX/IECEx or national) zoning and suitably rated equipment
    • Fixed gas detectors in the CHP room and near tanks
    • Flame arresters, over/under-pressure relief, safety flare
    • Ignition-source control and hot-work permits
  • Hydrogen sulphide (H₂S): acute toxicity, corrosion high
    • Biological / chemical desulphurisation of the biogas
    • Personal H₂S monitors, no lone working
    • H₂S monitoring upstream of the CHP (engine protection)
  • Confined spaces (digester, storage, pits): asphyxiation, toxic gases high
    • Entry only under permit, ventilation, standby person
    • Self-contained breathing apparatus for rescue
  • Over/under-pressure: membrane roof rupture, tank deformation medium
    • Liquid seals / relief valves venting to a safe location
    • Gas-holder level and pressure sensors
  • CHP: carbon monoxide, fire, high temperatures medium
    • CHP room ventilation, CO detectors
    • Emergency stop, fire suppression
  • Soil and water pollution: slurry/digestate spills, lagoon overflow high
    • Bund sized for the largest tank
    • Level sensors and a spill-response plan
    • Digestate storage covering the closed spreading season

Software does NOT replace a qualified process engineer and a process-safety engineer. Every final engineering design, hazardous-area classification and safe-operation programme must pass human professional review.

Assumptions used (163)

Every number has a source, date, country and confidence, and is tagged FACT / ASSUMPTION / CALCULATION / ESTIMATE. Full register: →

  • Support: Small manure plants ≤ 150 kW get a fixed EEG rate (≈ 20 ct/kWh, 20 years, ≥ 80 % manure); larger plants bid in tenders (2026 average award 18.5 ct/kWh) with a flexible-operation duty.
  • Mature market (≈ 9 300 CHP plants): German economics are tariff-driven — compare the support case with the no-support verdict.
  • The verdict excludes subsidies; national support is shown as separate cases.
  • This is a preliminary (screening) assessment — not a detailed engineering design and not a commercial offer.
  • Financial results are pre-tax project cash flows. Depreciation, income taxes, working capital, financing fees and detailed debt covenants are not modelled; DSCR is an EBITDA-based screening ratio, not lender CFADS.
  • Parameter bounds are tested individually using the applicable market/CAPEX evidence. These engineering or tariff ranges are not statistical confidence intervals and do not replace supplier quotations or customer bills.

What could break the economics

Each stress test applied to the base case on its own.

