Business situation

Modelled Canadian brewery: COD treatment and energy recovery. Veolia's Sleeman reference supports the technical flow and loading; budgets are illustrative; the avoided overstrength sewer surcharge (CAD 2.0/m³) is derived from Hamilton's 2026 BOD rate of CAD 0.89/kg.

Operating assumptions

  • Operating days: 330 d/a
  • Active months: 12 1–12
  • Starting month: 1 1–12
  • CAPEX: 3,800,000 CAD
  • OPEX: 150,000 CAD/a
  • Residuals disposal cost: 45 CAD/t
  • Upstream electricity use: 180,000 kWh/a
  • Additional process heat: 0 kWh_th/a
  • Scenario uncertainty: 30 %
  • Q: 1,800 m³/d
  • COD: 4,600 mg COD/L
  • COD removal: 82 % COD
  • CH₄: 65 % vol
  • Methane capture: 95 % CH₄
  • Removed COD to biomass: 8 % COD
  • Sludge dry solids: 5 % TS
  • VS / TS: 80 % VS/TS
  • HRT: 0.25 d
  • OLR: 19.8 kg/(m³·d)
  • Inlet temperature: 25 °C
  • Heat recovery: 60 %
  • Avoided treatment charge: 2 CAD/m³
  • Electricity: 5,000,000 kWh/yr · Electricity price on your bill (if known): —
  • All year: hot water, steam, process · Heat needed per year (if known): 8,000,000 kWh/yr
  • Land available for spreading digestate: — · Distance to the gas grid (for biomethane): 1 km
  • Grid connection? Yes

What to verify

Verify soluble and total COD, sludge yield, final effluent requirements, avoided sewer charges and current installed quotations.

Strong candidate

Worth detailed work: the project holds up even under conservative assumptions.

  • Simple payback ≈ 5.1 yrs (base) and ≈ 8.0 yrs in the conservative case; base NPV US$4.3M; minimum DSCR 2.44.

Largest benefit — “avoided treatment charges (contract basis)”: ≈ 77 % of all revenue and savings.

What would change the verdict
  • → Verify the inlet analysis and operating history, seasonal availability, and a supplier guarantee for the proposed treatment train.
  • → Confirm complete installed-cost quotations, residuals disposal, final effluent treatment and the energy offtake contract. Check the downside case before investment.
  • → Obtain site-specific permits and grid gas-quality requirements; extend this pre-tax screening to tax, working capital and lender cash-flow modelling.

Subsidies and tariffs excluded from the verdict. Preliminary screening, not an engineering design.

How firm is this answer?

Robust: profitable even in the conservative case (lower gas yield, higher CAPEX, lower prices). The next step is worth paying for.

NPV: conservative US$1.5M · base US$4.3M · optimistic US$5.2M

Biggest drivers of the result (stress tests):
  1. Feedstock potential −20 % (-US$2.4M)
  2. OPEX +30 % (-US$1.1M)
  3. CAPEX +20 % (-US$830K)

These are screening assumptions, not independently validated accuracy limits. Confirm BMP, supplier scope, grid connection and offtake terms before an investment decision.

To reach a bankable estimate (±15 %)
  1. Laboratory methane-potential (BMP) test of 2–3 feedstock samples — ≈ US$336–US$895 each
  2. 2–3 supplier quotes for the plant
  3. Grid or gas-network connection conditions from the operator
  4. Letters of intent for feedstock supply and for heat, power or biomethane offtake
  5. Then a feasibility study with permits and financing (±15 %)
From screening to construction

Key figures

Ranges: conservative — base — optimistic. We don't show fake precision.

Economics

Preliminary investment
US$3.7M – US$4M
≈ CA$5.4M (base)
Payback
4.5 yr – 8 yr
base: 5.1 yr · no subsidies
NPV (base)
US$4.3M
range: US$1.5M … US$5.2M
Chosen route
CHP (power + heat)
Confidence: Medium

1 EUR = 1.1193 USD · ECB · 2026-11-09

Feedstock and energy

Industrial wastewater
1,800 m³/d
COD: 4,600 mg COD/L
Biogas
660K – 1.3M Nm³/yr
≈ 131 Nm³/h (base)
Net energy
650 – 2,800 MWh/yr
useful heat: 0 – 650 MWh · ≈ 48 % of your electricity use
Candidate capacity
360 kWe
medium (0.25–1 MW)

How far you can rely on these numbers

Medium · 75/100
  • Backed by your data and our sources75
  • You can still add+6
  • Limits of our data−9
  • Needs a feasibility study (lab, quotes, contracts)10

75/100: how much of what a screening can know about this project rests on your data and current sources. A missing input costs points in proportion to how far it could still move your result.

What you can add

  • Biggest gainElectricity price on your bill (if known) (CAD/kWh)Large effectTotal of one bill divided by the kWh on it+6

With all of it: up to 81/100

Limits on our side

  • Process inputs and project budgets require document verification; ranges are assumptions, not validated accuracy.−9

These come from our country price and cost data or the screening scope, not from your project. We update them.

High requires verified laboratory and project documents, so a screening stops at 90/100.

Model warnings
  • Upstream budgets must include pretreatment, logistics, storage and final treatment; they are not independently verified installed quotations.
  • BMP/COD and retention time alone do not verify salinity, ammonia inhibition, toxic contaminants or treatment stability; confirm with representative analysis and continuous pilot/vendor data.
  • CHP performance uses a 60 Hz biogas full-load catalogue reference (04/2025), interpolated between ratings; part-load and ambient derating require supplier confirmation.
  • Market data require review (econ.electricity_retail_eur_kwh). Observation dates and validity are shown in the evidence; these are not verified current customer quotations.
Country conditions
  • Cold winters and low power prices: RNG contracts are usually the business case.

Action plan: what would make it stronger

Changes tested on this project with the same model. Break-even values show how far each must go; the scenario assumptions are LOW-confidence judgements to replace with offers.

Order of action
  1. 1Ask 3–5 suppliers for quotes: the project breaks even up to an investment of US$7.8M. →

Break-even prices

Each value on its own brings the base-case NPV to zero; everything else stays as calculated.

Electricity value at NPV = 0
positive even if the product earns nothing
now US$0.1/kWh
Highest installed cost at NPV = 0
US$7.8M
now US$3.8M

What could break the economics

Each stress test applied to the base case on its own.

Change in NPV vs base, USD (base: 4.3M)

  1. Feedstock potential −20 %-2.4M
  2. OPEX +30 %-1.1M
  3. CAPEX +20 %-830K
  4. Energy prices −20 %-530K
  5. CH₄ −20 %-520K
  6. Maintenance +30 %-200K
  7. CHP downtime +10 pp-97K
  8. Useful heat (economic) −50 %-23K
NPV = 0 if CAPEX falls by
already positive
grant, leasing, cheaper equipment
NPV = 0 if energy prices rise by
already positive
relative to the base case

Scenarios

Route: CHP (power + heat). Scenarios bundle consistent assumptions (lower yield comes with higher CAPEX).

Revenue + savings / yrUS$1.1M
  • Avoided treatment charge840K
  • Electricity self-consumption savings240K
  • Useful heat (economic)4.2K
OPEX / yrUS$340K
  • OPEX110K
  • Residuals disposal cost100K
  • CHP service and overhaul reserve50K
  • Staff48K
Operating margin (EBITDA)US$750K
ScenariosConservativeBaseOptimistic
Biogas, 1 000 Nm³/yr661.81,050.51,268.2
CAPEXUS$4MUS$3.8MUS$3.7M
OPEX / yrUS$310KUS$340KUS$340K
Revenue + savings / yrUS$810KUS$1.1MUS$1.2M
Operating margin (EBITDA)US$510KUS$750KUS$830K
Simple payback8 yr5.1 yr4.5 yr
Discounted payback10.3 yr6.3 yr5.5 yr
NPVUS$1.5MUS$4.3MUS$5.2M
IRR10.7 %18.9 %21.7 %
DSCR (min)1.62.42.8

Pre-tax, nominal USD, 15-year horizon, discount rate of the country or your own; a screening estimate, not a bankable feasibility study. DSCR = EBITDA ÷ debt service at 65 % debt (no taxes).