chp: local CAPEX factor
0.7 … 1.3 —
NPV low…high: €5.5M … €12M
Discount rate (nominal, pre-tax, EUR-equivalent, incl. country risk)
0.05 … 0.08 —
NPV low…high: €6.5M … €10M
Mineral potassium price
0.713 … 0.8099 EUR/kg K₂O
NPV low…high: €8.9M … €9M
Mineral nitrogen price
1.045 … 1.818 EUR/kg N
NPV low…high: €8.7M … €9.3M
Mineral phosphorus price
1.419 … 1.847 EUR/kg P₂O₅
NPV low…high: €8.9M … €8.9M
Avoidable share of an unsplit customer electricity bill
0.7 … 1 —
NPV low…high: €4.6M … €13M
Every number has a source, date, country and confidence, and is tagged FACT / ASSUMPTION / CALCULATION / ESTIMATE. Full register:
Biomethane price without support, base: 0.6925 EUR/Nm³ · CALCULATED_VALUE · LOW
CALCULATION: TTF 46.49 €/MWh HHV × 1.11 HHV/LHV + 20 €/MWh LHV green-gas premium (engineering assumption, no official GO price); World Bank Pink Sheet (2026-10-02), Natural gas Europe (TTF), mean Q4 2025 – Q3 2026 15.25 $/mmbtu GCV ÷ 0.2931 MWh/mmbtu at 1.1193 USD/EUR; × 9.6709 kWh LHV/Nm³. No guaranteed offtake or certificate eligibility.
2025-10 / 2026-09 · checked 2026-11-11 · Grid-injected biomethane, HHV prices converted to LHV; without feed-in tariffs, quotas or tax relief
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
chp: local CAPEX factor: 1 — · CALCULATED_VALUE · MEDIUM
0.72 traded equipment + 0.28 × local/German labour cost (31.5/31.5 €/h); split after DBFZ/Fraunhofer 2024; supplier quotes needed
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Debt interest rate (EUR-equivalent): 0.045 — · CALCULATED_VALUE · MEDIUM
Discount rate − 1.5 pp (senior debt is cheaper than blended project capital); consistent with ECB MIR corporate loan rates + project margin; a bank term sheet replaces this
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Debt share for DSCR test: 0.65 — · ENGINEERING_ASSUMPTION · MEDIUM
Typical agri / project lending (KfW, EBRD, IFC practice)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Debt tenor: 10 a · ENGINEERING_ASSUMPTION · MEDIUM
Typical
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Digestate that has no adequate land: 9.43 EUR/t · CALCULATED_VALUE · MEDIUM
Third-party export of digestate ≈ 2.5 €/t + 0.22 h/t × labour; ≈ 12 €/t in Germany, in line with manure-exchange prices in surplus regions (LWK Niedersachsen Nährstoffbericht: 10–20 €/t)
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Incremental digestate handling on adequate land: 3.72 EUR/t · CALCULATED_VALUE · MEDIUM
Pumping & trailing-hose spreading ≈ 1.2 €/t machinery + 0.08 h/t × labour; ≈ 4.8 €/t in Germany, in line with KTBL contractor rates (3–6 €/m³)
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Discount rate (nominal, pre-tax, EUR-equivalent, incl. country risk): 0.06 — · CALCULATED_VALUE · MEDIUM
Nominal, pre-tax, EUR-equivalent: 6.0 % mature-market WACC + 0.6 × country risk premium 0.00 % (Aaa; Damodaran, 2026-07); not a bank offer
2026-07-01 · checked 2026-10-27 · Rating-based CRP; baseline WACC and lambda are engineering/financial assumptions
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Wholesale electricity price (market average): 0.1043 EUR/kWh · MARKET_DATA · HIGH
ENTSO-E day-ahead (via Energy-Charts), zone DE-LU, average 104.3 €/MWh, 2025-10-01 – 2026-10-01
2025-10-01 / 2026-10-01 · checked 2026-10-30 · Wholesale bidding zone DE-LU; not a guaranteed export PPA
WITHIN_REVIEW_WINDOW: Within the 60-day review policy; applicability and latest publication must still be checked
Annual escalation of energy prices (nominal EUR): 0.02 — · ENGINEERING_ASSUMPTION · MEDIUM
At the ECB/Fed inflation target — no real energy-price growth assumed (conservative)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Share of the wholesale price realised for surplus power: 0.85 — · ENGINEERING_ASSUMPTION · MEDIUM
15 % profile & balancing discount for a small seller (assumption, same for all markets)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Mineral potassium price: 0.7611 EUR/kg K₂O · CALCULATED_VALUE · MEDIUM
World Bank Pink Sheet, 12-month mean 2025M10–2026M09; ÷ nutrient share × 1.35 farm-gate markup
2025M10 / 2026M09 · checked 2026-10-27 · World commodity reference; actual digestate nutrient substitution and local fertiliser price require confirmation
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Trailing-year commodity reference: 378.6 USD/t product (MARKET_DATA); Latest-month reference (2026-09): 367.5 USD/t product (MARKET_DATA); FX (2026-11-09): 1.119 USD/EUR (MARKET_DATA); Farm-gate markup: 1.35 — (ENGINEERING_ASSUMPTION)