Cumulative cash flow, USD
-4.9M-820K3.3M7.4M11M03691215yearsConservativeBaseOptimistic

Biogas use routes compared

Base case. The model picks the route with the best NPV among technically sensible ones.

RouteCAPEXEBITDA / yrPaybackNPV (base)NPV low…high
CHP (power + heat) chosenUS$3.8MUS$750K5.1 yrUS$4.3MUS$1.5M … US$5.2M
Boiler (heat only) US$3MUS$600K5.1 yrUS$3.5MUS$2.1M … US$4.1M
Biomethane US$4.3MUS$570K7.6 yrUS$1.9M-US$290K … US$3M
  • CHP pays when you use the power yourself and the heat is really used.
  • Biomethane: raw biogas ≈ 70 Nm³/h. The smallest upgrading units take ≈ 50–100 Nm³/h, and the cost per Nm³ falls steeply with size, so a small plant pays much more for each unit of gas.

National support schemes — separate cases

Not in the verdict: tariffs get cut, auctions fail, grant calls close. Status and source shown for each.

Bottom line

Support may be possible, but eligibility is not confirmed

On the scheme's terms the NPV is above zero.

Best option: Utility RNG offtake (FortisBC, Énergir, Enbridge) Details ↓

NPV change
-US$780K
NPV with support
US$3.5M
Payback
6 yr
IRR
15.7 %

Next step: Ask the scheme operator in writing whether your project meets the conditions the model does not check.

Country overviewchecked 30 Oct 2026

The RNG business case is utility offtake negotiated under regulated price caps (Québec ≤ 35 $2022/GJ per contract, BC ≤ $31/GJ from 2021/22, CPI-indexed); Clean Fuel Regulations credits and the Clean Technology ITC are uncertain extras. No electricity feed-in tariff.

Running, awarded by competition (1)

Support goes to the winners of a round or auction. The case assumes an award at the stated value.

Utility RNG offtake (FortisBC, Énergir, Enbridge)

Competitive
Biomethane support
Eligibility to confirm
Eligibility of wastewater (sewage) gas is not modelled: shown "if eligible". Confirm the gas-source category, tariff and any existing support with the scheme operator.
NPV change
-US$780K
NPV with support
US$3.5M
Payback
6 yr
IRR
15.7 %
Conditions
  • met: Raw biogas for upgrading from 60 Nm³/h (project ≈ 70 Nm³/h)
  • no data: Gas-source category accepted by the scheme
What the case uses
  • Route: Biomethane
  • Biomethane price: US$0.694/Nm³
Scheme terms

Bilateral contracts under regulated caps: Québec average ≤ 25 $2022/GJ, per contract ≤ 35 $2022/GJ (Régie D-2026-037 kept it); BC ≤ $31/GJ (2021/22), CPI-indexed; CAD 25/GJ used.

Next step: Ask the scheme operator in writing whether your project meets the conditions the model does not check.

Source: B.C. Reg. 102/2012 s.2.2, s.9 (last amended B.C. Reg. 145/2026); Régie de l'énergie D-2026-037 (R-4320-2025, 31.03.2026) · checked 30 Oct 2026 · Data confidence: Low

Support never changes the verdict. Each case is pre-tax, uses the scheme's published terms and assumes the support is awarded; it does not confirm eligibility or promise funding.

Where the energy goes

Heat produced ≠ useful heat. Heat without a user isn't income.

38/100

Of every 100 kWh of energy in the methane, 38 become a product that earns money or replaces a purchase.

100 % = 6,800 MWh of methane energy a year (LHV), base case. Every figure in this block is calculated by the model from your inputs.

Stream by stream

Calculated

Earns money

  • Electricity used on site2,400 MWh 35 %
  • Heat for a user200 MWh 3 %

Runs the plant

  • Plant’s own electricity180 MWh 3 %
  • Digester heating2,800 MWh 41 %

Produced, not used

  • Heat with no buyer50 MWh 0.7 %

Losses

  • Conversion losses (engine, boiler)1,100 MWh 16 %
  • Methane leaks100 MWh 2 %

What this means for the project

  • The plant uses 44 % of its energy itself, mostly to heat the digester in winter. Insulation, heat recovery from the digestate and a drier feedstock mix reduce it.
  • Methane leaks are 2 % of production in the base case: lost income and a greenhouse gas. Gas-tight digestate storage and regular leak checks keep them low.

What the figures rest on

Engine efficiency: electricity / heat
39 % / 49 %Assumption
Heat need
8,000 MWhYour data
Site electricity use
5,000 MWhYour data
Methane leaks, base case
2 %Assumption
Main product, conservative – optimistic
650 – 2,800 MWhCalculated

Season: how much the digester takes for itself

In January heating the digester needs heat equal to 42 % of that month’s methane energy, in July 41 %.

January: methane energy 570 MWh · digester heating 240 MWh (42 %) · heat for a user 16 MWh

  • Methane energy of the month
  • Digester heating
  • Heat for a user

How it works: from feedstock to products

Heat produced (gross)
3,039 MWh
Digester heat demand
2,788 MWh
Useful heat (economic)
201 MWh of 252
Power: own use / sold
2,407 / 0 MWh

Scores by dimension

No single magic number. The overall score comes with its explanation.

Feedstock fit
94/100
  • Energy equivalent ≈ 360 kWe (scale score 90/100)
  • Process-specific inlet basis; no generic feedstock energy-density score.
  • Feedstock available 12 of 12 months
Energy fit
98/100
  • Own consumption absorbs 100 % of the electricity produced
  • Useful heat 201 MWh of 252 MWh available after digester needs
Location & logistics
100/100
  • Land for digestate unknown
Technical feasibility
100/100
  • Standard layout for this scale, no critical obstacles
Economics
92/100
  • Base-case simple payback ≈ 5.1 years
  • NPV positive even in the conservative case
Regulatory complexity
0/100 risk
  • Number and weight of permitting / regulatory steps: 5 points (more = harder)
Environmental risk
24/100 risk
  • Expected methane loss 2.5 % (good practice ≤ 2 %)
  • Unknown where the digestate will go
Overall project viability
94/100
  • Weighted: economics 30 %, feedstock 20 %, energy 15 %, technical 10 %, location 10 %, regulatory 7.5 %, environment 7.5 %.
  • Strongest: Location & logistics (100); weakest: Environmental risk (76).

Calculation details

Industrial wastewater

Leave unknown costs and auxiliary loads blank. Economics require these inputs.

COD in
2,732,400 kg COD/a
COD out
491,832 kg COD/a
COD → X
179,245 kg COD/a
COD → CH₄
2,061,320 kg COD/a
m sludge (wet)
3,155.73 t/a
m in
594,000 t/a
m gas
1,280.45 t/a
m out
589,564 t/a
V
450 m³
HRT
0.25 d
OLR
18.4 kg COD/m³/d
COD out
834.23 mg COD/L
CH₄ → CHP / Upgrading / Boiler
682,795 Nm³ CH₄/a
CH₄ loss
35,936.6 Nm³ CH₄/a
CH₄ total
718,732 Nm³ CH₄/a
m residual
3,155.73 t/a

Enter the project budget for the upstream process, including pretreatment, logistics, storage and final treatment. Gas conversion equipment and energy are calculated separately. Enter zero only for a confirmed zero cost. Exclude from this budget; calculated separately: residuals disposal cost, biogas purchase price.

Technology & digester

COD / UASB–EGSB

Working volume
≈ 450 m³
Retention time
0.3 days

    Climate: Ontario (Guelph), mean 8.4 °C, ≈ 3,694 heating degree-days. Closest climate analogues: Vilnius (LT) (Δ 1.9 °C), Rzeszów (PL) (Δ 2.1 °C), Kraków (PL) (Δ 2.4 °C).