Mineral nitrogen price: 1.33 EUR/kg N · CALCULATED_VALUE · MEDIUM
World Bank Pink Sheet, 12-month mean 2025M10–2026M09; ÷ nutrient share × 1.35 farm-gate markup
2025M10 / 2026M09 · checked 2026-10-27 · World commodity reference; actual digestate nutrient substitution and local fertiliser price require confirmation
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Trailing-year commodity reference: 507.3 USD/t product (MARKET_DATA); Latest-month reference (2026-09): 407.5 USD/t product (MARKET_DATA); FX (2026-11-09): 1.119 USD/EUR (MARKET_DATA); Farm-gate markup: 1.35 — (ENGINEERING_ASSUMPTION)
Mineral phosphorus price: 1.678 EUR/kg P₂O₅ · CALCULATED_VALUE · MEDIUM
World Bank Pink Sheet, 12-month mean 2025M10–2026M09; ÷ nutrient share × 1.35 farm-gate markup
2025M10 / 2026M09 · checked 2026-10-27 · World commodity reference; actual digestate nutrient substitution and local fertiliser price require confirmation
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Trailing-year commodity reference: 639.8 USD/t product (MARKET_DATA); Latest-month reference (2026-09): 690 USD/t product (MARKET_DATA); FX (2026-11-09): 1.119 USD/EUR (MARKET_DATA); Farm-gate markup: 1.35 — (ENGINEERING_ASSUMPTION)
Exchange rate: 1 EUR/EUR · MARKET_DATA · HIGH
Euro
CONSTANT: EUR reporting currency; no currency conversion
Value of useful heat (displaced gas / boiler efficiency): 0.06709 EUR/kWh th · CALCULATED_VALUE · MEDIUM
Business gas 60.384 €/MWh LHV ÷ 0.9
2026-S1 · checked 2026-10-31 · GJ100000-999999; annual gas input converted to GJ HHV with assumed calorific value
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Evaluation horizon: 15 a · ENGINEERING_ASSUMPTION · MEDIUM
Shorter than the 20-year technical life — conservative
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Official hourly labour cost, economy-wide (wages + employer costs): 45 EUR/h · MARKET_DATA · HIGH
Eurostat lc_lci_lev: hourly labour cost (wages + employer costs), industry, construction & services, 2025
WITHIN_REVIEW_WINDOW: Within the 730-day review policy; applicability and latest publication must still be checked
Plant operator wage relative to the economy-wide average: 0.7 — · ENGINEERING_ASSUMPTION · MEDIUM
Plant operator ≈ 70 % of the economy-wide average hourly cost (high-income economy)
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Annual escalation of operating costs (nominal EUR): 0.025 — · ENGINEERING_ASSUMPTION · MEDIUM
Inflation target + 0.5 pp wage drift
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Road transport of organic feedstock: 0.154 EUR/(t·km) · CALCULATED_VALUE · MEDIUM
0.06 €/t·km vehicle & fuel + 0.003 × driver labour cost (€/h); matches KTBL slurry haulage ≈ 0.12–0.16 €/t·km in Germany
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Loading/unloading per tonne: 1.23 EUR/t · CALCULATED_VALUE · MEDIUM
0.6 €/t pump & loader + 0.02 h/t × labour cost (KTBL Betriebsplanung machine-cost norms, scaled by national labour cost)
WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
Avoidable share of an unsplit customer electricity bill: 0.85 — · ENGINEERING_ASSUMPTION · LOW
Engineering judgement, no published value: energy share of an unsplit bill; customer tariff sheet takes precedence
ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
Customer electricity price (invoice split not verified): 0.21 EUR/kWh · USER_INPUT · MEDIUM
USER_INPUT 0.21 EUR/kWh / FX 1; Euro. Invoice date not supplied; energy/demand split assumed separately.
REVIEW_REQUIRED: Customer input; invoice date, contract and validity not independently verified
potato_processing: dry matter: 13 % FM · MEASURED · MEDIUM
MEASURED laboratory report; replaces the catalogue value for this stream. Not independently verified.
REVIEW_REQUIRED: Customer measurement; sample, date and laboratory not independently verified
potato_processing: volatile solids: 90 % DM · MEASURED · MEDIUM
MEASURED laboratory report; replaces the catalogue value for this stream. Not independently verified.
REVIEW_REQUIRED: Customer measurement; sample, date and laboratory not independently verified
potato_processing: BMP (scenarios ± inter-laboratory spread): 350 L CH₄/kg VS · MEASURED · MEDIUM
MEASURED laboratory BMP test; replaces the catalogue value for this stream. Not independently verified.
REVIEW_REQUIRED: Customer measurement; sample, date and laboratory not independently verified