    Monthly energy balance

    Base case, chosen route. Gas energy is usable methane energy (LHV) after losses.

    MonthFeedstock, tGas energy, MWhDigester heat, MWhUseful heat, MWhNet electricity, MWh
    Jan50,41556923816204
    Feb45,94351921715186
    Mar50,41556923717204
    Apr48,78955122916198
    May50,41556923617204
    Jun48,78955122817198
    Jul50,41556923518204
    Aug50,41556923518204
    Sept48,78955122817198
    Oct50,41556923617204
    Nov48,78955122916198
    Dec50,41556923816204
    Σ594,0006,7052,7882012,407
    CAPEX, OPEX, revenue (base case)
    CAPEX (USD)
    Industrial wastewater2.7M
    Gas handling and cleaning47K
    CHP (power + heat)640K
    Heat network72K
    Backup boiler19K
    Electrical systems and controls47K
    Pipework31K
    Civil works47K
    Grid connection42K
    Engineering and permits75K
    Contingency100K
    Total3.8M
    OPEX / yr (USD)
    Staff48K
    CHP service and overhaul reserve50K
    Maintenance9.6K
    Insurance19K
    Testing and monitoring5.6K
    OPEX110K
    Residuals disposal cost100K
    Total340K
    Revenue + savings / yr (USD)
    Electricity self-consumption savings240K
    Useful heat (economic)4.2K
    Avoided treatment charge840K
    Total1.1M

    Unit costs are estimates. Replace them with supplier quotations.

    Digestate and residues

    Excess sludge ≈ 3,156 t/yr (wet); effluent ≈ 834 mg COD/L goes on to final treatment. Confirm the discharge limit and the sludge route.

    Methane losses & climate

    Expected losses: 2.5 % of methane produced (range 1.6 % – 3.5 %) ≈ 328 t CO₂e/yr; fossil emissions displaced ≈ 216 t CO₂/yr. Losses vs benefit: 152 %.

    Methane not captured by the project: ≈ 35,937 Nm³ CH₄/yr. It is outside the plant loss figure above.

    • Methane losses could cancel the climate benefit. Do not claim emission reductions without measurements.
    • Expected loss 2.5 % is above good practice (2 %): budget for monitoring.
    • Gas-tight covers on the digester and digestate storage (incl. lagoon covers) — the single most important measure.
    • Leak detection and repair (LDAR): optical gas imaging or tracer method at least yearly, plus an acceptance test after construction.
    • Continuous gas-holder pressure monitoring; a standby flare instead of venting.
    • CHP with an oxidation catalyst and tuning regime to cut methane slip.

    Avoided emissions from open manure storage are not credited (conservative).

    Permits & regulation (indicative)

    Complexity: lower. “To verify” means a local lawyer or engineer must confirm the item during the feasibility study.

    • Provincial environmental approval (e.g. Ontario ECA / O.Reg 267/03 for on-farm AD)
      New installation · effort: medium · to verify
    • Confirm discharge limits, final polishing and sludge disposal authorisations
      Process-specific site conditions; no automatic legal eligibility · effort: high · to verify
    Safety (risk register)
    • Methane: explosion and fire (flammable range ≈ 5–15 % in air) high
      • Hazardous-area (ATEX/IECEx or national) zoning and suitably rated equipment
      • Fixed gas detectors in the CHP room and near tanks
      • Flame arresters, over/under-pressure relief, safety flare
      • Ignition-source control and hot-work permits
    • Hydrogen sulphide (H₂S): acute toxicity, corrosion high
      • Biological / chemical desulphurisation of the biogas
      • Personal H₂S monitors, no lone working
      • H₂S monitoring upstream of the CHP (engine protection)
    • Confined spaces (digester, storage, pits): asphyxiation, toxic gases high
      • Entry only under permit, ventilation, standby person
      • Self-contained breathing apparatus for rescue
    • Over/under-pressure: membrane roof rupture, tank deformation medium
      • Liquid seals / relief valves venting to a safe location
      • Gas-holder level and pressure sensors
    • CHP: carbon monoxide, fire, high temperatures medium
      • CHP room ventilation, CO detectors
      • Emergency stop, fire suppression
    • Soil and water pollution: slurry/digestate spills, lagoon overflow high
      • Bund sized for the largest tank
      • Level sensors and a spill-response plan
      • Digestate storage covering the closed spreading season

    Software does NOT replace a qualified process engineer and a process-safety engineer. Every final engineering design, hazardous-area classification and safe-operation programme must pass human professional review.

    Assumptions used (103)

    Every number has a source, date, country and confidence, and is tagged FACT / ASSUMPTION / CALCULATION / ESTIMATE. Full register: →

    • Support: The RNG business case is utility offtake negotiated under regulated price caps (Québec ≤ 35 $2022/GJ per contract, BC ≤ $31/GJ from 2021/22, CPI-indexed); Clean Fuel Regulations credits and the Clean Technology ITC are uncertain extras. No electricity feed-in tariff.
    • Cold winters and low power prices: RNG contracts are usually the business case.
    • The verdict excludes subsidies; national support is shown as separate cases.
    • This is a preliminary (screening) assessment — not a detailed engineering design and not a commercial offer.
    • Financial results are pre-tax project cash flows. Depreciation, income taxes, working capital, financing fees and detailed debt covenants are not modelled; DSCR is an EBITDA-based screening ratio, not lender CFADS.
    • Parameter bounds are tested individually using the applicable market/CAPEX evidence. These engineering or tariff ranges are not statistical confidence intervals and do not replace supplier quotations or customer bills.

    Illustrative project assumptions, not an operator account or supplier quotation; avoided surcharge from the Hamilton 2026 sewer discharge permit rates (BOD CAD 0.89/kg)

    • Operating days: 330 d/a · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · CA
    • Active months: 12 1–12 · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · CA
    • Starting month: 1 1–12 · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · CA
    • CAPEX: 3,800,000 CAD · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · CA
    • OPEX: 150,000 CAD/a · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · CA
    • Residuals disposal cost: 45 CAD/t · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · CA
    • Upstream electricity use: 180,000 kWh/a · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · CA
    • Additional process heat: 0 kWh_th/a · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · CA
    • Scenario uncertainty: 30 % · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · CA
    • Q: 1,800 m³/d · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · CA
    • COD: 4,600 mg COD/L · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · CA
    • COD removal: 82 % COD · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · CA
    • CH₄: 65 % vol · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · CA
    • Methane capture: 95 % CH₄ · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · CA
    • Removed COD to biomass: 8 % COD · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · CA
    • Sludge dry solids: 5 % TS · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · CA
    • VS / TS: 80 % VS/TS · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · CA
    • HRT: 0.25 d · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · CA
    • OLR: 19.8 kg/(m³·d) · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · CA
    • Inlet temperature: 25 °C · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · CA
    • Heat recovery: 60 % · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · CA
    • Avoided treatment charge: 2 CAD/m³ · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · CA
    • Methane COD equivalent: 4 kg COD/kg CH₄ · ENGINEERING_ASSUMPTION · HIGH · 2019-01-01 · GLOBAL · https://www.ipcc-nggip.iges.or.jp/public/2019rf/pdf/5_Volume5/19R_V5_6_Ch06_Wastewater.pdf
    • Biomass COD/VSS: 1.42 kg COD/kg VSS · ENGINEERING_ASSUMPTION · LOW · 2026-10-28 · GLOBAL

    What could break the economics

    Each stress test applied to the base case on its own.

    chp: local CAPEX factor
    0.637 … 1.183 —
    NPV low…high: US$3.9M … US$4.7M
    Discount rate (nominal, pre-tax, EUR-equivalent, incl. country risk)
    0.05 … 0.08 —
    NPV low…high: US$3.3M … US$4.9M
    Business electricity reference, excl. VAT (default if the customer gives none)
    0.05666 … 0.1227 USD/kWh
    NPV low…high: US$2.7M … US$4.4M
    Share of the bill actually avoided by self-generation
    0.7 … 1 —
    NPV low…high: US$3.8M … US$4.8M
    COD
    3,220 … 5,980
    NPV low…high: US$3.8M … US$4.4M
    COD removal
    57.4 … 99
    NPV low…high: US$3.8M … US$4.4M
    Avoided treatment charge
    1.4 … 2.6
    NPV low…high: US$1.5M … US$7.1M
    OPEX
    105,000 … 195,000
    NPV low…high: US$3.9M … US$4.7M
    Residuals disposal cost
    31.5 … 58.5
    NPV low…high: US$4M … US$4.6M
    Every number has a source, date, country and confidence, and is tagged FACT / ASSUMPTION / CALCULATION / ESTIMATE. Full register:
    Biomethane price without support, base: 0.2798 USD/Nm³ · CALCULATED_VALUE · LOW
    National estimate (project team, 2026-10) — no official series found for this item; your own price overrides it; local market for biomethane / RNG without credits
    WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
    chp: local CAPEX factor: 0.91 — · CALCULATED_VALUE · MEDIUM
    0.72 traded equipment + 0.28 × local/German labour cost (21.3/31.5 €/h); split after DBFZ/Fraunhofer 2024; supplier quotes needed
    ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
    Debt interest rate (EUR-equivalent): 0.045 — · CALCULATED_VALUE · MEDIUM
    Discount rate − 1.5 pp (senior debt is cheaper than blended project capital); consistent with ECB MIR corporate loan rates + project margin; a bank term sheet replaces this
    WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
    Debt share for DSCR test: 0.65 — · ENGINEERING_ASSUMPTION · MEDIUM
    Typical agri / project lending (KfW, EBRD, IFC practice)
    ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
    Debt tenor: 10 a · ENGINEERING_ASSUMPTION · MEDIUM
    Typical
    ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
    Discount rate (nominal, pre-tax, EUR-equivalent, incl. country risk): 0.06 — · CALCULATED_VALUE · MEDIUM
    Nominal, pre-tax, EUR-equivalent: 6.0 % mature-market WACC + 0.6 × country risk premium 0.00 % (Aaa; Damodaran, 2026-07); not a bank offer
    2026-07-01 · checked 2026-10-27 · Rating-based CRP; baseline WACC and lambda are engineering/financial assumptions
    WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
    Business electricity reference, excl. VAT (default if the customer gives none): 0.1177 USD/kWh · CALCULATED_VALUE · MEDIUM
    Hydro-Québec, Comparison of Electricity Prices in Major North American Cities 2025 (rates 1 Apr 2025, excl. taxes), 500 kW and 200 MWh/month; provinces with two cities averaged; Ontario with Global Adjustment Class B. Territories computed from ATCO Electric Yukon, Naka Power and Qulliq Energy tariffs (2025–2026). National value: mean of five cities + 8 %. Regional reference: CA.08. Monthly bill ÷ monthly kWh, CAD/kWh. Converted at 1.5785 CAD/EUR (2026-11-09).
    2025-04-01 · checked 2026-10-30 · Hydro-Québec, Comparison of Electricity Prices in Major North American Cities 2025 (rates 1 Apr 2025, excl. taxes), 500 kW and 200 MWh/month; provinces with two cities averaged; Ontario with Global Adjustment Class B. Territories computed from ATCO Electric Yukon, Naka Power and Qulliq Energy tariffs (2025–2026). National value: mean of five cities + 8 %. Regional reference: CA.08.
    REVIEW_REQUIRED: Observation is 587 days old; exceeds the 400-day review policy
    FX (2026-11-09): 1.579 CAD/EUR (MARKET_DATA); Published local tariff: 0.166 CAD/kWh (MARKET_DATA)
    Wholesale electricity price (market average): 0.02487 USD/kWh · CALCULATED_VALUE · MEDIUM
    AESO pool price, hourly time-weighted mean Oct 2025 – Sep 2026: CAD 35.07/MWh (Alberta; other provinces have no market); converted at 1.5785 CAD/EUR (2026-11-09)
    2026-09-30 · checked undated · Historical national/regional reference; latest publication and customer applicability require verification
    WITHIN_REVIEW_WINDOW: Within the 60-day review policy; applicability and latest publication must still be checked
    Documented nominal reference (may include estimated adders): 0.03507 CAD (ENGINEERING_ASSUMPTION); FX (2026-11-09): 1.579 CAD/EUR (MARKET_DATA)
    Annual escalation of energy prices (nominal EUR): 0.02 — · ENGINEERING_ASSUMPTION · MEDIUM
    At the ECB/Fed inflation target — no real energy-price growth assumed (conservative)
    ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
    Share of the wholesale price realised for surplus power: 0.85 — · ENGINEERING_ASSUMPTION · MEDIUM
    15 % profile & balancing discount for a small seller (assumption, same for all markets)
    ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
    Exchange rate: 1.41 CAD/USD · MARKET_DATA · HIGH
    Official EUR reference rate, 2026-11-09
    2026-11-09 · checked 2026-11-10 · CAD per EUR; dated reference, not a guaranteed transaction rate
    WITHIN_REVIEW_WINDOW: Within the 7-day review policy; applicability and latest publication must still be checked
    Value of useful heat (displaced gas / boiler efficiency): 0.02087 USD/kWh th · CALCULATED_VALUE · MEDIUM
    Business gas 16.784755680776218 €/MWh LHV ÷ 0.9
    2026-10-01 · checked undated · Historical national/regional reference; latest publication and customer applicability require verification
    WITHIN_REVIEW_WINDOW: Within the 400-day review policy; applicability and latest publication must still be checked
    Documented nominal reference (may include estimated adders): 23.87 CAD (ENGINEERING_ASSUMPTION); FX (2026-11-09): 1.579 CAD/EUR (MARKET_DATA)
    Evaluation horizon: 15 a · ENGINEERING_ASSUMPTION · MEDIUM
    Shorter than the 20-year technical life — conservative
    ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
    Official hourly labour cost, economy-wide (wages + employer costs): 34.11 USD/h · CALCULATED_VALUE · MEDIUM
    Statistics Canada LFS average hourly wage 2024 CAD 35.20 × 1.035 (2025) × 1.10 paid/worked × 1.20 employer costs = CAD 48.1/h; converted at 1.5785 CAD/EUR (2026-11-09)
    2025-12-31 · checked undated · Historical national/regional reference; latest publication and customer applicability require verification
    WITHIN_REVIEW_WINDOW: Within the 730-day review policy; applicability and latest publication must still be checked
    Documented nominal reference (may include estimated adders): 48.1 CAD (ENGINEERING_ASSUMPTION); FX (2026-11-09): 1.579 CAD/EUR (MARKET_DATA)
    Plant operator wage relative to the economy-wide average: 0.9103 — · CALCULATED_VALUE · MEDIUM
    0.7 national operator ratio × 1.3005 regional wage relative for CA.08 (Job Bank NOC 92101 water and waste treatment plant operators, median wage by province (Nov 2025) × StatCan 36-10-0205 employer contributions ÷ CAD 48.1/h ÷ 0.7)
    WITHIN_REVIEW_WINDOW: Within the 730-day review policy; applicability and latest publication must still be checked
    Annual escalation of operating costs (nominal EUR): 0.025 — · ENGINEERING_ASSUMPTION · MEDIUM
    Inflation target + 0.5 pp wage drift
    ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity
    Share of the bill actually avoided by self-generation: 0.85 — · ENGINEERING_ASSUMPTION · MEDIUM
    TOU reference: energy/Ft portion only, demand/service charges retained. Else 85% engineering allowance. User invoice uses the generic allowance until its energy/demand split is known.
    ASSUMPTION: Engineering estimate or reconstructed cost; a recent review date does not establish current market validity